Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 25, Cited by 0]

Delhi District Court

(1)Birla Cable Limited vs Mahanagar Telephone Nigam Limited on 18 December, 2017

   IN THE COURT OF MS. ASHA MENON: DISTRICT &
SESSIONS JUDGE (SOUTH DISTRICT) SAKET: NEW DELHI

(1) CIS­ARBTN­313­2017
    CNR­DLST 01­003337­2017

(1)Birla Cable Limited,
(Formerly known as Birla Ericsson Optical Limited)
Registered office at:
Udyog Vihar, P.O. Chorhata,
Rewa 486006 (M.P.)
Also At:
2nd Floor, Wing­B, Commercial Plaza,
Radisson Hotel Delhi, National Highway No.8,
Mahipalpur, New Delhi­110037                        .....Petitioner.

                                                   Versus

Mahanagar Telephone Nigam Limited,
Through its AGM (MP­C)
3rd Floor, Lobby­2,
Mahangar Door Sanchar Sadan,
9, C.G.O Complex, Lodhi Road,
New Delhi­110003                                          ....Respondent.
Date of Institution: 28.11.2008
Judgment reserved on: 16.11.2017
Judgment pronounced on: 18.12.2017


(2)CIS­ARBTN­313­2017
CNR­DLST01­003342­2017
M/s Vindhya telelinks Limited
Having its Registered Office at
Udyog Vihar, P.O. Chorhata
Rewa (M.P.)­486006
And business office inter­alia at:
4th  Floor, UCO Bank Building,
Parliament street

CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017                          Page 1 of 36 
 New Delhi­110001
Through Mr. Sandeep Chawala, Vice President
& Commercial Attorney                                             ....Petitioner
                           Versus

Mahanagar Telephone Nigam Limited,
Through its AGM (MP­C)
3rd Floor, Lobby­2,
Mahangar Door Sanchar Sadan,
9, C.G.O Complex, Lodhi Road,
New Delhi­110003                                          ....Respondent.
Date of Institution: 07.10.2009
Judgment reserved on: 16.11.2017
Judgment pronounced on: 18.12.2017
                                          JUDGMENT

The two objection petitions have been filed under Section 34 of the Arbitration & Conciliation Act, 1996 by Birla Cable Limited   (Formerly   known   as  Birla   Ericsson   Optical   Limited)   and Vindhya   Telelinks   Limited   against   the   respondent   Mahanagar Telephone Nigam Limited before the Hon'ble High Court of Delhi. Pursuant to Notification No. 27187/DHC/Orgl. Dated 24.11.2015, as amended vide letter dated 25.07.2016 received from the High Court of Delhi, the aforesaid petitions have been transferred to this Court and are accordingly being disposed off.

This   judgment   will   dispose   of   two   objection   petitions filed  under  Section  34  of  the  Arbitration  &  Conciliation  Act,  1996 (hereinafter referred to as the Act).

The first petition u/s. 34 of the Act was filed by Birla Cable   Limited   against   Mahanagar   Telephone   Nigam   Limited challenging the Award dated 16.07.2008 passed by the Sole Arbitrator.

CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 2 of 36 

The   second   petition   u/s.   34   of   the   Act   was   filed   by   M/s   Vindhya Telelinks Limited against Mahanagar Telephone Nigam Limited for setting   aside   the   Award   dated   10.06.2009   passed   by   the   Sole Arbitrator.   Since the issues raised and the arguments advanced are common in both the objections, the two petitions are taken up together and shall be disposed of by this common judgment.

FACTS OF THE PETITION OF BIRLA CABLE LIMITED The facts as set out in the petition filed by Birla Cable Limited are that the petitioner is a company incorporated under the Companies Act, 1956 having its registered office and factory at Udyog Vihar,   P.O   Chorhata,   District   Rewa,   Madhya   Pradesh   and   was engaged in the business of manufacturing and supply of various types of   telecommunication   cables   including   polyethylene   insulated   jelly filled  underground  cables   (PIJF   U/G   Cables).     The   respondent  is   a Government   of   India   Undertaking   and   is   a   company   incorporated under the provisions of the Companies Act, 1956 and engaged  inter alia, in the business of planning, establishing, developing, providing, operating   and   maintaining   the   telecommunication   services   for   the National Capital Territory of Delhi and Mumbai.

The   respondent   had   floated   a   tender   enquiry   no.

MTNL/20­80   (66))/2004­2005/2004­MM/PIJF   dated   12.05.2004   for procurement of PIJF U/G Telecom Cables.  The petitioner responded to this by submitting an offer which was accepted by the respondent and   thereafter,   the   respondent   issued   the   following   two   Purchase Orders on the petitioner:­

(a). P.O. No. AGM (MP­C)/MM­128/PIJF/P.O./2004­       2005/BEOL/34 dated 19.08.2004 for supply of 178         Kms. of 100/0.5(A) Cables.

CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 3 of 36 

(b). P.O. No. AGM (MP­C)/MM­128/PIJF/P.O./2004­      2005/BEOL/46 dated 27.08.2004 for supply of       20/0.5(A) Cables.

It is further stated that the tender documents containing the General (Commercial) Conditions of Contract (Section III) and the Purchase Orders form the contract between the parties.  As per Clause 9 of the Purchase Orders the entire supply was to be completed as per Clause 3 of the said Purchase Orders which prescribed that 25% of the ordered quantity was to be completed within two months from the date of the issuance of the Purchase Order and the balance quantity was to be  supplied  within next  two  months  thereafter.    As  such the  entire supply was to be completed within a period of four months from the date of the respective Purchase Orders.   The PIJF U/G Cables were required to meet the latest TEC generic requirement   No. GR/CUG­ 01/03 August 2003 with update amendments.  As per Clause 8.2 of the Purchase Order the price quoted by the petitioner and accepted by the respondent were based on Copper Wire Rod (basic) per Metric Ton @ Rs.1,78,189/­ (excluding Excise Duty) as prevailing in the month of May,   2004   as   detailed   in   Clause   6   of   Section   IV   of   the   tender document.

It is further submitted by the petitioner that as per Clause 16 of the General (Commercial) Conditions of Contract (Section III) of the   tender   documents   and   Clause   12   of   the   Purchase   Orders   the provisions for liquidated damages was made applicable.  It was further submitted that PIJF Cables which were required to be supplied under the tender were to meet the latest specifications and the petitioner was required   to   obtain   PQT   Clearance/Bulk   Production   Clearance   after obtaining the TAC (Type Clearance Certificate). It was submitted that CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 4 of 36  since the specification of the PIJF Cables required by the respondent was a fresh specification, hence the petitioner applied for the Type Approval Certificate, which was issued on 09.09.2004.   As per the procedure   the   petitioner   was   then   to   take   PQT   Clearance/Bulk Production Clearance after obtaining the TAC which was immediately applied by the petitioner but PQT/Block Clearance was issued only on 30.10.2004   i.e.   after   more   than   two   months   from   the   date   of   the purchase order.  This fact was immediately brought to the notice of the petitioner/respondent vide its letter dated 04.10.2004.  It also requested for refixation of the delivery schedule enabling the petitioner to get all the required approvals and PQT done in time as the time to be taken for grant of the said clearance and certificate was beyond the control of the petitioner.

