Section 25 in Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009

25. Curtailment.

(1)When for the reason of transmission constraints or in the interest of grid security, it becomes necessary to curtail power flow on a transmission corridor; the transactions already scheduled may be curtailed by the Regional Load Despatch Centre.
(2)Subject to provisions of the Grid Code and any other regulation specified by the Commission, the short-term customer shall be curtailed first followed by the medium-term customers, which shall be followed by the long-term customers and amongst the customers of a particular category, curtailment shall be carried out on pro rata basis.