Union of India - Subsection

Section 13(1) in Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009

(1)On receipt of the application, the nodal agency shall, in consultation and through coordination with other agencies involved in inter-State Transmission system to be used, including State Transmission Utility, if the State network is likely to be used, process the application and carry out the necessary system studies as expeditiously as possible so as to ensure that the decision to grant long-term access is arrived at within the timeframe specified in Regulation 7:[***] [Deleted 'First proviso' by Notification No. L-1/(3)/2009-CERC, dated 9.1.2019 (w.e.f. 7.7.2009).]