Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 0, Cited by 0] [Section 2(1)] [Section 2] [Entire Act]

State of Himachal Pradesh - Subsection

Section 2(1)(g) in Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017

(g)["Date of commencement of operation of the project/Commercial operation date of the project/COD of the project"] [Substituted 'Date of commencement of operation of the project' by Notification No. No. HPERC/428, dated 28.1.2019.] means the date on which the first unit of the project is synchronized with the grid for the first time;