Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 23, Cited by 0]

Bombay High Court

Felguera Gruas India Private Limited vs Tuticorin Coal Terminal Private ... on 10 April, 2018

Author: Naresh H. Patil

Bench: Naresh H. Patil, Nitin W. Sambre

                                    1/44                                          comapl 20-25.18.sxw


         IN THE HIGH COURT OF JUDICATURE AT BOMBAY
               ORDINARY ORIGINAL CIVIL JURISDICTION

                   COMMERCIAL APPEAL (L) NO. 20 OF 2018
                                    IN
                    ARBITRATION PETITION (L) NO.369 OF 2016
                                   WITH
                      NOTICE OF MOTION (L) NO. 33 OF 2018
                                   WITH
                   COMMERCIAL APPEAL (L) NO. 21 OF 2018
                                    IN
                    ARBITRATION PETITION (L) NO.370 OF 2016
                                   WITH
                      NOTICE OF MOTION (L) NO. 31 OF 2018
                                   WITH
                   COMMERCIAL APPEAL (L) NO. 22 OF 2018
                                    IN
                    ARBITRATION PETITION (L) NO.367 OF 2016
                                   WITH
                      NOTICE OF MOTION (L) NO. 32 OF 2018
                                   WITH
                   COMMERCIAL APPEAL (L) NO. 23 OF 2018
                                    IN
                    ARBITRATION PETITION (L) NO.368 OF 2016
                                   WITH
                      NOTICE OF MOTION (L) NO. 34 OF 2018
                                   WITH
                   COMMERCIAL APPEAL (L) NO. 24 OF 2018
                                    IN
                    ARBITRATION PETITION (L) NO.371 OF 2016
                                   WITH
                      NOTICE OF MOTION (L) NO. 35 OF 2018
                                   WITH
                   COMMERCIAL APPEAL (L) NO. 25 OF 2018
                                    IN
                    ARBITRATION PETITION (L) NO.366 OF 2016




::: Uploaded on - 12/04/2018                       ::: Downloaded on - 13/04/2018 02:03:26 :::
                                         2/44                                          comapl 20-25.18.sxw


                                     WITH
                        NOTICE OF MOTION (L) NO. 30 OF 2018


 Felguera Gruas India Private Limited 
 Door No.10-50-24/A, 3rd and 4th floor,
 Opp. HSCB Call Center, Siripuram Junction,
 Vishakhapatnam-530003, Andhra Pradesh,
 Through Mr. Nandan Kumar,
 Senior Manager-Legal & Company Secretary                          .. Appellants

                               Vs.

 Tuticorin Coal Terminal Private Limited
 #3, C Wing 2nd floor, Amerchand Mansion,
 16, Madame Cama Road,
 Colaba, Mumbai 400039.

 2. Barclays Bank PLC
 1st floor, Eros Corporate Tower,
 Nehru Palace, New Delhi - 110019.

 3. Hong Kong & Shanghai Banking
 Corporation Limited,
 6-3-1107 & 1108, Raj Bhavan Road,
 Somajiguda Hyderabad - 500 082.                                      .. Respondents


 Mr.Darius Khambata,Senior Advocate a/w Mr. Zal Andhyarujina, 
 Mr.  Sanjeev   Sharma,   Ms.  Mumtaz   Bhalla,  Mr.  Praveer   Shetty, 
 Mr. Anirudh Gandhi i/by RES Legal for appellants.

 Mr. Aspi Chinoy, Senior Advocate a/w Mr. Chirag Kamdar, Mr. 
 Ranjit   Shetty,   Mr.   Nishit   Tanna,   Ms.   Vatsala   Pant   i/by   Argus 
 Partners for respondent no.1 in COMAPL/20/2018.




::: Uploaded on - 12/04/2018                           ::: Downloaded on - 13/04/2018 02:03:26 :::
                                              3/44                                          comapl 20-25.18.sxw


 Mr. Mustafa Doctor, Senior Advocate aw Mr. Chirag Kamdar, Mr. 
 Ranjit   Shetty,   Mr.   Nishit   Tanna,   Ms.   Vatsala   Pant   i/by   Argus 
 Partners for respondent no.1 in COMAPL/21, 22, 23, 24 and 25 of 
 2018.

 Mr. Parikshit Desai for respondent no.2 in COMAPL/21, 22, 23, 
 24 and 25 of 2018.

                               CORAM:   NARESH H. PATIL &
                                                 NITIN W. SAMBRE,JJ.          
             RESERVED ON           :  23rd  February, 2018
            PRONOUNCED  ON     : 10th April, 2018.

 JUDGMENT [ Per Naresh H. Patil, J.] :


These appeals arise out of judgment and order passed by the learned Single Judge on 11th January,2018. As issues involved in these appeals are similar, by consent the appeals are heard finally at admission stage and are being disposed of accordingly.

2. The appellants M/s.Felguera Gruas India Private Limited (hereinafter referred to as 'FGIPL' for short) preferred Arbitration Petition under Section 9 of the Arbitration and Conciliation Act, 1996 (for short referred to as 'the Act') praying for interim injunction against encashment of the Advance/Down Payment Bank Guarantees ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:26 ::: 4/44 comapl 20-25.18.sxw and Performance Bank Guarantees which were furnished by the FGIPL to the Respondent No.1 - Tuticorin Coal Terminal Pvt. Ltd. (hereinafter referred to as "TCTPL" for short). These guarantees were furnished consequent to six purchase orders. The particulars of subject Bank Guarantees and Purchase orders are set out in the judgment delivered by the learned Single Judge. FGIPL is a Company incorporated under the provisions of the Companies Act, 1956. The company is in the business of undertaking turn key projects across the country. It offers end to end services in design, testing, commissioning, manufacturing, sourcing, supply and construction. It has executed several major projects in Ports.

