State of Punjab - Act
Punjab State Electricity Regulatory Commission (Open Access) Regulations, 2005
PUNJAB
India
India
Punjab State Electricity Regulatory Commission (Open Access) Regulations, 2005
Rule PUNJAB-STATE-ELECTRICITY-REGULATORY-COMMISSION-OPEN-ACCESS-REGULATIONS-2005 of 2005
- Published on 9 August 2005
- Commenced on 9 August 2005
- [This is the version of this document from 9 August 2005.]
- [Note: The original publication document is not available and this content could not be verified.]
1. Short title and commencement.
2. Definitions.
- In these Regulations, unless the context otherwise requires -3. Extent of Application.
- These Regulations shall apply to Open Access for use of intra-State transmission system and/or the distribution system of licensees in the State, including when such systems are used in conjunction with inter-State transmission system.Note. - A consumer/person whose premises are situated within the area of supply of a distribution licensee, seeking to receive supply from a person other than the distribution licensee of his area of supply; a generating company (including captive generating plant) or licensee seeking to supply to a consumer/person in the State, would need to apply for Open Access under these Regulations.4. Eligibility for Open Access and Conditions to be satisfied.
5. Special Provisions for existing distribution licensees.
6. Provisions for existing consumers and generating companies availing Open Access.
7. Categorisation of Open Access Customers.
- Subject to the provisions of Regulations 5 and 6, the Open Access customers shall be classified into the following categories :-8. Criteria for allowing Open Access.
9. Allotment Priority.
- The priority for allowing Open Access shall be decided on the following criteria :10. Nodal Agency.
11. Issue of Guidelines.
- The State Transmission Utility and the State Load Despatch Center shall develop guidelines, procedures and application forms for applying for long-term and short-term Open Access respectively within 90 days of notification of these Regulations and submit the same to the Commission for approval.12. Procedure for Long term Open Access.
13. Procedure for Short-term Open Access Customer.
| S. No. | Term of Open Access | Maximum Processing time |
| 1. | Upto one day | 12 hours |
| 2. | Upto seven days | Two days |
| 3. | Upto thirty days | Seven days |
| 4. | Upto one hundred and eighty days | Fifteen days |
| 5. | Upto one year | Thirty days |
14. Open Access Agreement.
15. Non-utilisation of Open Access Capacity.
16. Charges for Open Access.
17. Surcharge.
18. Additional Surcharge.
19. Metering.
20. Communicating facility.
21. Operating charges.
22. Unscheduled interchange pricing.
- The entitlement at the drawal point shall be worked out after considering the Transmission and Distribution losses.The mismatch between the injection and overdrawal for any block of time shall be met from the grid and shall be governed by UI charges (As notified by CERC, from time to time) or applicable tariff for that category, at that point of time, whichever is higher. However, mismatch would be calibrated by loading the T&D losses before working out the UI charges.In the event of under-drawal by the Open Assess customer for any block of time, the same shall be governed by applicable UI charges or applicable tariff for the category, at that point of time, whichever is lower.23. Reactive Energy Charges.
- The payment for the reactive energy charges for the Open Access customers shall be calculated in accordance with appropriate Regulations.24. Energy losses.
- The transmission and distribution losses for the Intra- State System shall be determined by the Commission in their Tarrif Order for the applicable year and shall be apportioned in proportion to the actual energy drawal by the Open Access customers. The energy losses shall be compensated by additional injection at the injection point(s).The Open Access customers shall be required to bear one half (50%) of the aggregate of transmission and distribution losses determined by the Commission.25. Other Commercial Conditions.
- As a payment security towards charges, a deposit equal to 2 months of the average billing of that charge only on the basis of agreed capacity shall be maintained with each of the relevant agency, namely, State Transmission Utility, any other transmission licensee, distribution licensee and State Load Despatch Centre.26. Compliance with Grid Discipline.
- The Open Access customer shall abide by the Indian Electricity Grid Code, the State Gride Code and instructions given by State Transmission Utility and State Load Despatch Centre as applicable from time to time.27. Collection and Disbursement of charges.
28. Phasing of open Access.
| Sr. No. | Phase | Category of consumers | Open Access to be allowed before or on |
| 1. | Phase I | Consumers with demand of 15 MW and above | January 1, 2006 |
| 2. | Phase II | Consumers with demand of 3 MW and above | April 1, 2006 |
| 3. | Phase III | Consumers with demand of 1 MW and above | April 1, 2006 |