According to the  petitioner  the  respondent  ignored the letter of the petitioner and instead issued a show cause notice with regard   to   the   purchase   order   dated   19.08.2004   as   to   why   the   PIJF Cables   have   not   been   supplied   within   the   delivery   schedule.     The petitioner again vide letter dated 21.12.2004 requested the refixation of the   delivery   period   with   regard   to   the   Purchase   Order   dated 19.08.2004.  The respondent vide letter dated 04.01.2005 extended the delivery period of one month from the date of issuances of the said letter with regard to the Purchase Order dated 19.08.2004 belatedly. However, the respondent illegally, arbitrarily threatened to impose the liquidated damages.  

With regard to the Purchase Order dated 27.08.2004, the petitioner completed the supply within the original delivery period of four months from the date of the Purchase Order.  After the supply of CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 5 of 36  the PIJF Cables under both the Purchase Orders, the petitioner raised the bills.  However, the respondent illegally, arbitrarily and contrary to the   express   terms   of   the   Purchase   Orders   withheld   a   sum   of rs.8,00,223/­ allegedly to be recovered as the liquidated damages and on account of price variation in respect of both the aforesaid Purchase Orders.    The   details  of the  said  deduction  have  been  mentioned  as under:

_________________________________________________________ Sl. No. P.O.No. & Date      DEDUCTIONS (Rs.)      LD        PV           Total
1. P.O. No. AGM (MP­C)/MM­     426795/­   222346/­   649141/­ 128/426795/­PIJF/P.O./2004­ 2005/BEOL/34 dated 19.08.2004 for supply of 100/0.5(A) Cables.
2. P.O. No. AGM (MP­C)/MM­     100898/­      50184/­   151082/­ 128/PIJF/P.O./2004­2005/ BEOL/46 dated 27.08.2004 for supply of 20/0.5(A) Cables.
   Total:      527693/­   272530/­    800223/­ _________________________________________________________ According   to   the   petitioner   they   informed   the respondents   that   the   respondents   had   wrongly   with­held   a   sum   of Rs.6,49,141/­   and   Rs.1,51,082/­   against   both   the   Purchase   Orders dated 19.08.2004 and 27.08.2004 respectively and requested for the release of the amount immediately.   No response was given by the respondent   and   as   the   respondent   wrongfully   with­held   the   sum   of Rs.8,00,223/­ , the petitioner vide notice dated 28.05.2005 invoked the arbitration   agreement.     Thereafter,   vide   letter   dated   03.06.2005   the respondent refused to pay the said amount.  Accordingly, the petitioner filed   the   statement   of   claim   before   the   Ld.   Sole   Arbitrator.     The CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 6 of 36  respondent filed a reply and the petitioner a rejoinder thereto.

Vide   the   impugned   Award   dated   16.07.2008   the   Sole Arbitrator decided the matter against the claimant/petitioner holding that no case for refund of the deduction made by the respondent was made out and the claim have no merit.   Accordingly, the claim was dismissed. 

Aggrieved, the petitioner has filed the present objections against the said Award dated 16.07.2008 submitting that the Award was against public policy and was therefore, liable to be set aside.  The grounds taken inter alia, are that: it was violative of the provisions of Section 28(3) of the Act; that Clause 12 of the Contract was a penal clause being a clause in terrorem and, therefore, cannot be enforced unless   the   respondent   proved   to   have   suffered   actual   loss   and therefore, the Award was contrary to the terms agreed between the parties;   that   the   Ld.   Arbitrator   had   completely   ignored   the   three Awards passed by different Arbitral Tribunals unanimously holding that   the   first   portion   of   clause   12.2   was   a   penal   clause   and   the respondent was not entitled to claim any liquidated damages unless the actual loss suffered was proved beyond any shadow of doubt; that the Ld. Arbitrator erred in applying the ratio of the judgment in  'Hind Construction Contractors Vs. State of Maharashtra', (1979) 2 SCC 70 and that time was not intended to be of the essence of the contract as the contract between the parties contained clause relating to imposition of penalty and extension of time; that the Ld. Arbitrator erred in not adjudicating the dispute with recourse to Sections 73 and 74 of the Indian   Contract   Act,   1872   which   specifically   provided   that compensation/damages could be awarded only if the loss was suffered CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 7 of 36  as per the case of the breach of the contract whereas in the present case the   respondent   had   made   no   effort   to   prove   the   loss;   that   the   Ld. Arbitrator failed to distinguish between two clauses of Clause 12.2 and to notice that the first part was a penalty clause without actual loss or harm   whereas   the   second   part   provided   for   liquidated   damages   if substantial harm has been caused and that therefore, the mere penalty without actual loss could not have been recovered under Clause 12.2; that the Ld. Arbitrator failed to take into account the admitted fact that as per the agreement entered into by the petitioner and the respondent the petitioner has in fact supplied the entire quantity of cables within the original or extended delivery period thereby providing no occasion for   the   respondent   to   recover   any   liquidated   damages   from   the petitioner   and,   therefore,   the   Ld.   Arbitrator   had   committed   grave mistake   in   passing   the   Award;   that   the   Ld.   Arbitrator   erred   in concluding   that   time   was   of   the   essence   of   the   contract   as   the agreement between the parties contained the Clauses for imposing of penalty as well as extension of time and the very fact that the time was actually   extended   in   the   instant   case   proved   that   the   time   was   not essence of the contract in the present matter; that the respondent was not entitled to invoke the price variation clause in respect of the supply made against the Purchase Order dated 27.08.2004 and, therefore, the petitioner   was   entitled   to   recover   the   said   amount   of   Rs.2,72,530/­ wrongfully   withheld   by   the   respondent;   that  the   Ld.   Arbitrator   had incorrectly   interpreted   the   Clause   12   and   Clause   11.5   and   thus   the findings of the Ld. Arbitrator were contrary to the fact.  On all these grounds, it was prayed that the Award dated 16.07.2008 be set aside.

CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 8 of 36 

FACTS OF THE PETITION OF M/S VINDHYA TELELINKS  LTD The facts as set out in the petition filed by M/s Vindhya Telelinks  Limited are  that  the  petitioner is  a  company incorporated under the Companies Act, 1956 having its registered office and factory at Udyog Vihar, P.O Chorhata, District Rewa, Madhya Pradesh and was engaged in the business of manufacturing and supply of various types   of   telecommunication   cables   including   polyethylene   insulated jelly filled underground cables (PIJF U/G Cables).  The respondent is a Government   of   India   Undertaking   and   is   a   company   incorporated under the provisions of the Companies Act, 1956 and engaged  inter alia, in the business of planning, establishing, developing, providing, operating   and   maintaining   the   telecommunication   services   for   the National Capital Territory of Delhi and Mumbai.  The respondent had floated   a   tender   enquiry   no.   MTNL/20­80   (66))/2004­2005/2004­ MM/PIJF   dated   12.05.2004   for   procurement   of   PIJF   U/G   Telecom Cables.  The petitioner responded to this by submitting an offer which was accepted by the respondent and thereafter, the respondent issued the following four Purchase Orders on the petitioner:­

(a). P.O. No. AGM (MP­C)/MM­128/PIJF/P.O./2004­       2005/VTL/30 dated 19.08.2004 for supply of 117                   Kms. of 200/0.5(A) Cables and 60.4 Kms of        1200/0.5 (A) cables.

