Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 8, Cited by 84]

Supreme Court of India

Hindustan Steel Works Construction Ltd vs C. Rajasekhar Rao on 27 July, 1987

Equivalent citations: 1987 SCR (3) 653, 1987 SCC (4) 93, AIRONLINE 1987 SC 484

Author: Sabyasachi Mukharji

Bench: Sabyasachi Mukharji, G.L. Oza

           PETITIONER:
HINDUSTAN STEEL WORKS CONSTRUCTION LTD.

	Vs.

RESPONDENT:
C. RAJASEKHAR RAO

DATE OF JUDGMENT27/07/1987

BENCH:
MUKHARJI, SABYASACHI (J)
BENCH:
MUKHARJI, SABYASACHI (J)
OZA, G.L. (J)

CITATION:
 1987 SCR  (3) 653	  1987 SCC  (4)	 93
 JT 1987 (3)   239	  1987 SCALE  (2)218


ACT:
    Arbitration	 Act, 1940: Sections 3, 28 and	33--Arbitra-
tion  proceedings-Not to be unduly prolonged--Whether  Court
has  power  to extend time for giving award after  award  is
made--Award--When  can	be set aside  Reasons not  given  by
arbitrator--Whether  court entitled to speculate  and  probe
mental process by which arbitrator reached conclusion.



HEADNOTE:
    There was an Agreement between the respondent-contractor
and the appellant-construction company in respect of certain
works.	Differences and disputes arose and there  were	pro-
ceedings  before the arbitrators named in the Agreement.  As
the arbitrators could not agree and there were	differences,
this  Court by an Order dated 16th June, 1983 directed	that
the arbitrators appointed by each of the parties be appoint-
ed  arbitrators	 and if there was disagreement	between	 the
arbitrators, the matter was to be referred to the Umpire. In
pursuance of the said directions the parties appeared before
the  arbitrators who referred the matter to the	 Umpire	 and
the  Umpire  after consideration made an  award	 dated	15th
July, 1985.
    The	 petitioner-construction company made a petition  to
this  Court  for a decree in terms of the award,  which	 was
opposed by the respondent-contractor contending that (a) the
Umpire	had made a speaking award and that the	validity  or
otherwise  of the said award was justifiable in a  Court  of
law, (b) that the Umpire had no jurisdiction to proceed with
the  arbitration  on  or about 18th December,  1984  as	 the
period of two months from the date of his entering upon	 the
reference had expired and consequently the award was  beyond
time,  and (c) that the award contained error of law on	 the
face of the award and there were inconsistent findings.
The Court while confirming the award,
    HELD: 1.1 The policy of law is that arbitration proceed-
ings should not be unduly prolonged. The arbitrator,  there-
fore,  has to give the award within the time prescribed,  or
such extended time as the
654
court concerned may in its discretion extend, and the  Court
alone had been given the power to extend the time for giving
the award. [656E]
    1.2	 The Court has got power to extend time	 even  after
the  award has been given or after the expiry of the  period
prescribed for the award. But the court has to exercise	 its
discretion  in a judicial manner. This power could be  exer-
cised even by the appellate court. [656F]
    1.3 The arbitrator gets the jurisdiction to enlarge	 the
time for making the award only in a case where after  enter-
ing  on	 the  arbitration, the parties	to  the	 arbitration
agreement consent to such enlargement of time. [657B]
    In	the instant case, in view of the policy of law	that
the  arbitration proceedings should not be unduly  prolonged
and  in view of the fact that the parties have	been  taking
willing part in the proceedings before the arbitrator  with-
out  a demur and had all along been willing to extend  time,
this  will be a fit case for the extension of time, and	 the
time  for giving the award is accordingly extended  and	 the
award will be deemed to have been given in time. [656F-G]
    2.1	 An  award might be set aside by the  court  on	 the
ground	of error on the face of the award, but an  award  is
not  invalid  merely because by a process of  inference	 and
argument,  it might be demonstrated that the arbitrator	 had
committed some mistake in arriving at his conclusion. [657D]
    Jivarajbhai	 Ujamshi  Sheth and others  v.	Chintamanrao
Balaji and others, [1964] 5 S.C.R. 480, followed.
    2.2	 Only in a speaking award the Court could took	into
the  reasoning of the award. It is not open to the Court  to
speculate, where no reasons are given by the arbitrator,  as
to what impelled him to arrive at his conclusion. It is also
not open to the Court to attempt to probe the mental process
by which the arbitrator had reached his conclusion where  it
is not disclosed by the terms of his award. [657D, H, 658A]
    The	 instant  case is not one of a speaking	 award.	 The
Umpire	had not spoken his mind indicating why he has  done,
what  he has done, he has narrated only how he came to	make
the  award.  No reasons have been given for the	 purpose  of
making the award. There is no legal proposition in the award
which  is  unsustainable or improper. The challenge  to	 the
award cannot, therefore, be accepted. [659G-H]
655
    State  of  Punjab v. Sri Hardyal, [1985] 3	S.C.R.	649;
H.K. Wattal v. V.N. Pandya, [1974] 1 S.C.R. 259 and Chempsay
Bhara  and  Company v. Jivraj Balloo  Spinning	and  Weaving
Company Ltd., L.R. 50 I.A. 324, referred to.
    CIVIL  APPELLATE JURISDICTION: Civil Misc. Petition	 No.
28356 of 1986.
IN



JUDGMENT:

CIVIL APPEAL No. 5579 of 1983.

