State of Maharashtra - Section

Section 38 in The Maharashtra Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2005

38. Rebate/Late payment surcharge.

- 38.1 For payment of bills through a letter of credit on presentation, the Generating Company and Distribution Licensee may mutually agree to a maximum rebate of 2 per cent of the bill amount. If the payments are made within one week of presentation of the bill, the Generating Company and Distribution Licensee may mutually agree to a maximum rebate of 1.25 per cent of the bill amount.
38.2In case the payment of bills is delayed beyond a period of two (2) months from the date of billing, a late payment surcharge at the rate of 1.25 per cent per month shall be allowed to be levied by the Generating Company.