(b). P.O. No. AGM (MP­C)/MM­128/PIJF/P.O./2004­       2005/ VTL/53 dated 10.09.2004 for supply of         27 Kms. of 800/0.5 (UA)Cables.

(c). P.O. No. AGM (MP­C)/MM­128/PIJF/P.O./2004­       2005/ VTL/57 dated 13.09.2004 for supply of         156 Kms. of 200/0.5 (A)Cables.

(d). P.O. No. MTNL­MUM/DWPE/GM(MM)/16­28/         VTL/04­05 dated 06.09.2004 for supply of         3.2 Kms. of 1200/0.5 (A)Cables and 12.4 Kms. of CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 9 of 36          800/0.5(UA) Cables.

It is further stated that the tender documents containing the General (Commercial) Conditions of Contract (Section III) and the Purchase Orders form the contract between the parties.  As per Clause 9 of the Purchase Orders the entire supply was to be completed as per Clause 3 of the said Purchase Orders which prescribed that 25% of the ordered quantity was to be completed within two months from the date of the issuance of the Purchase Order and the balance quantity was to be  supplied  within next  two  months  thereafter.    As  such the  entire supply was to be completed within a period of four months from the date of the respective Purchase Orders.   The PIJF U/G Cables were required to meet the latest TEC generic requirement   No. GR/CUG­ 01/03 August 2003 with update amendments.  As per Clause 8.2 of the Purchase Order the price quoted by the petitioner and accepted by the respondent were based on Copper Wire Rod (basic) per Metric Ton @ Rs.1,78,189/­ (excluding Excise Duty) as prevailing in the month of May,   2004   as   detailed   in   Clause   6   of   Section   IV   of   the   tender document.

It is further submitted by the petitioner that as per Clause 16 of the General (Commercial) Conditions of Contract (Section III) of the   tender   documents   and   Clause   12   of   the   Purchase   Orders   the provisions for liquidated damages was made applicable.  It was further submitted that PIJF Cables which were required to be supplied under the tender were to meet the latest specifications and the petitioner was required   to   obtain   PQT   Clearance/Bulk   Production   Clearance   after obtaining the TAC (Type Clearance Certificate). It was submitted that since the specification of the PIJF Cables required by the respondent CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 10 of 36  was a fresh specification, hence the petitioner applied for the Type Approval Certificate, which was issued on 09.09.2004.   As per the procedure   the   petitioner   was   then   to   take   PQT   Clearance/Bulk Production Clearance after obtaining the TAC which was immediately applied by the petitioner but PQT/Block Clearance was issued only on 30.10.2004   i.e.   after   more   than   two   months   from   the   date   of   the purchase order.  This fact was immediately brought to the notice of the petitioner/respondent vide its letter dated 28.10.2004.  It also requested for refixation of the delivery schedule enabling the petitioner to get all the required approvals and PQT done in time as the time to be taken for grant of the said clearance and certificate was beyond the control of the petitioner.

  It is submitted that the petitioner duly complied with the terms of the agreement and completed the supplies within the original delivery   period.     Thereafter,   in   respect   of   the   Purchase   orders   the petitioner   raised   the   bills.     However,   the   respondent   illegally   and arbitrarily   and   contrary   to   the   expressed   terms   of   Purchase   Order withheld a sum of Rs.34,36,695/­ allegedly towards the recovery of liquidated damages and on account of price variation in respect of the purchase   orders.     The   details   of   the   said   deductions   have   been mentioned as under:­ _________________________________________________________ Sl. No. P.O.No. & Date                DEDUCTIONS (Rs.)      LD        PV           Total

1.    P.O. No. AGM (MP­C)/MM­128/  10,58,780/­ 7,22,043/­  17,80,823/­        PIJF/P.O./2004­2005/VTL/30        dated 19.08.2004 for supply of 117        Kms. of 200/0.5(A) Cables and 60.4        Kms of 1200/0.5 (A) cables.

CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 11 of 36 

2.    P.O. No. AGM (MP­C)/MM­128/  3,46,234/­  2,51,888/­  5,98,122/­       PIJF/P.O./2004­2005/ VTL/53       dated 10.09.2004 for supply of 27       Kms. of 800/0.5 (UA)Cables.

3.   P.O. No. AGM (MP­C)/MM­128/ 3,34,206/­  1,53,820/­  4,88,026/­       PIJF/P.O./2004­2005/ VTL/57      dated 13.09.2004 for supply of      156 Kms. of 200/0.5 (A)Cables.

4.  P.O. No. MTNL­MUM/DWPE/GM  5,40,894/­  28,830/­  5,9,724/­     (MM)/16­28/VTL/04­05      dated 06.09.2004 for supply of      3.2 Kms. of 1200/0.5 (A)Cables     and 12.4 Kms. of  800/0.5(UA) Cables.

     Total:         22,80,114/­     14,77,707/­   34,36,695/­ _________________________________________________________ It   is   submitted   that   the   petitioner   informed   the respondents   that   the   respondents   have   wrongly   withheld   a   sum   of Rs.17,80,823/­, Rs.5,98,122/­, Rs.488,026/­ and Rs.5,69,724/­ against the Purchase Orders   dated 19.08.2004, 10.09.2004, 13.09.2004 and 06.09.2004 respectively and the petitioner requested the respondent to immediately release the wrongly withheld amount of Rs.34,36,695/­. The   respondents   despite   repeated   requests   failed,   neglected   and avoided   to   pay   the   wrongfully   withheld   amount   of   Rs.34,36,695/­. The   petitioner   vide   notice   dated   08.11.2005   invoked   the   arbitration agreement contained in the Purchase Orders and the tender documents. On 30.11.2005, the respondent vide their letter refused to pay the said amount.

The   petitioner   filed   its   claim   before   the   Ld.   Sole Arbitrator and the respondent also filed its Statement of Claim.   It is further   stated   that   the   petitioner   filed   an   application   u/s.   151   CPC before the Ld. Arbitrator submitting that the hearing may be adjourned till the decision of the Hon'ble High Court of Delhi in the petition u/s. 34 of the Act filed by its associate company M/s Birla Cable Limited CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 12 of 36  against the Award passed by the same Ld. Sole Arbitrator.  However, the   application   was   rejected.     Thereafter,   the   petitioner   filed   an application u/s. 12 and 13 of the Act before the Ld. Sole Arbitrator submitting that the Ld.  Arbitrator was  on the  regular panel   of the respondent   having   been   appointed   by   the   respondent   in   numerous cases and that the arbitrator was required to disclose the circumstances giving   rise   to   a   justifiable   doubt   as   to   the   independence   and impartiality of the Ld. Arbitrator and as no such disclosure had been made   either   at   the   time   of   the   accepting   the   appointment   or   even during the proceedings as required u/s. 12 of the Act and further as the Ld. Arbitrator had already decided the issue against the petitioner and as the Ld. Arbitrator would not pass an Award contrary to the Award passed in the case of M/s Birla Cable Limited and as there existed circumstances which gave rise to justifiable doubt in the mind of the claimant as to the independence and impartiality of the Arbitrator, the petitioner   requested   the   Ld.   Arbitrator   to   withdraw   from   the   case. However,   the   application   was   dismissed   without   even   issuing   any notice.

