State of Rajasthan - Subsection

Section 2(16) in Rajasthan Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) Regulations, 2009

(16)"Cut-off Date" means the date of the first financial year closing after three hundred and sixty-five (365) days of the date of commissioning of a generating station;