From the Judgment and Order dated 22.4.1983 of the Andhra Pradesh High Court in Civil Rev. Petn. No. 2626 of 1982.

Dr. Shanker Ghose and P.P. Singh for the Appellant. S. Markandeya and C. Markandeya for the Respondent. The Judgment of the Court was delivered by SABYASACHI MUKHARJI, J. This is an application filed by the Hindustan Steelworks Construction Company Limited for filing the award of the Umpire appointed by this Court, Shri Justice Jaganmohan Reddy, retired Judge of this Court and for passing a decree in terms of the said award. It appears that there was an agreement between Shri Rajasekhar Rao, the contractor and the Hindustan Steelworks Construction Limit- ed, petitioner, in respect of certain works. Differences and disputes arose, and there were proceedings before the arbi- trator named in the Agreement and there were certain pro- ceedings, the detail of which is not necessary to refer. As the arbitrators could not agree, there were differences. This Court by an order dated 16th of June, 1983 directed that arbitrators appointed by each of the parties be ap- pointed arbitrator to adjudicate upon the dispute between the parties. It was stipulated therein that in the said order of this Court dated 16th of June, 1983, it would be no longer open to the party to question the validity of the appointment of the arbitrators. In the event of any disa- greement between the two arbitrators, Shri Jaganmohan Reddy, a former Judge of this Court was directed to act as the Umpire. Further consequential directions were also given. Thereafter the parties appeared before the arbitrators and referred the matter to the umpire. The Umpire after consid- eration has made the award dated 15th of July, 1985 which has been filed in this 656 Court and the petitioner seeks a decree in terms of the award. The respondent-contractor, Shri Rajasekhar Rao ob- jects to the award being made a rule of the Court. He states in his objections that the umpire had made a speaking award, therefore according to his counsel the validity or otherwise of the said award was justifiable in a court of law. He, however, firstly contends that the award was made beyond time. He further contends that the umpire had no jurisdiction to proceed with the arbitration on or about 18th of December, 1984 as the period of two months from the date of his entering upon the reference viz, October 20, 1984 had expired on December 18, 1984. According to the said objections, the umpire became functus-officio. It was con- tended that the power to extend the period of passing the award was vested in the court alone under section 28 of the Arbitration Act and it was not permissible for the parties to extend the time. We are unable to accept this position. Mr. Markendeya drew our attention to certain observations of this Court in the case of State of Punjab v. Sri Hardyal, [1985] 3 S.C.R. 649. He relied on the observations of the Court at page 656 and emphasised that law precludes parties from extending time after the matter had been referred to the arbitrator, it would be contradiction in terms to hold that the same result could be brought about by the conduct of the parties. These observations, in our opinion, are out of the context. The policy of law is that the arbitration proceedings should not be unduly prolonged. The arbitrator therefore has to give the award within the time prescribed or such extended time as the court concerned may in its discretion extend and the court alone has been given the power to extend time for giving the award. The court has got the power to extend time even after the award has been given or after the expiry of the period prescribed for the award. But the court has to exercise its discretion in a judicial manner. In that case this Court found that the High Court was justified in taking the view that it did. This power, however, could be exercised even by the appellate court. In view of the policy of law that the arbitration proceedings should not be unduly prolonged and in view of the fact that the parties have been taking willing part in the proceedings before the arbitrator without a demur and had all along been willing to extend time, this will be a fit case, in our opinion, for the extension of time. We accordingly extend the time for giving the award and the award will be deemed to have been given in time. In this case, it appears that under section 28 and in the light of section 3 of the First Schedule the parties are allowed to extend the time. In this connection reference may be made to H.K. Wattal v. V.N. Pandya, [1974] 1 S.C.R. 259, where this Court 657 reiterated that sub-section (2) of section 28 indicated one exception to the above rule that the arbitrator could not enlarge the time, and that was when the parties agreed to such an enlargement. It is clear this Court reiterated that the arbitrator gets the jurisdiction to enlarge the time for making the award only in a case where after entering on the arbitration the parties to the arbitration agreement consent to such enlargement of time. In this case precisely it happened. Furthermore the parties have proceeded before the umpire on that basis which is just and proper and further- more the time should be extended as was done in the case of State of Punjab v. Sri Hardyal, (supra). In the aforesaid view of the matter we are unable to accept the submission on behalf of Shri Markendeya that the award of the umpire was beyond time.