3. TCTPL is a Private Company incorporated under the provisions of the Companies Act,1956. They entered into a Concession Agreement on 11th September, 2010 with the Board of Trustees for Tuticorin Port ("Concessioning Authority") for Development of North Cargo Berth-II (NCB-II) for handling bulk cargoes at Tuticorin Port on Design, Build, Finance, Operate and Transfer basis. This ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:26 ::: 5/44 comapl 20-25.18.sxw concessional agreement was operational for a period of 30 years. In the year 2012, FGIPL offered services to TCTPL for supplying as well as designing, erecting and commissioning of stacker-cum-reclaimers, stacker and conveyor system. A Letter of Intent was entered into accordingly. There were six purchase orders under the contract entered into between the parties. Each purchase order had clause for advance payment, down payment, bank guarantee and performance bank guarantee. FGIPL issued Down Payment Bank Guarantee and Performance Bank Guarantee in favour of TCTPL in respect of each Purchase Order. In the petition filed under Section 9 of the Act, FGIPL seeks injunction from invoking the guarantees mainly on the ground that they were conditional. The guarantees were worth Rs.43 Crores. An injunction against respondents 2 and 3 bank from releasing the amounts under the said Bank Guarantees, in favour of respondent no.1 is sought by the appellant. The grounds were that the guarantees were conditional and could be invoked if the appellants had defaulted in complying with their obligations under the Purchase Orders. There were special equities in favour of appellants. According ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:26 ::: 6/44 comapl 20-25.18.sxw to appellants the TCTPL had admitted in correspondence that Rs.32 Crores was payable to the appellants. It is the case of the appellants that irretrievable injustice and injury would be caused to the appellants if respondent no.1 was permitted to encash the bank guarantees. Respondent no.1 is a Special Purpose Vehicle which is making losses.

4. By an order dated 10th March, 2016 the appellants obtained ex parte order passed by the learned Single Judge in favour of the appellants in terms of prayer clauses (b) and( c) of the petition i.e. restraining Respondents 2 and 3, the two Banks from releasing the amounts under the Guarantees in favour of Respondent No.1 or anyone else.

5. We may reproduce the paragraphs 1 and 2 of the Advance Bank Guarantee and Performance Bank Guarantee as under:

ADVANCE BANK GUARANTEE "NOW THEREFORE IN CONSIDERATION OF THE FOREGOING PREMISES AND FOR OTHER GOOD AND ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:26 ::: 7/44 comapl 20-25.18.sxw VALUABLE CONSIDERATION, THE RECEIPT AND LEGAL SUFFICIENCY OF WHICH IS HEREBY ACKNOWLEDGED. THE GUARANTOR HEREBY ABSOLUTELY AND IRREVOCABLY AGREES FOR THE BENEFIT OF THE PURCHASER AS FOLLOWS:-
1. IF THE DELIVERY OBLIGATION IS NOT PERFORMED BY THE SELLER IN ACCORDANCE WITH THE TERMS OF THE PURCHASE ORDER, THE GUARANTOR SHALL WITHIN 7 (SEVEN) DAYS FROM THE RECEIPT OF A DEMAND BY THE PURCHASER PAY TO THE PURCHASER ANY SUM NOT EXCEEDING RS.17,000,000/- (RUPEES ONE CRORE SEVENTY LAKHS ONLY)"
2. THE OBLIGATION OF THE GUARANTOR UNDER THE GUARANTEE SHALL BE UNCONDITIONAL ABSOLUTE AND IRREVOCABLE IRRESPECTIVE OF THE GENUINENESS, VALIDITY, REGULARITY OR ENFORCEABILITY OF THE PURCHASE ORDER OR ANY OTHER CIRCUMSTANCE WHICH MIGHT OTHERWISE CONSTITUTE A LEGAL AND/OR EQUITABLE DISCHARGE OF A SURETY OR THE GUARANTOR UNDER THE LAW RELATING TO ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:26 ::: 8/44 comapl 20-25.18.sxw SURETIES, THE GUARANTOR SHALL NOT BE ENTITLED TO DISPUTE OR ENQUIRE INTO WHETHER THE PURCHASER HAS BECOME ENTITLED TO CLAIM THE SAID AMOUNT UNDER THE PURCHASE ORDER OR NOT OR WHETHER THE SUPPLIER HAS COMMITTED ANY BREACH OF THE PURCHASE ORDER AND/OR THE GENERAL TERMS AND CONDITIONS APPLICABLE THERETO OR NOT OR WHETHER THE PURCHASER IS ENTITLED TO RECOVER ANY DAMAGES FROM THE SUPPLIER FOR BREACH THEREOF OR NOT."

PERFORMANCE BANK GUARANTEE "NOW THEREFORE, IN CONSIDERATION OF THE FOREGOING PREMISES, THE GUARANTOR HEREBY ABSOLUTELY AND IRREVOCABLY AGREES FOR THE BENEFIT OF THE PURCHASER AS FOLLOWS:

