Union of India - Section

Section 6 in Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2014

6. Declaration, scheduling and elimination of gaming.

(1)The provisions of the Grid Code and the Central Electricity Regulatory Commission (Open Access in inter- State Transmission) Regulations, 2008, as amended from time to time, shall be applicable for declaration of capacity, scheduling and elimination of gaming.
(2)The generating station, as far as possible, shall generate electricity as per the day-ahead generation schedule finalized by the Regional Load Despatch Centre in accordance with the Grid Code:Provided that the revision in generation schedule on the day of operation shall be permitted, in accordance with the procedure specified under the Grid Code and Central Electricity Regulatory Commission (Open Access in inter-State Transmission) Regulations, 2008, as the case may be.
(3)The Commission, either suo motu or on a petition made by RLDC, or any affected party, may initiate proceedings against any generating company or seller on charges of gaming and if required, may order an inquiry in such manner as decided by the Commission. When the charge of gaming is established in the above inquiry, the Commission may, without prejudice to any other action under the Act or regulations thereunder, disallow any Charges for Deviation received by such generating company or the seller during the period of such gaming."