[Cites 0, Cited by 0] [Section 21] [Entire Act]

Union of India - Subsection

Section 21(5) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019

(5)If the delay in achieving the COD is attributable either in entirety on in part to the generating company or the transmission licensee or its contractor or supplier or agency, in such cases, IDC and IEDC beyond SCOD may be disallowed after prudence check either in entirety or on pro-rata basis corresponding to the period of delay not condoned and the liquidated damages, if any, recovered from the contractor or supplier or agency shall be retained by the generating company or the transmission licensee, as the case may be.