1. IF THE SELLER EITHER FAILS TO PERFORM ANY OF ITS OBLIGATIONS UNDER THE PURCHASE ORDER OR BREACHES/VIOLATES ANY OF THE TERMS OF THE PURCHASE ORDER, THE GUARANTOR SHALL, WITHIN 7 (SEVEN) WORKING DAYS FROM THE DATE OF RECEIPT OF A WRITTEN DEMAND FROM THE PURCHASER, PAY TO THE ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:26 ::: 9/44 comapl 20-25.18.sxw PURCHASER ANY SUM NOT EXCEEDING RS.85,00,000 (RUPEES EIGHTY FIVE LAKH ONLY).
2. THE OBLIGATION OF THE GUARANTOR UNDER THIS GUARANTEE SHALL BE UNCONDITIONAL ABSOLUTE AND IRREVOCABLE, IRRESPECTIVE OF THE GENUINENESS, VALIDITY, REGULARITY OR ENFORCEABILITY OF THE PURCHASE ORDER OR ANY OTHER CIRCUMSTANCE WHICH MIGHT OTHERWISE CONSTITUTE TO A LEGAL/OR EQUITABLE DISCHARGE OF A SURETY OR THE GUARANTOR UNDER THE LAW RELATING TO SURETIES. THE GUARANTOR SHALL NOT BE ENTITLED TO DISPUTE OR ENQUIRE INTO WHETHER THE PURCHASER HAS BECOME ENTITLED TO CLAIM THE SAID AMOUNT UNDER THE PURCHASE ORDER OR NOT OR WHETHER THE SUPPLIER HAS COMMITTED ANY BREACH OF THE PURCHASE ORDER AND/OR THE GENERAL TERMS AND CONDITIONS APPLICABLE THERETO OR NOT OR WHETHER THE PURCHASER IS ENTITLED TO RECOVER ANY DAMAGES FROM THE SUPPLIER FOR BREACH THEREOF OR NOT."
::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:26 :::
10/44 comapl 20-25.18.sxw
6. Briefly stated, the grounds as reflected during the course of arguments and the written submissions filed on behalf of the appellants are as under:
It is submitted by the learned Senior Counsel Shri Darius Khambatta that the impugned order is bad in law and deserves to be set aside on the grounds that the final arguments have now commenced before the Arbitral Tribunal on 02.02.2018; that the bank guarantees are conditional; the conditions for invocation of the bank guarantees in question are not satisfied; and existence of special equities in favour of FGI (including irretrievable injustice).
It is submitted by the learned Senior Counsel that the two bank guarantees which are in issue in the present Appeal are Advance Bank Guarantee dated 4-4-2014 and the Performance Bank Guarantee dated 29-4-2015. It is ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:26 ::: 11/44 comapl 20-25.18.sxw submitted that both these bank guarantees in fact contain express provisions, which make it unambiguously clear that they are conditional. Learned Counsel submits that Article 1 of the Advance Bank Guarantee is clearly conditional.
The learned Senior Counsel submits that a plain reading of the aforesaid articles of the Advance Bank Guarantee shows that the invocation and obligation of the bank under the Bank Guarantee is dependent and conditional upon the delivery obligation not being performed by the seller in accordance with the terms of the Purchase Order. The 'delivery obligation' is defined as being 'the terms of the Purchase Order'.
It is pointed out that the Learned Single Judge has further held that the said 'general reference' was followed by subsequent Articles and that made it clear that the Bank guarantee was absolute and unconditional. It is ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:26 ::: 12/44 comapl 20-25.18.sxw submitted that the other provisions of the bank guarantees cannot override and/or whittle down in any manner whatsoever the condition imposed by Article 1 which is categorical and which is the provision imposing liability on the Bank.
The learned Senior Counsel submits that indeed what the Learned Single Judge has in fact done is to give overriding effect to Article 2 to supersede the conditional nature of Article 1. The learned Single Judge, by adopting such construction, has rendered the words "If the Delivery Obligation is not performed by the Seller in accordance with the terms of the Purchase Order" and "if the Seller either fails to perform any of its obligations under the Purchase Order or breaches/violates any of the terms of the Purchase Order" contained in Article 1 of the advance bank guarantee and performance bank guarantee respectively, meaningless and otiose. ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:26 :::
13/44 comapl 20-25.18.sxw The learned Senior Counsel Shri Khambatta further argued that the learned Single Judge erred by rejecting the submissions of FGI that existence of special equities was not limited to irretrievable harm / injury and entitled a party to an injunction against the invocation/pay out under the Bank Guarantee.
It is submitted that the law laid down by the Supreme Court on the definition of Special Equities is clear and the term 'Special Equities' comprises of special circumstances which make it inequitable for the Bank Guarantee to be invoked. Special Equities is wide enough to cover any other miscellaneous issues that might arise among the parties other than just irretrievable injuries/harm.
It is submitted that the learned Single Judge failed to appreciate that FGI will also suffer irretrievable ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:26 ::: 14/44 comapl 20-25.18.sxw injustice if the bank guarantees are permitted to be encashed. The irretrievable injustice lies in the fact that the aggregate amount of the Bank Guarantees viz Rs. 43,98,13,832 will be irrecoverable by FGI from TCTPL. The tests for this laid down in the judgments cited on behalf of TCTPL are fully satisfied in the present case by the undisputed facts. It is submitted that it is decisively established that FGI would suffer irretrievable injustice.
7. The learned counsel for the appellants, in support of his submissions, placed reliance on the following judgments:
(a) Mahatma Gandhi Sahakari Sakhar Karkhana vs. National Heavy Engg. Co-op.Ltd. [AIR 2007 SC 2716].
(b) Sri. Tufan Chatterjee vs. Sri. Rangan Dhar [AIR 2016 Cal. 213].
(c) BSES Ltd. vs. Fenner India Ltd. and anr. [(2006) 2 SCC 728].
(d) Western Coialfields Ltd. & Anr. vs. Rajesh Biyani [2011 (6) ALL MR 722].
(e) Crest Communications ltd. vs. SBI [2000 (1) ALL MR 598].
::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:26 :::
15/44 comapl 20-25.18.sxw
(f) Radha Sundar Dutta vs. Mohd. Jahadur Rahim [AIR 1959 SC 24 (V46 C5)].
(g) Sahebzada Mohd Kamgarh Shah vs. Jagdish Chandra Deo [AIR 1960 SC 953 (V 47 C 169)].
(h) Hindustan Construction Co. Ltd. vs. State of Bihar [(1999) 8 SCC 436].
(i) M/s. Meena Advertisers vs. Delhi Metro Rail Corpn.

