[Cites 0, Cited by 0]
[Section 11]
[Entire Act]
State of Odisha - Subsection
Section 11(2) in Orissa Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulation, 2005
| Phase | Eligibility criteria | Commencement date |
| 1. | Requiring power exceeding 5 MW | April 1, 2008 |
| 2. | Requiring power exceeding 2 MW | October 1, 2008 |
| 3. | Requiring power exceeding 1 MW | January 1, 2009 |
| Phase | Eligibility criteria | Commencement date |
| 1. | Requiring power exceeding 5 MW | August 1, 2005 |
| 2. | Requiring power exceeding 2 MW | April 1, 2006 |
| 3. | Requiring power exceeding 1 MW | April 1, 2008 |