Union of India - Subsection

Section 13(2) in Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009

(2)Based on the system studies, the nodal agency shall specify the inter-State transmission system that would be required to give long-term access. In case augmentation to the existing inter-State Transmission system is required, the same will be intimated to the applicant.[***] [Deleted '(3)' by Notification No. L-1/(3)/2009-CERC, dated 9.1.2019 (w.e.f. 7.7.2009).]