Ltd. [OMP(I) No. 344/2015 and I.A. No. 13973/2015].

(j) HSSG India Pvt. Ltd. vs. Gammon India Ltd. [Comp. Appeal (L) No. 22/2017].

(k) Nagar Palika Parishad vs. Ramesh Construction Pvt. Ltd. [2017(3)UC 2214].

In the case of BSES Ltd. (Now Reliance Energy Ltd.) v/s. Fenner India Ltd. & anr.,1 cited supra the Apex Court in Paragraph 10 observed as under:

"10. There are, however, two exceptions to this rule. The first is when there is a clear fraud of which the bank has notice and a fraud of the beneficiary from which it seeks to benefit. The fraud must be of an egregious nature as to vitiate the entire underlying transaction. The second exception in the general rule of non-intervention is when there are "special 1 [(2006) 2 SCC 728].
::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:26 :::
16/44 comapl 20-25.18.sxw equities" in favour of injunction, such as when "irretrievable injury" or "irretrievable injustice" would occur if such an injunction were not granted. The general rule and its exceptions has been reiterated in so many judgments of this Court, that in U.P. State Sugar Corpn. v/s. Sumac International Ltd. (hereinafter "U.P. State Sugar Corpn") this Court, correctly declared that the law was "settled".

In the case of Western Coalfields Limited & anr. Vs. Rajesh s/o Nandlal Biyani & anr.,2 it is observed in Paragraph 24 as under:-

"24. The requirement of unconditional payment of the amount of Bank Guarantee without any demur, has nothing to do with the compliance of the conditions of Bank Guarantees and it only prohibits the respondent no .2 Bank from raising any dispute as to compliance or fulfillment of the terms and conditions of the contract between the appellant and the respondent no.1 Company. The respondent no.2 Bank cannot insist for proof of failure or negligence of respondent no.1 Company in performing the 2 [2011 (6) ALL MR 722].
::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:26 :::
17/44 comapl 20-25.18.sxw terms and conditions contained in the contract. It is in this background that the Condition No.1 has been incorporated in the Bank Guarantees agreeing, that the appellant Company shall be the sole judge as to whether the said contractor has failed/neglected in performing any of the terms and conditions of the said contract and the decision of the appellant Company in this behalf shall be binding upon the respondent no.2 Bank. Hence, on the basis of condition no.1 in the Bank Guarantee it cannot be urged that it is an unconditional Bank Guarantee and confers an unfettered right upon the appellant to invoke the Bank Guarantees and to demand immediate payment.
In the case of Crest Communications Ltd. Vs. State Bank of India & anr.3 it is observed in Paragraph 12 as under:
"12. Recently, in Hindustan Construction Co. Ltd. & others v. State of Bihar & others (supra), the Apex Court while reiterating the principles which govern Court interference in invocation of bank guarantee highlighted that such performance guarantee has to be invoked in 3 [2000 (1) ALL MR 598] ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:26 ::: 18/44 comapl 20-25.18.sxw accordance with the terms and conditions of the guarantee. In paragraph 21 of the report, the Apex Court held thus :-
"21. As pointed out above, Bank Guarantee constitutes a separate, distinct and independent contract. This contract is between the Bank and the defendants. It is independent of the main contract between the HCCL and the defendants. Since the Bank Guarantee was furnished to the Chief Engineer and there is no definition of "Chief Engineer" in the Bank Guarantee nor is it provided therein that "Chief Engineer" would also include Executive Engineer, the Bank Guarantee could be invoked by none except the Chief Engineer. The invocation was thus wholly wrong and the Bank was under no obligation to pay the amount covered by the "performance Guarantee" to the Executive Engineer."

In the case of Sahebzada Mohammad Kamgarh Shah vs Jagidsh Chandra Deo Dhabai Deb & ors.4 The Apex Court in paragraphs 12 and 13 observed as under:-

"12. In his attempt to establish that by this later lease the lessor granted a lease even of those minerals which had been excluded specifically by clause 16 of the earlier lease, Mr. Jha has arrayed in his aid several well established principles of construction. The first of these is that the intention of the parties to a document of grant must be ascertained first and foremost from the words used in the disposition 4 [AIR 1960 SC 953 (V 47 C 169)] ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:26 ::: 19/44 comapl 20-25.18.sxw clause, understanding the words used in their strict, natural grammatical sense and that once the intention can be clearly understood from the words in the disposition clause thus interpreted it is no business of the courts to examine what the parties may have said in other portions of the document. Next it is urged that if it does appear that the later clauses of the document purport to restrict or cut down in any way the effect of the earlier clause disposing of property the earlier clause must prevail. Thirdly it is said that if there be any ambiguity in the disposition clause taken by itself, the benefit of that ambiguity must be given to the grantee, the rule being that all documents of grants must be interpreted strictly as against the grantor. Lastly it was urged that where the operative portion of the document can be interpreted without the aid of the preamble, the preamble ought not and must not be looked into.

13. The correctness of these principles is too well established by authorities to justify any detailed discussion. The task being to ascertain the intention of the parties, the cases have laid down that that intention has to be gathered by the words used by the parties themselves. In doing so the parties must be presumed to have used the words in their strict grammatical sense. If and when the parties have first expressed themselves in one way and then go on saying something, which is irreconcilable with what has gone before, the ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:26 ::: 20/44 comapl 20-25.18.sxw courts have evolved the principle on the theory that what once had been granted cannot next be taken away, that the clear disposition by an earlier clause will not be allowed to be out down by later clause. Where there is ambiguity it is the duty of the Court to look at all the parts of the document to ascertain what was really intended by the parties. But even here the rule has to be borne in mind that the document being the grantor's document it has to be interpreted strictly against him and in favour of the grantee."

