State of Odisha - Section
Section 11 in Orissa Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulation, 2005
11. Phasing of open access.
| Phase | Eligibility criteria | Commencement date |
| 1. | Requiring power exceeding 5 MW | April 1, 2008 |
| 2. | Requiring power exceeding 2 MW | October 1, 2008 |
| 3. | Requiring power exceeding 1 MW | January 1, 2009 |
| Phase | Eligibility criteria | Commencement date |
| 1. | Requiring power exceeding 5 MW | August 1, 2005 |
| 2. | Requiring power exceeding 2 MW | April 1, 2006 |
| 3. | Requiring power exceeding 1 MW | April 1, 2008 |