It was next contended that the award contained error of law on the face of the award and there were inconsistent findings. It has to be borne in mind that it was only in a speaking award that the court could look into the reasoning of the award. In the case of Jivarajbhai Ujamshi Sheth and others v. Chintamanrao Balaji and others, [1964] 5 S.C.R. 480, this Court observed that an award might be set aside by the court on the ground of error on the face of the award, but an award was not invalid merely because by a process of inference and argument it might be demonstrated that the arbitrator had committed some mistake in arriving at his conclusion. The law on this point is well-settled. The Judicial Committee in Chempsey Bhara and Company v. Jivraj Balloo Spinning and Weaving Company Ltd. L.R. 50 I.A. 324 clarified that an error of law on the face of the award means, that one could find in the award or a document actu- ally incorporated thereto, as for instance a note appended by the "arbitrator stating the reasons for his judgment, some legal proposition which is the basis of the award and which one could then say was erroneous. It did not mean that if in narrating a reference was made to a contention of one party, that opened the door to seeing first what that con- tention was, and then going to the contract on which the parties' rights depended to see if that contention was sound". It has been further reiterated by this Court in the aforesaid decision relying on Chempsey Bhara and Company's case (supra) that in dealing with an application to set aside an award the court had not to consider whether the view of the arbitratorr on the evidence was justified. The arbitrator's adjudication was generally considered binding between the parties, for he was the tribunal selected by the parties and the power of the Court to set aside the award was restricted to cases set out in section 30 of the Arbi- tration Act. It is not open to the court to speculate, where no reasons are 658 given by the arbitrator, as to what impelled the arbitrator to arrive at his conclusion. It is not open to the Court to attempt to probe the mental process by which the arbitrator had reached his conclusion where it is not disclosed by the terms of his award. In this case this is not a speaking award. The learned Umpire has not spoken his mind indicating why he has done, what he has done, he has narrated only how he came to make the award.

Counsel drew our attention to page 26 of the award where different items have been set out and referred to page 30 of the award where the arbitrator noted as under:

"The Respondent demurs to this and its officers have denied having received them in their affidavits and in their oral testimo- ny. No officer of the Post Office from which the letter was sent by Registered Post or of the Post Office through which delivery of that Registered letter was effected to the address- ee has been summoned to establish that these letters did not emanate from their Post Of- fices or that the Post Office seals affixed on the "Certificates of Posting" and "Postal Acknowledgements" were not of those Post Offices which delivered them to HSCL or that they were forged or fraudulent, nor was any- thing produced to show that these were not posted or registered from the Post Offices from which they emanated".

Counsel further drew our attention to the statement at page 33 of the award about the losses. Mr. Markandeya con- tended that these were the reasons given by the learned umpire. We are unable to accept. What the learned umpire did in the aforesaid paragraphs was to narrate the facts and state the history and state of pleadings. The umpire in the operative part of the award observed as under:

"WHEREAS I perused and considered the entire record with great care including the record of affidavits, the oral evidence ten- dered before me, the statement of claim dated 12.10.1983; the counter-statements dated 27/31-101983 and the Rejoinder of the claimant and considered the documents filed in support of the case of the respective parties as also the written and oral submissions made before me by counsel for the parties in support of their respective cases of the parties for which they have 659 appeared; and having duly considered the dispute in its varied aspects placed before me by the parties and in the light of the entire material in the case as above narrated. I.P.JAGANMOHAN REDDY, the Umpire, nominated by the Supreme Court of India as aforesaid, and having jurisdiction to adjudi- cate the dispute between the parties in the claims and counter-claims relating to Work Orders Nos. 3, 4, 5, 6 and 8 concerning the Glass Factory and Works Orders Nos. 9 and 10 concerning Lamp Factory and the contention of the claimant and the respondent in respect of the said Claims and counter claims. (1) I DO HEREBY MAKE MY AWARD, order and direct that the Respondent do pay to the claimant a sum of Rs.31,740-30p. (Rupees thirty one thousand seven hundred and forty and thirty paise) only in full satisfaction of its liability for the claim made by the Claim-

ant-Contractor against the Respondent with interest at the rate of six per cent per annum from the date of Award.

(2) I further award and direct that the counter-claims made by the respondent do stand dismissed.

(3) I further award and direct that the parties do bear their respective costs incidental to these proceedings.

(4) I further direct that the amounts paid by the parties towards the heating fees etc., from time to time in respect of the several heatings of these arbitration proceed- ings and the amount in deposit be appropriated and has/ have accordingly been appropriated towards the remuneration of the Umpire".

Therefore, in his award as a whole no reasons have been given for the purpose of making the award. In other words, it is not a speaking award at all. The Award did not speak as to why the umpire has awarded as he did. It does not speak the mind of the umpire. It mentions the events leading to the making of the award. In the award, there is no legal proposition which is unsustainable or improper. In that view of the matter the challenge to the award cannot be accepted.

660

In the premises, the objections are rejected. There will be decree in terms of the award of the Umpire, Shri P. Jaganmohan Reddy. There will be interest on the judgment at 9% until realisation. The applicant will have the costs of this application.

N.P.V.					    Award Confirmed.
661