In the case of Hindustan Construction Co. Ltd. v/s. State of Bihar & ors.,5 in Paragraphs 13, 14 and 22 the Apex Court observed as under:

"13. The Bank, in the above Guarantee, no doubt, has used the expression "agree unconditionally and irrevocably" to guarantee payment to the Executive Engineer on his first demand without any right of objection, but these expressions are immediately qualified by following :-
"......in the event that the obligations expressed in the said clause of the abovementioned contract have not been fulfilled by the contractor giving the right of claim to the employer for recovery of the whole or part of the Advance Mobilisation Loan from the contractor under the contract."

14. This condition clearly refers to the original contract between 5 [(1999) 8 SCC 436].

::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:26 :::

21/44 comapl 20-25.18.sxw the HCCL and the defendants and postulates that if the obligations, expressed in the contract, are not fulfilled by HCCL giving to the defendants the right to claim recovery of the whole or part of the "Advance Mobilisation Loan", then the Bank would pay the amount due under the Guarantee to the Executive Engineer. By referring specifically to Clause 9, the Bank has qualified its liability to pay the amount covered by the Guarantee relating to "Advance Mobilisation Loan" to the Executive Engineer only if the obligations under the contract were not fulfilled by HCCL or the HCCL has misappropriated any portion of the "Advance Mobilisation Loan". It is in these circumstances that the aforesaid clause would operate and the whole of the amount covered by the "Mobilisation Advance" would become payable on demand. The Bank Guarantee thus could be invoked only in the circumstances referred to in Clause 9 whereunder the amount would become payable only if the obligations are not fulfilled or there is misappropriation. That being so, the Bank Guarantee could not be said to be unconditional or unequivocal in terms so that the defendants could be said to have had an unfettered right to invoke that Guarantee and demand immediate payment thereof from the Bank. This aspect of the matter was wholly ignored by the High Court and it unnecessarily interfered with the order of injunction, granted by the Single Judge, by which the defendants were restrained from invoking the Bank ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:26 ::: 22/44 comapl 20-25.18.sxw Guarantee.

22.We have scrutinised the facts pleaded by the parties in respect of both the Bank Guarantees as also the documents filed before us and we are, prima facie, of the opinion that the lapse was on the part of the defendants who were not possessed of sufficient funds for completion of the work. The allegation of the defendants that HCCL itself had abandoned the work does not, prima facie, appear to be correct and it is for this reason that we are of the positive view that the "special equities" are wholly in favour of HCCL."

8. The learned Senior Counsel Mr. Aspi Chinoy submits that the subject guarantees are unconditional, absolute and irrevocable. The petitioners had filed Company Petition No.780/2015 against TCTPL seeking winding up of of the company for non-payment of amount of Rs.2 Crores. By an order dated 22 nd August, 2017 the said petition was dismissed by the Company Judge. Learned Counsel has referred to Paragraph 13 of the said order which reads as under:

"13. I find that the admissions of liability were all as a result of negotiations which were in anticipation of ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:26 ::: 23/44 comapl 20-25.18.sxw continuation of work under the contract sand not as a result of the termination of the contract. All these negotiations were pre termination and hence should not now be held against the Company."

The appellants herein did not prefer any appeal against the order passed on 22nd August, 2017. The appellants did not seek any relief against TCTPL. An ex parte order was granted against respondents 2 and 3 i.e. two Banks restraining them from releasing the payment. The Arbitral Tribunal was constituted on 13th September, 2016 and the reference made to the arbitrator is presently being heard before the Arbitral Tribunal. In the submissions of the Counsel, the learned Single Judge has addressed all the three substantial issues raised by the appellants and a sound and reasoned view has been adopted by the learned Single Judge while dealing with the issue raised by the appellants. The issue is covered by the judgment of the Apex Court in the case of Mahatma Gandhi Sahakari Karkhana v/s Heavy Engineering Corpn1. The appellants have sought to distinguish the 1 (2007) 6 SCC 470 ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:26 ::: 24/44 comapl 20-25.18.sxw aforesaid case on the ground that clause 2 of the Guarantee in that case has made the purchasers the sole judge in determining whether there is a breach of the Purchase Order. This distinction sought to be made by the appellants is a distinction without difference. The Clause 1 of the Bank Guarantee had to be read alongwith Clauses 2 and 15 thereof which makes it clear that guarantees were absolute and unconditional. Clause-2 of the Guarantee contemplates that the demand by the respondents shall not be disputed or enquired into by the Bank and it is this language of Clause 2 which makes TCTPL the sole Judge in determining whether there is a breach of the purchase order and whether any amount should be claimed under the Bank Guarantee from the Guarantor i.e. the Bank.

9. It is further submitted that the judgment in the case of Hindustan Construction Co. vs State of Bihar 2 which was relied upon by the appellants was not applicable to the facts; either terms of Bank Guarantee in that case were quite different and liability thereunder was clearly qualified and conditional.


 2 {(1999) 8 SCC 436}




::: Uploaded on - 12/04/2018                            ::: Downloaded on - 13/04/2018 02:03:26 :::
                                           25/44                                          comapl 20-25.18.sxw




10. The judgment of the Apex Court in the case of Mahatma Gandhi Sahakari Karkhana(cited supra) was not a determining aspect/feature on the basis of decision in that case. The Bank Guarantee is a separate contract between the Bank and beneficiary. It was submitted that appellants reliance on the decisions in the case of Hindustan Construction Company (cited supra) is misplaced as the terms of the Bank Guarantee in that case were very different.

