13. Truing up of tariff for the period 2019-24.

(1)The Commission shall carry out truing up exercise for the period 2019-24 along with the tariff petition filed for the next tariff period, for the following:
(a)the capital expenditure including additional capital expenditure incurred up to 31.3.2024, as admitted by the Commission after prudence check at the time of truing up:
(b)the capital expenditure including additional capital expenditure incurred up to 31.3.2024, on account of Force Majeure and Change in Law.
(2)The generating company or the transmission licensee, as the case may be, shall make an application, as per Annexure-I to these regulations, for carrying out truing up exercise in respect of the generating station or a unit thereof or the transmission system or an element thereof by 30.11.2024.
(3)The generating company or the transmission licensee, as the case may be, may make an application for interim truing up of tariff in the year 2021-22, if the annual fixed cost increases by more than 20% over the annual fixed cost as determined by the Commission for the respective years of the tariff period:Provided that if the actual additional capital expenditure falls short of the projected additional capital expenditure allowed under provisions of Chapter 7 of these regulations, the generating company or the transmission licensee, as the case may be, shall not be required to file any interim true up petition for this purpose and shall refund to the beneficiaries or the long term customers, as the case may be, the excess tariff recovered corresponding to the projected additional capital expenditure not incurred at the bank rate as on 1st April of the respective years, under intimation to the Commission:Provided further that the generating company or the transmission licensee shall submit the complete details along with the calculations of the refunds made to the beneficiaries or the long term customers, as the case may be, at the time of true up.
(4)After truing up, if the tariff already recovered exceeds or falls short of the tariff approved by the Commission under these regulations, the generating company or the transmission licensee, shall refund to or recover from, the beneficiaries or the long term customers, as the case may be, the excess or the shortfall amount along with simple interest at the rate equal to the bank rate as on 1st April of the respective years of the tariff period in six equal monthly instalments.Chapter - 4 Tariff Structure