It   is   further   submitted   that   the   Ld.   Arbitrator   without appreciation of the facts as well as the law has passed the Award dated 10.06.2009 rejecting the claims, contrary to the law laid down by the Hon'ble Supreme Court.   It is submitted that the Ld. Arbitrator had wrongly   observed   that   the   respondent   were   entitled   to   liquidated damages since Clause 12 of the Purchase Order provided recovery of the liquidated damages and had also wrongly observed that the time was   of   the   essence   of   the   contract,   in   spite   of   the   fact   that   the agreement   between   the   parties   explicitly   provided   that   in   certain CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 13 of 36  contingencies extension of time would be available to the petitioner and in view of the judgment of the Hon'ble Supreme Court in  'Hind Construction Contractors Vs State of Maharashtra', (1979) 2 SCC 70 the observations of the Ld. Arbitrator were "per se  in curium".   It is further stated that the Award was also contrary to the terms of the agreement between the parties.  The Award and the orders dismissing the two applications have been challenged in the present petition u/s. 34 of the Act submitting that it was against the law laid down by the Hon'ble   Supreme   Court   in  'Hind   Construction   Contractors'   (supra) and  'Oil & Natural Gas Corporation Ltd. Vs. Saw Pipes Ltd.', 2005 (3) SCC 705.

The Award dated 10.06.2009 has been challenged on the following   grounds  inter   alia,  that   the   Ld.   Arbitrator   had   erred   in dismissing   the   application   filed   by   the   petitioner   for   awaiting   the decision of the Hon'ble High Court in the case of Birla Cable Limited; that the Ld. Arbitrator erred in dismissing the application filed by the petitioner u/s. 12 and 13 of the Act in limine; that the Ld. Arbitrator erred in not adjourning the matter till the disposal of the petition u/s. 34 of the Act by the Court; that the Ld. Arbitrator had already made up his   mind   before   delivering   the   Award;   that   there   was   a   justifiable doubt as to the independence or impartiality of the Ld. Arbitrator; that the Ld. Arbitrator had not disclosed his interest as required u/s. 12(1) (2)   of   the   Act   whereas   he   ought   to   have   withdrawn   from   the arbitration; that the Award dated 10.06.2009 was against public policy; that the Award dated 10.06.2009 was in violation of the provisions of Section 38(3) of the Act and was thus against public policy; that the Ld.   Arbitrator   erred   in   holding   that   the   respondents   are   entitled   to CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 14 of 36  liquidated damages merely because Clause 12 of the Contract provided for the recovery of the liquidated damages in case of the non­supply of the goods during the stipulated period whereas it was apparent that Clause 12 of the Purchase order read with Clause 16 of the Special Conditions of the contract made it evident that the Clause was penal in nature and a clause in terrorem; that Clause 12 of the Contract was a penal   clause   being   a   clause   in   terrorem   and,   therefore,   cannot   be enforced unless the respondents proved to have suffered actual loss and therefore, the Award was contrary to the terms agreed between the parties;   that   the   Ld.   Arbitrator   had   completely   ignored   the   three Awards passed by different Arbitral Tribunals unanimously holding that   the   first   portion   of   clause   12.2   was   a   penal   clause   and   the respondent was not entitled to claim any liquidated damages unless the actual loss suffered was proved beyond any shadow of doubt; that the Ld. Arbitrator erred in applying the ratio of the judgment in  'Hind Construction Contractors Vs. State of Maharashtra', (1979) 2 SCC 70 and that time was not intended to be of the essence of the contract as the contract between the parties contained clause relating to imposition of   penalty   and   extension   of   time   and   the   very   fact   that   time   was extended   in   this   case   showed   that   time   was   not   of   essence   of   the contract;   that   the   Ld.   Arbitrator   failed   to   distinguish   between   two clauses of Clause 12.2 and to notice that the first part was a penalty clause without actual loss or harm whereas the second part provided of liquidated   damages   if   substantial   harm   has   been   caused   and   that therefore, the mere penalty without actual loss could not have been recovered under Clause 12.2; that the Ld. Arbitrator failed to take into account the admitted fact that as per the agreement entered into by the CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 15 of 36  petitioner and the respondents, the petitioner has in fact supplied the entire   quantity   of   cables   within   the   original   or   extended   delivery period thereby providing no occasion for the respondent to recover any liquidated   damages   from   the   petitioner   and,   therefore,   the   Ld. Arbitrator had committed grave mistake in passing the Award;   that the Ld. Arbitrator had failed to appreciate that the petitioner could get the Type Approval Certificate  only on 09.09.2004 and 21.09.2004 and thereafter, the petitioner was to obtain PQT Clearance/Bulk Production Clearance which was issued on 29.10.2004 for 200 pair cables and 1200 pair cables and 24.11.2004 for 800 pair cables and the petitioner was granted the PQT Clearance only on 29.10.2004 and 24.11.2004 that is after two months of the issue of the Purchase Orders and still the petitioner supplied the entire quantity of cables within the original delivery period of four months thereby providing no occasion for the respondent to recover any liquidated charges from the petitioner.  

Thus, it was submitted that the recovery of the liquidated damages by the respondent for an additional sum of Rs.22,80,114/­ was illegal and contrary to Section 73 & 74 of the Contract Act and had been wrongly withheld by the respondent and the claimant was entitled to recover the said amount.   It is further submitted that the respondent had wrongly recovered a sum of Rs.7,22,043/­ against the Purchase Order dated 19.08.2004, a sum of Rs.2,51,888/­ against the Purchase Order dated 13.09.2004 and a sum of Rs.1,53,820/­ against the Purchase Order dated 06.09.2004 by wrongfully applying the price variation clause despite the fact that the cables were supplied within the   original   period   of   four   months.     It   is   submitted   that   the   Ld. Arbitrator failed to appreciate that the respondent had not made any CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 16 of 36  submission substantiating its action in recovering the price variation. Thus, it was submitted that the Ld. Arbitrator had committed serious error in interpreting Clause 12 and 11.5 of the Contract.  Thus, it was prayed that the Award dated 10.06.2009 be set aside. REPLIES OF THE MAHANAGAR TELEPHONE NIGAM LTD Replies were filed by the Mahanagar Telephone Nigam Limited (MTNL, for short) in both the petitions.  There is no dispute regarding the contract between the parties.   However, it is submitted that at the time of issuance of tender itself all prospective bidders were informed   about   the   TAC   (Type   Approval   Certificate)   which   they would be required to obtain with respect to the supply of cables and it was misconceived to allege that these specifications of PIJF cable was fresh   specifications   which   were   issued   to   the   petitioner   only   on 09.09.2004.  The respondent submitted that it was for the petitioner to ensure that it met the required specification in the tender on time.

In   respect   of   the   objections   filed   by   the   Birla   Cable Limited, the respondent denied that these facts had been brought to the notice of the respondent vide letter dated 04.10.2004 or that vide the said letter a request for refixing of the delivery schedule to enable the petitioner to get all the required approval of PQT in time and it is submitted that in view of the petitioner failure to supply the cables on time, a show cause notice was issued.   It was further submitted that keeping in view the need of the material, the delivery schedule was re­ fixed vide respondent's letter dated 04.01.2005.  It was denied that the petitioner vide letter dated 21.12.2004 had requested for refixing of the delivery period with regard to the Purchase Order dated 19.08.2004 and   denied   that   the   extension   letter   dated   04.01.2005   was   issued CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 17 of 36  belatedly.     It   was   submitted   that   the   decision   to   impose   liquidated damages   was   as   per   the   terms   and   conditions   agreed   between   the parties.  

