State of Maharashtra - Section

Section 353B in The Mumbai Municipal Corporation Act, 1888

353B. [ Structures Stability Certificate. [Section 353B inserted by Maharashtra 6 of 2009, Section 2, dated 14-3-2009.]

(1)Every owner or occupier of a building in respect of which a period of thirty years, from the date of -
(i)issue of its completion certificate by the Corporation; or
(ii)issue of permission of occupy a building under section 353A; or
(iii)its physical occupation of at least 50 per cent of its built-up area,
whichever is earlier, has expired, shall cause such building to be examined by a Structural Engineer registered with the Corporation for the purposes of certifying that the building is fit for human habitation (such certificate hereinafter referred to as "the Structural Stability Certificate"). The Structural Stability Certificate issued by such Structural Engineer shall be submitted to the Commissioner.
(2)The Structural Stability Certificate shall be submitted within one year from the expiry of a period of thirty years referred to in sub-section (1), and every ten years thereafter or such earlier period as the Commissioner may determine having regard to the condition of the building and the corrective repairs carried out by the owner or occupier.
(3)Notwithstanding anything contained in sub-section (1), the Commissioner may, at any time, after having recorded the reasons, in writing, direct the owner or occupier of a building, to cause such building to be examined by such Structural Engineer and to submit to the Commissioner, the Structural Stability Certificate, as required under sub-section (1), within the period not exceeding thirty days as specified by the Commissioner, in such direction.
(4)If the Structural Engineer recommends any corrective repairs for securing the structural stability of the building, such corrective repairs shall be carried out by the owner or occupier of a building to the satisfaction of the Commissioner.
(5)Any owner or occupier, as the case may be, who fails to carry out corrective repairs for securing structural stability, within a period of six months from the date of report of the Structural Engineer, shall be punished with the fine as provided in section 471.
(6)Notwithstanding anything contained in sub-section (5), the Commissioner may, after giving the owner or occupier, a notice in writing, require him to carry out, within the period specified in the notice, corrective repairs for securing structural stability of a building. If the owner or occupier fails to carry out such corrective repairs within the period specified in the notice, the Commissioner may carry out the same and the expenses incurred by the Commissioner on such repairs shall, on demand if not paid within thirty days, be recovered from the owner or occupier as arrears of property tax.
(7)If there is any dispute about the amount of expenses for which demand is made under sub-section (6), an appeal may be preferred to the Chief Judge of the Small Causes Court, but no such appeal shall be entertained by the said Chief Judge, unless -
(i)it is preferred within twenty-one days from the date of receipt of notice of such demand;
(ii)the amount for which demand is made is deposited. with the Corporation and a true copy of the receipt showing that the amount has been so deposited accompanies the appeal.
(8)In case the appeal is decided in favour of the appellant and the amount of expenses deposited with the Corporation is more than the amount payable by the appellant, the Commissioner shall adjust the excess amount with interest at 6.25 per cent per annum from the date on which the amount is so deposited by the appellant, towards the property tax payable by the owner in respect of such building thereafter.]Dangerous Structures