11. It is submitted by the learned Senior Counsel in written submissions in clauses (A) to (D) of Paragraph 3 as under:-

(A) The Petitioners / Appellants have sought to contend that there were "Special Equities" for restraining the invocation of the Bank Guarantees, as an amount of Rs.32 Crores was allegedly payable by TCTPL to the Petitioners / Felguera (as evidenced by correspondence and Minutes of Meetings). (B) The Learned Judge has rejected the Petitioners contention and held that non payment of dues under a Contract, by the party invoking a Bank Guarantee, did not constitute "Special Equities", inasmuch as non payment was only a dispute arising under the ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:27 ::: 26/44 comapl 20-25.18.sxw Contract. The Learned Judge has relied upon three Supreme Court judgments which have held that such contractual claims and disputes could not be considered by the Guarantor Bank, or by the Court to restrain payment under the bank Guarantee.

(C ) It is submitted that the so called 'admissions' of liability which are relied on, were made in the course of negotiations between the parties and accordingly cannot be held against the Respondent Company / TCTPL. As has been stated above, the Petitioners / Felguera had filed a Company Petition (No. 780 of 2015) for winding up against the Respondent / TCTPL, on the basis of the very same 'admissions' / material. The Hon'ble Court [Menon, J] had dismissed the Appellant/Felguera's Company Petition by an order dated 22nd August, 2017 and had held that the admissions of liability were made in the course of negotiations and hence could not be held against the Company/TCPTL. In paragraph 13 of the order dated 22 nd August 2017 the Learned Single Judge had held as follows:

"13. I find that the admissions of liability were all as a result of negotiations which were in anticipation of continuation of work under the ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:27 ::: 27/44 comapl 20-25.18.sxw contract sand not as a result of the termination of the contract. All these negotiations were pre termination and hence should not now be held against the Company."

The Petitioners/Appellants herein had not preferred an Appeal against the said Order dt.22nd August, 2017, which has accordingly attained finality.

(D) The Supreme Court has repeatedly held, that such contractual disputes and claims of non-payment of dues / breach of contract [including claims of admitted non payment of contractual dues, or double recovery of contractual advances ], could not be considered as a basis for seeking to restrain the invocation and encashment of an unconditional Bank Guarantee.

12. The learned Senior Counsel appearing for respondent no.1 placed reliance on following judgments:-

(a) Mahatma Gandhi Sahakari Sakhar Karkhana vs. National Heavy Engg. Co-op.Ltd.

[AIR 2007 SC 2716].

(b) Vinitec Electronics Pvt. Ltd. vs. HCL Inforsystems Ltd. [(2008) 1 SCC 544].

::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:27 :::

28/44 comapl 20-25.18.sxw

(c) Dwarikesh Sugar Ind. Ltd. vs. Prem Heavy Eng. Works [(1997) 6 SCC 450].

(d) U. P. State Sugar Corpn. vs. Sumac International Ltd. [(1997) 1 SCC 568.

(e) Somwanti and ors. vs. The State of Punjab and the State of Gujarat [AIR 1963 SC 151].

13. The learned Single Judge while dealing with the issues referred to the clause of the guarantees as incorporated in the judgment and dealt with rival contentions of both the parties. Paragraph 17 of the impugned judgment is reproduced herein below:-

"............It is therefore clear that Article 1 of the Advance Bank Guarantee as well as the Performance Bank Guarantee have only made a general reference to the purchase order and generally set out that if the delivery obligation is not performed by the seller/FGIPL in accordance with the terms of the purchase order, or if the seller fails to perform any of its obligation/s under the purchase order, or breaches or violates any of the terms of ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:27 ::: 29/44 comapl 20-25.18.sxw the purchase order, the guarantor bank shall within seven days from receipt of the demand from the purchaser make payment to TCTPL in a sum not exceeding the amount for which the Bank Guarantee is provided. After the above general reference to the purchase orders in Article 1, the subsequent Articles have made it clear that the Bank Guarantees are absolute and unconditional by a clear assertion that the bank shall not be entitled to dispute or inquire into whether TCTPL has become entitled to claim the guaranteed amount under the purchase order or not ; or whether FGIPL has committed any breach of purchase order and/or general terms and conditions applicable thereto or not ; or whether TCTPL is entitled to recover any damages from the Supplier/FGIPL for breach thereof or not. It is further clearly asserted in Articles 3, 6, 7(D) and 15 of the Bank Guarantees that TCTPL need not initiate any proceeding or claim against FGIPL before lodging any claim under the guarantee; that the liability of the Guarantor/Bank under the Guarantees shall be primary, direct and immediate, and not conditional and/or contingent upon pursuit by the ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:27 ::: 30/44 comapl 20-25.18.sxw purchaser/TCTPL of any remedies that it may have against the seller/FGIPL and/or any other person in relation to the purchase order; that the demand for observance, performance and/or enforcement of any terms and/or provisions of the guarantees and/or purchase order is expressly waived ; and that a demand for payment under the guarantees shall be deemed to have been sufficiently made if a claim in writing is sent by post or hand delivered to the Guarantor/Bank at its office and is received by the guarantor. It is required to be made clear that only because TCTPL has in its invocation letters stated that, "the delivery obligation is not performed by the seller" and that "the seller has failed to perform its obligation/s under the purchase order", the submission of FGIPL that TCTPL is conscious of the fact that the Bank Guarantees are conditional, cannot be accepted."

14. As regards the judgment relied upon by the appellants, the learned Single Judge observed that in view of peculiar facts and circumstances of the Apex Court case and language of the Bank ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:27 ::: 31/44 comapl 20-25.18.sxw Guarantee, the Apex Court held that the Bank Guarantee therein was conditional. The contents of none of the articles is found in the subject bank guarantee. It was, therefore, observed that the judgment of the Apex Court is not applicable to the facts of the present case. The learned Single Judge observed in Paragraph 24 as under:-

24. I am therefore, of the view that Articles 1 and 2 of the subject Bank Guarantees and the other Articles set out hereinabove can be harmoniously construed, and since I do not find any conflict between Articles 1 and 2 of the subject Bank Guarantees and/or any other Article/s of the subject Bank Guarantees, I hereby hold that the Bank Guarantees in question are absolute and unconditional. The submissions made on behalf of FGIPL in support of their contention that the Bank Guarantees are conditional, therefore cannot be accepted and the case laws relied upon by them do not assist them. The distinction sought to be made by them, with regard to the case laws relied upon by TCTPL, also cannot be accepted. The principles laid down by the Hon'ble Supreme ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:27 ::: 32/44 comapl 20-25.18.sxw Court in the case of Saheb Zada Mohd. Kamgar Shah (supra) and Radha Sundar Dutta (supra) also do not assist FGIPL.

