State of Himachal Pradesh - Subsection

Section 17(2) in Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017

(2)[ Where, prior to commencement of Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017-
(a)any part of the original capacity as well as that of the additional capacity has been synchronized with the grid at least once; or
(b)joint petition(s) for the approval, whether under the REC mechanism or on long term basis, of PPA(s) in relation to the original capacity as well as of the supplementary PPA in relation to additional/enhanced capacity, has/have been filed before the Commission; or
(c)PPA(s), or the supplementary PPA, whether under the REC mechanism or on long term basis, for purchase of net saleable energy from the original capacity and the additional capacity or the enhanced capacity has/have been signed by the concerned developer with Distribution Licensee;
the tariff(s) for the original capacity and the additional capacity, or the composite rate for the enhanced capacity as the case may be, and the associated conditions for each of such tariffs, shall be regulated as per the provisions of Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012.