It was further stated that the delay in delivery period with respect to the purchase order dated 27.08.2004 was clearly brought out before the Arbitral Tribunal by filing a detailed chart, which has not been disputed by the petitioner.  It has been submitted that though the communication   dated   17.05.2005   written   by   the   petitioner   was   a matter of record, it was denied that the amount of Rs.8,00,223/­ had been wrongly withheld or had to be returned to the petitioner.  

In   respect   of   M/s   Vindhya   Telelinks   Limited,   the respondent submitted that all bidders including the petitioner were put to notice that they would be liable to pay the liquidated damages in terms   of   the   contract   on   their   failure   to   adhere   to   the   prescribed delivery schedule and were also informed about the Type Approval Certificate and PQT to be got done in time.   It was stated that there was   delay   in   supplying   the   material   within   the   original   delivery schedule.  It has further submitted that the details of the deductions on account of the liquidated charges were clearly brought out in various communications which were in accordance with the various terms and conditions of the purchase orders issued by the respondent.   It was denied that the respondent had withheld any amount wrongly and there was no question of the refund of the sum of Rs.34,36,695/­ since the deductions   are   in   accordance   with   the   terms   and   conditions   of   the purchase orders.

It   was   further   stated   in   the   replies   submitted   by   the respondent MTNL to both the objection petitions, that merely because CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 18 of 36  some other Arbitral Tribunal had passed an Award in favour of the petitioner it did not mean that the present Arbitral Tribunal was also bound   to   pass   a   similar   Award   and   the   previous   Awards   had   no bearing  on  the   present   cases.     It  was   denied  that  the   Awards   were illegal or erroneous or in conflict with public policy.  It was reiterated that the Arbitral Tribunal had rightly held that the time was of essence of the contract as specific delivery schedule had been informed to the petitioner and extension was granted subject to liquidated damages. The respondent also submitted that it was entitled to price variation in terms of the contract.

In   response   to   the   other   objections   raised   by   M/s Vindhya   Telelinks   Limited,   the   respondent   submitted   that   merely because an identical matter had been challenged in the Hon'ble High Court it would constitute no reason for the arbitrator to stay the arbitral proceedings.  Further, merely because the Ld. Arbitrator had come to a conclusion and passed an Award in the case of an associate company it would not mean that the arbitrator was not independent and impartial. Such an interpretation would mean that no Court could hear a matter where it has decided a matter against a litigant in the past.  Moreover, the   mere   fact   that   the   Ld.   Arbitrator   had   been   appointed   in   other matters by the respondent would not mean that the arbitrator was not independent or impartial.   Therefore, it was submitted that both the applications were rightly dismissed by the Ld. Arbitrator.   For these reasons, the respondent prayed that both these sets of objections be dismissed.

ARGUMENTS The   arguments   of   the   Ld.   Counsel   for   the   petitioner CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 19 of 36  centred around the interpretation to the Clause 12.2 of the terms and conditions of the Contract.  According to the Ld. Counsel the Clause provided   for   two   separate   contingencies   one   was   a   simpliciter short/delayed supply and the other was a short/delayed supply which hampered the system.   It was in the latter case that there was legal injury   and   therefore,   there   was   no   need   to   prove   actual   damages. However,   in   the   first   case,   the   provision   was   in   terrorem   and   was actually a penalty.

It was submitted that there was delay in the performance of   the   contract   but   the   delay   was   attributable   to   the   Mahanagar Telephone Nigam Limited.   Further no loss had been caused to the Mahanagar Telephone Nigam Limited.   Therefore, the penalty clause could   not   be   enforced.     The   Ld.   Counsel   submitted   that   the   Ld. Arbitrator   had   failed   to   distinguish   the   two   parts.     Further,   despite other Awards being brought to the notice of the Ld. Sole Arbitrator in these matters, where the Arbital Tribunal had concluded that a similar provision was a penalty clause and without proof of actual damages the   award   of   reasonable   compensation   based   on   the   penalty   clause could  not have  been passed,  the  Ld.   Arbitrator  in  the  instant  cases allowed   the     Mahanagar   Telephone   Nigam   Limited   to   retain   the claimed amount.

It was submitted that such an interpretation of the Ld. Arbitrator   was   against   public   policy   as   it   was   against   the   law   as provided u/s. 73 and 74 of the Contract Act as well as the decision of the   Hon'ble   Supreme   Court   in  'Fateh   Chand   Vs   Balkishan   Dass', (1964) 1 SCR 515  and  Maula Bux Vs Union of India  (1969) 2 SCC

554.  Relying on the judgment of the Hon'ble Supreme Court in 'Oil & CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 20 of 36  Natural Gas  Corporation  Limited  Vs  Saw   Pipes  Limited',  (2203)  5 SCC 705, it was submitted that the Award was perverse and contrary to establish law and was liable to be set aside.  

The   further   contention   in   respect   of   M/s   Vindhya Telelinks Limited was that the Ld. Sole Arbitrator had not disclosed that he was a panel arbitrator.   He had already given an Award in favour   of   the   Mahanagar   Telephone   Nigam   Limited   therefore, disclosure was essential.  Since the disclosure was not made the entire proceedings were initiated and, therefore, the Award was liable to be set aside and another arbitrator be appointed.

The   Ld.   Counsel   for   the   respondent/Mahanagar Telephone   Nigam   Limited   however,   submitted   that   the   scope   of interference u/s. 34 of the Act was extremely limited.   Reliance has been placed on the judgment of the Hon'ble Supreme Court in case 'Associate Builders Vs Delhi Development Authority', (2015) 3 SCC 49 to point out that only where the Award was in conflict with public policy that the Court could looked into the Award.  Furthermore, what was the meaning of the word 'perverse' was specifically explained in this   case   and   the   parameters   were   not   fulfilled   in   the   present   two matters.

It was further submitted that the factual findings could not be interfered with by the Court while dealing with the objections u/s. 34 of the Act.  The Arbitrator was the sole interpretor of the terms of   the   contract   and   the   Court   could   not   interfere   with   such interpretation.     It   was   submitted   that   the   Clause   12.2   provided   for liquidated damages in graded manner and was a genuine estimate of loss and, therefore, the Ld. Arbitrator had rightly passed the Award CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 21 of 36  and it called for no interference.   Since the deductions made by the respondent were in terms of the Clause 12.2 which was not a penalty but was the agreed liquidated damages, no proof of actual damages had to be given and the conclusion drawn by the Ld. Arbitrator was fully lawful and legal and in­keeping with the policy of the country.   

Thus, relying on the judgment of the Hon'ble Supreme Court   in   'Oil   &   Natural   Gas   Corporation   Limited   Vs   Saw   Pipes Limited',   (2203)   5   SCC   705,  the   ld.   Counsel   for   the   respondent submitted that no ground for interference was made out.  It is further pointed out that the Arbitrator no doubt had been appointed in other cases but the petitioner itself had through its letter invited the same sole arbitrator to arbitrate the second case in  M/s Vindhya Telelinks Limited referring to the fact that he was the sole arbitrator in the Birla Cable Limited.  Thus, there were no merits in the objections now taken to the appointment of the Ld. Arbitrator in the second case and there was no cause to seek his recusal.  

