[Cites 0, Cited by 0] [Section 7] [Entire Act]

State of Tamilnadu - Subsection

Section 7(1) in The Central Electricity Authority (Technical Standards for Connectivity to the Grid) Regulations, 2007

(1)A Site Responsibility Schedule (SRS) for every connection point shall be prepared by the owner of the substation where connection is taking place.