Since I am of the view that there is no ambiguity qua the construction of the Bank Guarantees, the question of applying the contra proferentum rule also does not arise. In respect of plea of special equities, the learned Single Judge observed in Paragraph 33 as under:

33. I am in agreement with the above submissions of Mr. Kamdar. The word "special equities" came to be coined for the first time by Sabyasachi Mukharji J. sitting as a judge of the Calcutta High Court in the case of Texmaco Ltd. v. State Bank of India and Ors. (supra), in which he observed as follows:
"10. In my opinion, the position in law is as follows, whether the bank is obliged to pay and pay on what terms must depend upon both in the case of bank guarantee and in the case of letter of credit on the terms of the document. With respect to the Court of Appeal, it is not necessary for this Court to go to the extent of saying whether the ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:27 ::: 33/44 comapl 20-25.18.sxw performance guarantee stands on a similar footing of a letter of credit but so far as the Court of Appeal says the bank must pay according to the guarantee on demand, if so stipulated, without proof or conditions, I respectfully agree. The Court of Appeal has referred to the exception of a clear fraud. I venture to suggest there may be another exception in the form of special equities arising from a particular situation which might entitle the party to an injunction restraining the performance of bank guarantee. But in the absence of such special equities and in the absence of any clear fraud, the Bank must pay on demand, if so stipulated, and whether the terms are such must have to be found out from the performance guarantee as such." (Emphasis supplied) [See at Page 49] Sabyasachi Mukharji J., when sitting as a Judge of the Hon'ble Supreme Court explained the above observation in the Texmaco case whilst deciding the case of U.P. Co-operative Federation Ltd. v. Singh Consultants and Engineers (P) Ltd. (supra) in the following terms:
::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:27 :::
34/44 comapl 20-25.18.sxw "16. The Court of Appeal in England had occasion once again to consider this question in Elian and Rabbath v. Matsas and Matsas -(1966) 2 Lloyd's List Law Reports 495. In that case injunction was granted to prevent irretrievable injustice......
21. In the instant case, the learned Judge has proceeded on the basis that this was not an injunction sought against the bank but this was the injunction sought against the appellant. But the net effect of the injunction is to restrain the bank from performing the bank guarantee. That cannot be done. One cannot do indirectly what one is not free to do directly. But a maltreated man in such circumstances is not remedyless. The respondent was not to suffer any injustice which was irretrievable. The respondent can sue the appellant for damages. In this case there cannot be any basis for apprehension that irretrievable damages would be caused if any. I am of the opinion that this is not a case in which injunction should be granted. An irrevocable commitment either ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:27 ::: 35/44 comapl 20-25.18.sxw in the form of confirmed bank guarantee or irrevocable letter of credit cannot be interfered with except in case of fraud or in case of question of apprehension of irretrievable injustice has been made out. This is the well-settled principle of the law in England. This is also a wellsettled principle of law in India, as I shall presently notice from some of the decisions of the High Court and decisions of this Court.
...
24. I may notice that in India, the trend of law is on the same line. In the case of Texmaco Ltd. v. State Bank of India and ors. - AIR 1979 Calcutta 44, one of us (Sabyasachi Mukharji, J.) held that in the absence of special equities arising from a particular situation which might entitle the party on whose behalf guarantee is given to an injunction restraining the bank in performance of bank guarantee and in the absence of any clear fraud, the bank must pay to the party in whose favour guarantee is given on demand, ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:27 ::: 36/44 comapl 20-25.18.sxw if so stipulated, and whether the terms are such have to be found out from the performance guarantee as such. There the Court held that where though the guarantee was given for the performance by the party on whose behalf guarantee was given, in an orderly manner its contractual obligation, the obligation was undertaken by the bank to repay the amount on "first demand" and "without contestation, demur or protest and without reference to such party and without questioning the legal relationship subsisting between the party in whose favour guarantee was given and the party on whose behalf guarantee was given," and the guarantee also stipulated that the bank should forthwith pay the amount due "notwithstanding any dispute between the parties," it must be deemed that the moment a demand was made without protest and contestation, the bank had obliged itself to pay irrespective of any dispute as to whether there had been performance in an orderly manner of the contractual obligation by the party. Consequently, in ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:27 ::: 37/44 comapl 20-25.18.sxw such a case, the party on whose behalf guarantee was given was not entitled to an injunction restraining the bank in performance of its guarantee. It appears that special equities mentioned therein may be a situation where the injunction was sought for to prevent injustice which was irretrievable in the words of Lord Justice Denning, M.R. in Elian and Rabbath v. Matsas and Matsas.
...
28. I am however, of the opinion that these observations must be strictly considered in the light of the principle enunciated. It is not the decision that there should be a prima facie case. In order to restrain the operation either of irrevocable letter of credit or of confirmed letter of credit or of bank guarantee, there should be serious dispute and there should be good prima facie case of fraud and special equities in the form of preventing irretrievable injustice between the parties. Otherwise the very purpose of bank guarantees would be negatived and ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:27 ::: 38/44 comapl 20-25.18.sxw the fabric of trading operation will get jeopardised. ...
34. On the basis of these principles I reiterate that commitments of banks must be honoured free from interference by the courts. Otherwise, trust in commerce internal and international would be irreparably damaged. It is only in exceptional cases that is to say in case of fraud or in case of irretrievable injustice be done, the Court should interfere." (Emphasis supplied) [see at pages 183; 186; 187 - 188; 189; 190]"