The   Ld.   Counsel   for   the   objector/petitioner   however, reiterated that what was under challenge was not the interpretation of clauses,   since   the   Clause   12.2   could   be   subjected   to   only   one interpretation   and   what   was   in   question   was   the   application   of   the same.  It was further submitted that the objections were also covered u/s. 34 (2A)of the Act as there was patent illegality on the face of the Award, as the first part of the Clause 12.2 was a penalty clause and could not be interpreted in any other way and the conclusions drawn by the Ld. Arbitrator were liable to be set aside as no loss has been established before the Ld. Arbitrator.  

CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 22 of 36 

DISCUSSION Under Section 12 of the Act the arbitrator is bound to disclose any conflict in interest.  Such a disclosure can be made at any time in the course of the arbitration.  Reliance has been placed on the judgment of Hon'ble Supreme Court in 'Shakti Bhog Foods Limited Vs Kola Shipping Limited & Another', 2012 LawSuit(Del) 2147.   In that case it had been held that conflict of interest had occurred when the arbitrator in that case had failed to disclose that he had acted as co­ arbitrator   of   respondent   no.1   in   relation   to   a   dispute   between respondent no.1 and the head owners of the same vessel involved in the same transaction.  While the arbitrator has to disclose any previous engagement by one of the parties and such disclosure ought to be made in   writing,   there   is   a   difference   in   the   fact   situation   in   the   present objections.  The Ld. Sole Arbitrator was already seized of the dispute between   Birla   Cable   Limited   Vs   Mahanagar   Telephone   Nigam Limited when the subsequent dispute between M/s Vindhya Telelinks Limited Vs. Mahanagar Telephone Nigam Limited arose.

   In the case covered by  'Shakti Bhog Foods Limited's case (supra) the petitioner had no knowledge of the conflict of interest. In   the   present   matter   when   the   second   case   arose   between   M/s Vindhya Telelinks Limited Vs. Mahanagar Telephone Nigam Limited it   was     M/s   Vindhya   Telelinks   Limited   who   wrote   a   letter   to   the Mahanagar   Telephone   Nigam   Limited   on   08.11.2005   seeking   the appointment of Mr. Justice Harbans Lal (Retd.) on the ground that a 'similar case' wherein similar law and facts are involved namely, Birla Cable Limited had been referred to him.  The copy of the appointment letter   was   also   enclosed.     A   further   request   was   made   to   the CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 23 of 36  Mahanagar Telephone Nigam Limited in the following words:

"If you so desire you can appoint Hon'ble Justice  Harbans Lal (Retd.) as the Sole Arbitrator in the present dispute or any other retired High Court Judge".

In these circumstances clearly the present petitioner had waived any objections to the appointment of Hon'ble Justice Harbans Lal (Retd.) as the Sole Arbitrator in the dispute between M/s Vindhya Telelinks   Limited   Vs   Mahanagar   Telephone   Nigam   Limited.     Just because the Ld. Sole Arbitrator returned the findings against the Birla Cable   Limited   in   its   dispute   with   Mahanagar   Telephone   Nigam Limited objection was raised regarding his impartiality.  The same was rightly  dismissed by  the   Ld.  Sole  Arbitrator.    Impartiality  certainly does not hinge on the opinion of the losing party or for that matter the successful party.

The other grouse of the petitioner in Vindhya Telelinks Limited's case is that an application made to the Ld. Sole Arbitrator to hold the Award till the decision in the objection petition filed by Birla Cable Limited was rejected unfairly, has also no merit.  The objections filed were in an independent matter.  Moreover, the Ld. Sole Arbitrator was not expected to wait for the disposal of the objections filed in 2008 which would have been dealt with in the course of the regular hearings of matters by the Hon'ble High Court. Such expectation has no reasonableness.  The Ld. Sole Arbitrator therefore, rightly declined to withhold the Award till the disposal of the objections filed u/s. 34 of the Act against the other Award passed by the Sole Arbitrator in Birla Cable Limited's case.

Therefore,   the   dismissal   of   these   applications   has   not CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 24 of 36  vitiated the Award dated 10.06.2009 in Vindhya Telelinks Limited.

The   Superior   Courts   have   over   a   period   of   time repeatedly defined the scope of powers of the Court dealing with the objections filed u/s. 34 of the Act.   In 'P.R. Shah, Shares and Stock Brokers Private Limited Vs B.H.H. Securities and others', (2012) 1 SCC 594  it was held as under:

"A Court does not sit in appeal over the award of an  Arbitral Tribunal by reassessing or re­appreciating the  evidence.  An Award can be challenged only under the   grounds mentioned in Section 34(2) of the Act......"

Therefore, in the absence of any ground u/s. 34 (2) of the Act, it is not open to the Court to re­examine the facts to determine whether a different decision could be arrived at.

The   Hon'ble   Delhi   High   Court   in   State   Trading Corporation   of   India   Limited   Vs   Toepfer   International   Asia.   PTE Limited has held as under:

"A Section 34 proceedings, which in essence is the  remedy of annulment, cannot be used by one party to  convert the same into a remedy of appeal.  In our view,  mere erroneous/wrong finding of fact by the Arbitral  tribunal or even an erroneous interpretation of  documents/evidence is non­interferable under Section 34 and if such interference is done by the Court, the same  will set at naught the whole purpose of amendment of the Arbitration Act."  Again,  "The remedy provided in Section 34 against an arbitral  award is in no sense an appeal.  The legislative intent in  CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 25 of 36  Section 34 was to make the result of the annulment  procedure prescribed therein  potentially different from  that in an appeal.  In appeal, the decision under review  not only may be confirmed, but may also be modified.  In annulment, on the other hand, the decision under review  may either be invalidated in whole or in part or be left to stand if the plea for annulment is rejected......."
"Section 34 is found to provide for annulment only on   the grounds affecting legitimacy of the process of  decision as distinct from substantive correctness of the   contents of the decision......" 
"Annulment in the case of arbitration focuses not on the  correctness of decision but rather more narrowly  considers whether, regardless of errors in application of  law or determination of facts, the decision resulted from  a legitimate process."

The   Hon'ble   Supreme   Court  in  'Associate   Builders   Vs Delhi   Development   Authority'   (2015)   3   SCC   49  held   that   "  an arbitration award can be set aside under the Act only on the grounds mentioned u/s 34(2) (a) & (iii) and not otherwise".   It was noted by the Hon'ble Supreme Court that none of the grounds contained in sub­ section (2)(a) of Section 34 dealt with merits of the decision rendered by an arbitral award.  It was only when the award is in conflict with the public policy of India the Court could look into the merits of the arbitral award under certain specified circumstances.

