[Cites 0, Cited by 0] [Section 14] [Entire Act]

Union of India - Subsection

Section 14(5) in Central Electricity Regulatory Commission (Cross Border Trade of Electricity) Regulations, 2019

(5)In the event of delay by the transmission licensee in commissioning of transmission system within India beyond its scheduled date and the generating company is ready with its generating station or unit(s), the transmission licensee shall pay transmission charges to generating company proportionate to commissioned generation capacity in case no alternative arrangement is made by the CTU.Provided that in case of non-payment of transmission charges by the transmission licensee to the generating company, such charges shall be recovered by the CTU from the Contract Performance Guarantee furnished by the transmission licensee and paid to the generating company.