[Cites 0, Cited by 0] [Section 12] [Entire Act]

State of Punjab - Subsection

Section 12(5) in Punjab State Electricity Regulatory Commission (Open Access) Regulations, 2005

(5)If, in the opinion of the State Transmission Utility, further system strengthening is essential before providing long-term access, the applicant may request the State Transmission Utility to carry out system studies and preliminary investigation for the purpose of cost estimate and completion schedule for system strengthening;