Section 34 of the Arbitration & Conciliation Act, 1996 reads as under:­ CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 26 of 36  "(2) An arbitral award may be set aside by the Court  only if­

  (a) the party making the application furnishes proof  that­ (I) a party was under some incapacity; or

(ii)the arbitration agreement is not valid under the law  to which the parties have subjected it or, failing any  indication thereon, under the law for the time being in   force; or

(iii)the party making the application was not given  proper notice of the appointment of an arbitrator or of  the arbitral proceedings or was otherwise unable to  present his case; or 

(iv)the arbitral award deals with a dispute not  contemplated by or not falling within the terms of the  submission to arbitration, or it contains decisions on  mattes beyond the scope of the submission to arbitration:

Provided that, if the decisions on matters submitted to   arbitration can be separated from those not so  submitted, only that part of the arbitral award which  contains decisions on matters not submitted to  arbitration may be set aside; or
(v)the composition of the arbitral tribunal or the arbitral procedure was not in accordance with the agreement of  the parties, unless such agreement was in conflict with a  provision of this Part from which the parties cannot  derogate, or, failing such agreement, was not in  accordance with this Part; or
(b)the Court finds that­
(i)the subject­matter of the dispute is not capable of  settlement by arbitration under the law for the time  being in force, or
(ii)the arbitral award is in conflict with the public policy  of India.

After the amendment on 2015 the additional explanation and sub­section 2(a) has been added which is as follows:­ (1) in sub­section (2), in clause (b), for the Explanation,  the following Explanations shall be substituted, namely:­ CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 27 of 36  "Explanation 1­ For the avoidance of any doubt, it is clarified that an award is in conflict with the public policy of India, only if,­

(i) the making of the award was induced or affected by fraud or corruption or was in violation of section 75 or section 81; or

(ii)it is in contravention with the fundamental policy of Indian law; or

(ii)it is in conflict with the most basic notions of morality or justice.

Explanation 2­For the avoidance of doubt, the test as to whether there is a contravention with the fundamental policy of Indian law shall not entail a review on the merits of the dispute.

(II) after sub­section (2) the following sub­section shall be inserted, namely:­"

2(A) An arbitral award arising out of arbitrations other than international commercial arbitrations, may also be set aside by the Court, if the Court finds that the award is vitiated by patent illegality appearing on the face of the award;
Provided that an award shall not be set aside merely on the ground of an erroneous application of the law oar by re­appreciation of evidence."

In the present case the arguments have been centered on the arbitral award being in conflict with public policy of India (Section 34 (2)(b)(ii)) and of being vitiated by patent illegality apparent on the face of the Award (Section 34(2)A).   The Hon'ble Supreme Court in 'Oil & Natural Gas Corporation Ltd.'s case (supra) had interpreted the phrase "public policy of India" used in the Section 34.  It was held that an Award could be set aside, if it is contrary to :

(a) fundamental policy of Indian law; or
(b) the interest of India; or 
(c) justice or morality; or
(d) if it is patently illegal.

Legality   must   go   to   the   root   of   the   matter   and   if   the CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 28 of 36  illegality is of a grave nature it can be said that the Award is against Public Policy.  It was held that the Award could also be set aside if it is so unfair and unreasonable that it shocks the conscience of the Court. Such   an   Award   was   also   held   to   be   opposed   to   public   policy   and required to be adjudged void.

Similarly,   the   Hon'ble   Supreme   Court   in   "Associate Builder's case (supra) explained what was the fundamental policy of the   Indian   Laws,   interest   of   India,   justice   or   morality   and   patent illegality   while   cautioning   that   when   a   Court   was   applying   'public policy' test to an arbitration award, it did not act as a Court of appeal and consequently errors of fact cannot be corrected.   It was further held that a possible view by the arbitrator on facts has necessarily to pass muster as the arbitrator is the ultimate master of the quantity and quality of the evidence relied upon which he delivers his arbitral award and that once it was found that the arbitrator's approach is not arbitrary or capricious then he was the last word on the facts.

Ld. Counsel for the objector submitted that the awards in question were perverse as they disregarded the orders of the superior Courts   and   was   perverse   as   it   allowed   the   Mahanagar   Telephone Nigam Limited to recover liquidated damages which were actually in the   nature   of   penalty.     On   the   other   hand,   Ld.   Counsel   for   the respondent submitted that none of the tests laid down in the  'Oil & Natural Gas Corporation Ltd.'s case (supra) were satisfied by way of the present challenge.

From the aforegoing discussion, it is clear that when this Court   is   dealing   with   the   objections   u/s.   34   of   the   Act,   this   Court cannot sit as a Court in appeal and has only a limited role, merely to CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 29 of 36  see whether the Award passed is against the 'public policy' of India or is   patently   illegal   or   perverse.     The   present   case   is   one   where   the decision hinges on the interpretation of Clause 12.2 of the Purchase Orders and Clause 16.2 of the General (Commercial) Conditions of Contract   and   Clause   13.2   (   in   one   Purchase   Order   in   relation   to Vindhya Telelinks Limited).

Before proceeding further, it may be noted that before considering the question whether the Ld. Arbitrator had come to the conclusion in violation of the statute and the judgment of the Hon'ble Supreme Court that actual loss was not required to be proved; it is necessary to consider the Clauses itself, as that question would depend on   the   interpretation   of   the   Clause.     The   submissions   of   the   Ld. Counsel   for   the   petitioners   that   it   was   not  the   interpretation   of   the Clause but its application that was in question by means of the present objections   is   rhetorical.     The   arguments   before   this   Court   had  also been   on   how   to   interpret   the   Clauses   in   question   and   not   its application.

Thus, while the Ld. Counsel for the respondent submitted that the Clause 12.2 provided for graded liquidated damages, the ld. Counsel for the petitioner argued that the Clause had two parts, one which was a pure penalty and the other which provided for liquidated damages.   It was therefore, the contentions of the Ld. Counsel that since the part applied in the present cases by the respondent was the first part as there was no material hampering to the installation and commissioning   of   the   system   and   was   merely   delay   in   supply   of stores/consignment actual proof of loss had to be proved before the penalty could be invoked or a reasonable compensation granted to the CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 30 of 36  respondent.    Therefore,   all these  submissions  made   on the  basis  of 'Fateh Chand's case and Maula Bux's case (supra) and Section 73 and 74 are not determinative of the question as to whether the Award is perverse as it is first to be determined whether the conclusion of the Ld. Arbitrator that the Clause was not a penalty Clause was wrong.

The   Clause   for   liquidated   damages   is   mentioned   as Clause 16.2 in the General (Commercial) Conditions of Contract and the   same   is   reproduced   in   all   the   purchase   orders   (except   one)   as Clause 12.2.   In one Purchase Order dated 06.09.2004 the Clause is 13.2.   This Clause is re­produced as under:­ "Should   be   supplier   fails   to   deliver   the   store   or   any consignment   thereof   within   the   period   prescribed   for   delivery,   the purchaser shall be entitled to recover 0.5% of the value of the delayed supply   for   each   week   of   delay   or   part   thereof   for   a   period   upto 10(TEN) weeks and thereafter at the rate of 0.7% of the value of the delayed supply for each week of delay or part thereof for another TEN weeks   of   delay.     In   the   case   of   package   supply   where   the   delayed portion   of   the   supply   materially   hampers   installation   and commissioning of the systems, L/D charges shall be levied as above on the total value of the concerned package of the PO.  Quantum of L/D assessed   &   levied   by   the   purchaser   shall   be   final   and   not challengeable by the supplier.  However, when supply is made within 21   days   of   QA   clearance   in   the   extended   delivery   period,   the consignee may accept the stores and in such cases the LD shall be levied upto the date of QA clearance."

