Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 10, Cited by 0]

Central Information Commission

Mrdavis George Thomas vs Ministry Of Environment & Forests on 21 October, 2015

                        CENTRAL INFORMATION COMMISSION
         (Room No.315, B­Wing, August Kranti Bhawan, Bhikaji Cama Place, New Delhi 110 066)

                    Prof. M. Sridhar Acharyulu (Madabhushi Sridhar)
                                     Information Commissioner

                                         CIC/SA/A/2015/000509
                                    (Video Conference - Bangalore)
                                                           
Davis George Thomas Vs. Ministry of Environment & Forest, Climate Change, GOI

                                     Important Dates and time taken:

      RTI Application: 19­11­2014        1st Appeal: 17­1­2015             2nd Appeal: 24­4­2015

      Disposed of with directions        Hearing:13­10­2015                Decision: 




Parties present: 


    The appellant is present for video conference at Bangalore.  The Public Authority is represented 

by Mr. Y.P.Singh, Scientist­D. 


FACTS: 

2.    The appellant is seeking information regarding compliance of the order of NGT for revisiting  the exemption given to Solar Power projects for Environmental clearance.   As no information was  received he approached the Commission in second appeal after exhausting the first appeal. 

3.       M/s Sagitaur Ventures India Pvt Limited has been allotted 1250 acres of land in the Amrit  Mahal   Kavals   of   Challakere   Taluk,   Chitradurga   District,   Karnataka  state   to  set   up   a  200  mw  capacity   Solar   Power   Generation   project.   Quoting   the   Environment   Impact   Assessment  Notification 2006 the Ministry claimed that Solar projects do not require Environmental Clearance  CIC/SA/A/2015/000509 Page 1 as   they   cause   minimal   or   no   damage   to   the   environment.   Citing   recent   research   showing  environmental hazards that Solar project could cause, the NGT directed the Ministry to revisit the  exemption order with regard to Environmental Clearance given to M/s Sagitaur Ventures India Pvt  Ltd and pass suitable orders, in the light of research reports. 

DECISION: 

4.     Both the parties made their submissions.  Appellant Davis George Thomas said neither the  CPIO nor the FAAO of the MoEF have complied with the letter and spirit of the RTI Act, 2005 by  either   furnishing   information   sought   or   by   providing   reasons   by   such   information   cannot   be  provided to him. 

5.       The   Environment   Support   Group   (ESG),   to   which   appellant   also   belonged,   has   filed  Applications No. 6/2013 and 12/2013 before the Hon'ble National Green Tribunal. In those cases,  the ESG raised a variety of grounds highlighting how project proponents had commenced work in  total   disregard   of   applicable   laws,   norms   and   clearance   procedures.     In   particular   it   was  highlighted   that   fundamental   provisions   of   the  Environment   Protection   Act,   1986  (and   Rules),  Environment Impact Assessment Notification, 2006, Water (Prevention and Control of Pollution)  Act, 1974Air (Prevention and Control of Pollution) Act, 1981Forest Conservation Act, 1980, etc.  had been flouted by the proponents, who started ground work without any clearances whatsoever.  The Petitioners also demonstrated that none of the projects had been grouped together flouting  risk   assessment   norms   (for   instance   an   uranium   enrichment   plant   is   proposed   next   to   a  weaponised drone testing facility) and without addressing basic land use planning, industrial and  hazardous  facilities   citing  norms.   In  addition,   the  locating  of   the   projects   were  in  violation  of  provisions of the Factories Act, 1948Karnataka Town and Country Planning Act, 1961, Aircraft  th Act, 1934 and the Constitutional 74  Amendment (Nagarpalika) Act, 1992.  

CIC/SA/A/2015/000509 Page 2

6.      The appellant stated that the NGT (Southern Zone, Chennai) in order dated 27th August 2014  in Application No.6/2013 and 12/2013 had given directions to the respondent Ministry to revisit the  exemptions given to the M/s Sagitaur Ventures India Pvt Ltd to commission solar power project.  He has referred to relevant paragraph:

"2. Citing an Office Memorandum issued by the MoEF, M/s. Sagitaur Ventures India Pvt. Limited,  the 14th Respondent in Application no. 6 of 2013,  claims that it need not obtain EC from the  MoEF. We are of the considered view that the Solar thermal power technology is still at its infancy.  Its impacts  on environment are being investigated in many research institutes across the globe  and newer and newer information on this aspect in emerging. In fact, the applicant placed before  the tribunal a few of the recent literature on this aspect and took us through the significant findings  in this regard. Keeping these and the averments made by the applicant on the subject in mind and  also   guided   by   the   "Precautionary   Principle"­   one   of   the   legs   of   the   concept   of  "Sustainable  Development", we direct the MoEF to revisit the exemption order with regard to EC given to M/s.  Sagitaur   Ventures   India   Pvt.   Limited  and   pass   suitable   orders   in   the   light   of   recent   research  findings and other relevant materials available."

Applicant also stated that  the aforesaid direction of the Hon'ble Tribunal needs to be read with  another part of its aforesaid order wherein it has been stated that any or all clearances whether  granted or exemptions provided must be based on acute rationalization which the Hon'ble Tribunal  termed in its wisdom as "verifiable and measurable "conditions". 

"215. In addition to directions given under different heads at appropriate sections of the judgment,  we   give   the   following   "Specific"   directions   to   the   MoEF,   KSPCB   and   the   Allottee   Project  Proponents: 
At the time of granting EC or CFE to the Project Proponents who have been allotted sites in  the land in question, the MoEF and/or KSPCB as the case may be, are directed to take strict  note   of  the   observations   and   comments   made   in   this   judgment   regarding   several  environmental   issues   and    concerns   raised   by   the   applicants   and   include   verifiable   and  measurable    "conditions"  regarding   the   same   to  be   complied   in   full,   at   all  stages,   by  the  project proponents."