The learned Single Judge observed in Paragraph 36 of the judgment that the alleged admitted non-payment of claim by TCTPL to FGIPL cannot create a special equity so as to injunct the invocation of the Bank Guarantee. It was observed that whether there was any payment due or not under the underlying contract is not the subject matter which can be considered for grant or refusal of grants. The learned Single Judge also considered the submission that the respondent TCTPL is financially sound company and has already ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:27 ::: 39/44 comapl 20-25.18.sxw invested in excess of Rs.350 Crores to develop and commission a Rs.640 Crore Coal Terminal for the V.O. Chadambaranar Port Trust, Tuticorin.

15. We have perused the record placed before us, considered reply and written submissions advanced. We have also perused the record placed before us.

16. The Counsel appearing for the appellants submits that Bank Guarantee is conditional. We have perused the relevant clauses of Bank Guarantee, particularly clauses 1 and 2.

17. In the facts we are of the view that both the Bank Guarantees have to be harmoniously construed in the light of the agreement executed between the parties, the purchase orders and correspondence exchanged.

18. A conjoint reading of Articles 1 and 2 of the Advance Bank ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:27 ::: 40/44 comapl 20-25.18.sxw Guarantee and Performance Bank Guarantee indicate that it is an unconditional Bank Guarantee. We find substance in the submissions of the learned Counsel that there was a similar clause for consideration of the Apex Court in Mahatma Gandhi Sahakari Karkhana cited supra. It was held that said guarantees were unconditional one. Clause-1 of the Bank Guarantee has to be read alongwith clause-2 which would make it clear that Guarantees are absolute and unconditional. Taking into consideration clause-2 of the Bank Guarantee we find that TCTPL would be sole judge in determining whether there is breach of the purchase order and whether any amount should be claimed under the Bank Guarantee. In the facts of the case the judgment in the case of Hindustan Construction cited supra by the appellants would not be applicable to the present set of facts. In that case the guarantees were qualified and conditional. It is a settled position that Bank Guarantee is a separate contract between the Bank and beneficiary. Accordingly, if by the terms of Bank Guarantee, the Bank/Guarantor is precluded from questioning or enquiring into the beneficiary's decision to invoke the ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:27 ::: 41/44 comapl 20-25.18.sxw Guarantee, the beneficiary necessarily would become the sole Judge in deciding whether the right to invoke guarantee has accrued or not.

19. The learned Senior Counsel Shri Khambata submitted that amount of Rs.30 Crores was payable by TCTPL to the appellants which constituted "special equities" justifying the restraint upon the encashment of Bank Guarantee. We have gone through the Apex Court judgment and the issues and in the facts of the case we hold that such contractual claims and disputes could not be considered by the Guarantor Bank or by the Court to restrain payment under the Bank Guarantee. It is to be noticed that the relief sought and granted are against the Bank in this case.

20. We find substance in the submissions of the learned Senior Counsel Aspi Chinoy that so called demands of the liability which are relied upon by the appellants were made in the core of negotiations between the parties and, therefore, cannot be held against the respondent company/TCPTL. The Company Petition filed by the ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:27 ::: 42/44 comapl 20-25.18.sxw appellants was dismissed by the learned Single Judge on 22 nd August, 2017 and as no appeal has been preferred, thus it has become final.

21. In the facts of the case, we find that the view of the Supreme Court in Mahatma Gandhi case cited supra applies to the present guarantees in question. The distinction sought to be made in respect of Articles 1 and 2 of the Guarantees and the reliance on the case of Apex Court is misplaced one in our view and is not convincing one. The view adopted by the learned Single Judge is sound, reasonable and convincing one.

22. The learned Counsel appearing for appellants submitted that TCTPL is a special purpose Vehicle which was making losses and its debts exceeds its equity. This proposition has been dealt with by the Counsel appearing for the respondents. In the submissions of the Counsel though the contention has been denied on the said proposition that TCTPL is making losses, the same could not be ground for the Court to grant an injunction against TCTPL from invoking the Bank Guarantee. It is the contention of the TCTPL that ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:27 ::: 43/44 comapl 20-25.18.sxw they have infused capital of Rs.170 Crores in the project. The Concession Agreement executed between the parties is for 30 years. During this period TCTPL will be entitled to recover tariff from the users of the Project Facilities and services. The total estimated revenue during the balance concession period shall be Rs.10,067.14 crores.

23. In the facts of the case we find that appellants have failed to make out a case for interfering in the view adopted by the learned Single Judge. We find that the learned Single Judge adopted a reasonable and sound view based on the facts and material placed before the Court by harmoniously construing the relevant clauses of the advance and performance bank guarantees. There is no merit in these appeals. They are accordingly dismissed.

(NITIN W. SAMBRE,J.) (NARESH H. PATIL,J.)

24. After pronouncement of the judgment, the learned Counsel appearing for the appellants prays for continuation of the ad-interim ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:27 ::: 44/44 comapl 20-25.18.sxw relief for a period of six weeks which was in operation for near about two years.

25. The learned Counsel appearing for respondents opposes the prayer. It is submitted that taking into consideration the efficacy of Bank Guarantee in commercial transactions, prayer for stay be rejected.

26. In the facts of the case, we continue the ad-interim relief granted by this Court earlier for a period of three weeks.

(NITIN W. SAMBRE,J.) (NARESH H. PATIL,J.) L.S. Panjwani, P.S. ::: Uploaded on - 12/04/2018 ::: Downloaded on - 13/04/2018 02:03:27 :::