The Ld. Arbitrator in deciding the claim of Birla Cable Limited held that the contention of the petitioner, being the claimant CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 31 of 36  before it, that as there was no evidence regarding any loss having been suffered,   the   liquidated   damages   cannot   be   imposed   could   not   be accepted   in   view   of   Clause   12   of   the   Contract   which   clearly   laid down/provided that in case supplies are not made during the stipulated period   as   originally   fixed   or   extended,   the   respondent   would   be entitled to the liquidated damages according to the formula provided in Clause 12.  It was further held that the contention was not sustainable as there was clear stipulation regarding the levy of liquidated damages in case of non supply or delayed supply of contracted goods.   The same   observations   were   made   while   the   disposing   of   the   claim   of Vindhya Telelinks Limited that Clause 12 provided for the recovery of liquidated damages on the basis of the formula.

While   dealing   with   the   claim   of   Vindhya   Telelinks Limited three Awards were placed before the Ld. Arbitrator one dated 12.03.2003   in   Haryana   Telecom   Limited   Vs   MNTL,   Award   dated 19.06.2007 in Haryana Telecom Limited Vs Union of India and Others and Award dated 07.08.2007 in Haryana Telecom Vs Union of India and Others, whereas the respondent relied on the observations of the Hon'ble Supreme Court in Oil & Natural Gas Corporation Ltd.'s case (supra).   Considering these Awards and judgment relied upon by the parties, the Ld. Arbitrator concluded that even as per the judgment of the Hon'ble Supreme Court, in case of a breach of contract, the Court may award the amount of compensation as agreed to by the parties at the time of the contract, if it was a case of genuine pre­estimate of damages   by   the   parties   and   that   the   same   can   be   up­held   as   a reasonable compensation.  It was concluded by the Ld. Sole Arbitrator that the  parties  had  agreed that in case  of  delay the  purchaser was CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 32 of 36  entitled to liquidated damages  on the basis of formula as specifically laid down in Clause 12.2 and in view of the terms of the contract, the provision of liquidated damages cannot be held to be penalty and was a   clear   pre­estimate   of   damages   in   case   of   delay   in   supply   and liquidated damages that the respondent was entitled to on the basis of the formula, cannot be held to be unreasonable compensation.  

By relying on the Awards passed in the aforementioned cases,   the   Ld.   Counsel   for   the   petitioner   has   submitted   before   this Court that the Ld. Arbitrator had erred.  According to the Ld. Counsel the Clause reproduced hereinabove had two parts, which was the view taken by the previous Arbitral Tribunals.

   It was the contention of the Ld. Counsel that the Ld. Sole Arbitrator ought to have followed the conclusions in the Awards passed in Haryana Telecom's cases by the various Arbitral Tribunals that the language of a similar Clause in those contracts providing for a payment of damages for mere delay at a particular rate was a penalty clause.

 There is no merit in this submissions of the Ld. Counsel as Awards passed by one Arbitral Tribunal are not binding in nature and act as a precedent for other Arbitral Tribunals.  Moreover, the Ld. Sole Arbitrator has relied on the observations made by the Hon'ble Supreme Court in 'Oil & Natural Gas Corporation Ltd.'s case (supra) to   hold   that   the   Clause   provided   for   a   genuine   pre­estimate   of   the damages as in the present case it was clearly understood by the parties to the contract that time was essence of the contract and the delivery period was specifically provided for and in case of delay both parties agreed that the purchaser was entitled to liquidated damages on the CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 33 of 36  basis of a formula as specifically laid down in Clause 12.2.

The   reasoning   given   for   arriving   at   such   a   conclusion cannot be discarded as "perverse" or against "public policy".  Even if two views are possible, the adoption of one view by the arbitrator per se would not constitute perversity.  The very words used in the Clause 12.2 are explicit.  Delayed supplies would be resulting in payment of liquidated   damages.     The   Ld.   Sole   Arbitrator   rightly   described   the terms as providing for a "formula' which clearly was agreed to by the parties.  The loss on account of delay was assessed at the time of the contract and the graded method of determining the liquidated damages on the basis of value was agreed to.  Therefore, no part of the clause is a penalty.  In fact the arguments before this Court has been that by not calling upon the respondents to prove actual damages the Award was perverse.  But when the Ld. Arbitrator has come to a conclusion that the Clause 12.2 provided for liquidated damages for reasons given and was not in the nature of a penalty, the Award does not suffer from any perversity just because no evidence of loss was brought on record, as there was no need to prove actual damage/loss if the clause was not in the nature of a penalty.

Arguments were also addressed on the question of the Ld. Arbitrator holding that there was delay and also awarding price variation.  In fact there is no dispute that there was delay in supplies. Moreover, a Court does not sit in appeal over the Award of an Arbital Tribunal by reassessing or re­appreciating the evidence as was held by the Hon'ble Supreme Court in 'P.R. Shah, Shares and Stock Brokers Private   Limited's   case   (supra).    In   that   case   the   Hon'ble   Supreme Court also held  that it was not possible to re­examine the facts to find CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 34 of 36  out a  different  decision could be  arrived at  which  is  what is  being sought by means of the present objection petitions.

Once   the   Ld.   Arbitrator   came   to   the   conclusion   that Clause 12.2 provided for liquidated damages, the question of the need for proof of actual damages does not arise and, therefore, the citations in this regard call for no further discussion as to how damages/penalty ought   to   have   been  calculated.     It   may  be   also  mentioned  that   the judgment of the Hon'ble High Court in 'Haryana Telecom Limited Vs Union of India and Another, AIR 2006 Delhi 339 is distinguishable on facts, as the Clause that required interpretation was different and facts regarding the acceptance of delayed delivery were also different.   In the   present   case   Clause   12.2   (13.2   in   one   Purchase   Order)   clearly underlines the necessity to adhere to the supply schedule.  The Clause 12.2 provided for the acceptance of the delayed supplies by grading the   damages   for   different   short   supplies   payment   of   which   would regularise   such   delayed   supplies   unlike   in   the   case   of  Haryana Telecom   Limited   (supra)  and   also   does   not   provide   for   any   other authority to approve of the delayed supplies.

It   has   been   repeatedly   held   by   the   Hon'ble   Supreme Court   including   in  'M/s   Construction   &   Design   Services   Vs.   DDA' decided   on   04.02.2015,   where   it   has   been   reiterated   that   where   a genuine   pre­estimate   has   been   provided   for   there,   was   no   need   to prove actual damages.

In the light of this aforegoing discussion, therefore, the objections   filed   by   Birla   Cables   Limited   to   the   Award   dated 16.07.2008 and the objections filed by Vindhya Telelinks Limited,  to the Award dated 10.06.2009 being devoid of merits are dismissed.

CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017 Page 35 of 36 

The records of the Ld. Arbitrator be returned alongwith a copy of the judgment.

The original judgment be placed on the records of Birla Cable Limited's case CIS­ARBTN­313­2017 and copy be placed on the   records   of  Vindhya   Telelinks   Limited's   case   bearing   no.  CIS­ ARBTN­312­2017.

The files be consigned to the Record Room.




Announced in open Court 
today i.e. 18.12.2017                               (ASHA MENON)    
                                         District & Sessions Judge (South)
                                                    Saket/New Delhi.




CIS­ARBTN­313­2017 & CIS­ARBTN­312­2017                                Page 36 of 36