7.    The Respondent Ministry is an essential party in the case before the Hon'ble National Green  Tribunal and the same Ministry has also taken the stand that the particular project in question, the  CIC/SA/A/2015/000509 Page 3 information of which was sought, is apparently in violation of the provisions of the Environment  Protection Act as is stated in the affidavit dated 28.10.2013 by the Hon'ble Ministry, the relevant  paragraph being:

"6. The Respondent further submits that with regard to para­33, it is submitted that there is  a   violation   of   Environment   (Protection)   Act,   1986   in   as   much   as   some   of   the   project  authorities have  started  the work  without  clearance under  Environment  Protection  Act,  1986."

8.       Appellant contended that given the weight of the matter, the stand taken by the Ministry  before the Hon'ble Tribunal, the explicit direction to the Ministry by the Hon'ble  NGT  as cited  above, and the fact that the Ministry has violated the provisions of the RTI Act, 2005 by not  responding to his Application as well as his Appeal. 

9.        The CPIO cited an Office Memorandum/Notification of 2006 issued by his ministry saying  that solar power projects are not listed, among those requiring the Environment Clearance. Only  those projects listed in the 2006 order need to take EC from their Ministry. That was why the  question of taking Environmental Clearance (EC) to M/s Sagitaur Ventures India Pvt Ltd for solar  power project does not arise. The CPIO, a scientist in the Ministry submitted that he is not aware  of the judgment given by the NGT.

10.     It is a paradox that the CPIO Mr. YP Singh says that he does not know about the order of  NGT. The office memorandum of 2006 which the CPIO is referring in his response was considered  by the NGT and directed the MoEF to revisit this kind of general exemption deemed to have been  granted to all Solar Thermal Stations including that of M/s Sagitaur Ventures India Pvt. limited.  The   Ministry   of   Environment   is   a   party   to   the   case   before   NGT.   It   was   directed   by   NGT   to  reconsider this general order. It is surprising that Public Authority claims that it does not know the  order.  

CIC/SA/A/2015/000509 Page 4

11.         The CPIO has repeatedly mentioned that 2006 OM and pleaded ignorance of the NGT  order.  The CPIO should know that he is representing the public authority, not just his desk or RTI  wing. Being a party how can the Ministry of Environment claim that it does not know the order of  NGT?  The appellant was specific in his request for action taken report as order by NGT.  When  Commission took a serious objection to this kind of ignorance, the CPIO said he would make  enquiries with the other officers and find out the information.  This is a clear denial of information  to the appellant on a very important issue of violation of environment law. 

12.     Section 4(1)(c) of RTI Act mandates the public authority to publish all relevant facts while  formulating important policies or announcing the decisions which affect public. And (d) demands  to provide reasons for its administrative or quasi judicial decisions to affected persons. 

13.   Hence it is the statutory duty of respondent Ministry of Environment to explain why the order  of the NGT was not implemented, what is their policy on this issue, what is their administrative  decision regarding revisiting of the blanket exemption deemed to have been  given under  2006  order, which was agreed by the Ministry of Environment through an affidavit before NGT to be  a  breach of Environment Protection Act; Are they pursuing any further legal remedy at higher courts  to continue this violation of Environment Act

14.       Instead of publishing this information voluntarily as per section 4(1) (c) & (d), the public  authority has adopted dilatory attitude and denying the information, which is very vital in public  interest and protection of environment, even after this RTI request and first appeal were filed.  

15.  The Commission cannot agree with the plea of ignorance by the CPIO and declares that the  ignorance of NGT order cannot be excused. It is not possible to agree that he does not know the  stand of the public authority he is representing. Once NGT gave direction to Ministry, being a  party,   it   is   presumed   that   entire   public   authority   including   CPIO   knew   it.   The   Commission  presumes that the Ministry of Environment and his CPIO knew the order of NGT, its implications  CIC/SA/A/2015/000509 Page 5 and finds that they  deliberately not implemented that order, and also denied the information to the  appellant. Hence the Commission directs the respondent public authority 

a) to   explain   reasons   for   this   non­publication   of   policy   related   information   about   Solar  Thermal projects as mandated by Section 4(1) of RTI Act,

b) to publish the policy along with the reasons in permitting Solar Thermal projects, including  that   M/s  Sagitaur   Ventures  India  Pvt.   limited  as   mentioned  in  this   application,   without  Environmental Clearance, in spite of stand taken by the Ministry that it was a breach of  Environment Protection Act.

c) To provide the information sought by the appellant

d) to explain why adequate compensation should not be given to the appellant who was  denied information till now, and 

e) to   provide   necessary   training   to  CPIOs   to   understand   their   duties   under   Environment  Protection Act, Right to Information Act, duties as the CPIO representing the entire public  authority.

16.   The Commission having heard the submissions and perused the record, directs the CPIO to  provide information as directed in clauses (a) to (d) to the appellant within 25 days from the date of  receipt of this order regarding the status of implementation of the NGT order on EC for Solar  Power projects.  The appeal is disposed of. 





                                                                                      (M. Sridhar Acharyulu)
                                                                                  Information Commissioner
Authenticated true copy




CIC/SA/A/2015/000509                               Page 6
 (U.C.Joshi)
Deputy Secretary

Address of the parties :

   1. The CPIO under the RTI Act, Govt. of India
         Ministry of Environment and Foresits & Climate change
         Indira Parvaran Bhavan, Jor Bagh Road  (RTI Cell)
         Lodi Road PO, New Delhi­110003 



   2. Shri Davis George Thomas

           3354, K.R.Road, 

           Bangalore­560070




CIC/SA/A/2015/000509                     Page 7