Section 35 in Karnataka Town and Country Planning Act, 1961

35. Restrictions after declaration to make a scheme.

(1)On or after the date on which the Planning Authority's declaration of intention to make a scheme under section 29 or the notification issued by the State Government under section 31 is published,-
(a)no person shall within the area included in the scheme erect or proceed with any building work or remove, pull down, alter, make additions to, or make any substantial repair to any building, part of a building, a compound wall or any drainage work or remove any earth, stone or material, or sub-divide any land or change the user of any land or building unless such person has applied for and obtained necessary permission which shall be contained in a commencement certificate granted by the Planning Authority in the form prescribed;
(b)the Planning Authority on receipt of such application shall at once furnish the applicant with a written acknowledgment of its receipt and may, after inquiry and in consultation with the Director, either grant or refuse such certificate or grant it subject to such conditions as the Planning Authority may, with the previous approval of the Director, think fit to impose if the Planning Authority communicates no decision to the applicant within three months from the date of such acknowledgment, the applicant shall be deemed to have been granted such certificate;
(c)if any person contravenes the provisions contained in clause (a) or clause (b), the Planning Authority may direct such person by notice in writing to stop any work in progress, and after making inquiry in the prescribed manner, remove, pull down, or alter any building or other work or restore the land in respect of which such contravention is made to its original condition;
(d)any expenses incurred by the Planning Authority under clause (c) shall be a sum due to such authority under this Act from the person in default or the owner of the plot.
(2)No person shall be entitled to compensation in respect of any damage, loss or injury resulting from any action taken by the Planning Authority under sub-section (1) except in respect of a building or work begun or a contract entered into before the date on which the Planning Authority published a declaration of intention to make a scheme under section 29 or the State Government published a notification under section 31 and only in so far as such building or work has proceeded at the time of the publication of such declaration or notification:Provided that such claim to compensation in the excepted cases shall be subject to the conditions of any agreement entered into between such person and the Planning Authority.
(3)Where under clause (j) of sub-section (2) of section 26 or under a draft scheme under section 32,-
(a)the purpose to which any plot of land may not be used has been specified, such plot of land shall, within such period of not less than one year as may be specified in the final scheme, cease to be used for such purpose and shall be used only for the purposes specified in the Scheme;
(b)the purpose to which any existing building may not be used has been specified, such building shall, within such period of not less than three years as may be specified in the scheme, cease to be used for the purpose other than the purpose specified in the scheme;
(c)the purpose to which any plot of land with existing buildings may not be used has been specified in the scheme and the existence of such buildings is inconsistent with the provisions of the scheme, such buildings shall, within such period of not less than ten years as may be specified in the scheme cease to exist:
Provided that such period shall not be less than the reasonable life of the building;No compensation shall be payable for any plot of land or building adversely affected by the making of town planning scheme.
(4)Any person aggrieved by the decision of the Planning Authority under this section may, within sixty days from the date of the decision, appeal to the prescribed authority or if no authority has been prescribed, to the State Government and the order of such prescribed authority or State Government in appeal shall be final.
(5)The restrictions imposed by sub-sections (1) and (2) shall cease to operate in the event of the State Government refusing to sanction the draft scheme or the final scheme.