Union of India - Section

Section 5 in Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009

5. Filing of Application.

- Applications for giant of connectivity or long-term access or medium-term open access shall be made to the nodal agency:[Provided that an application for connectivity is not required to be made by any transmission licensee;] [Substituted by Notification No. L-1/(3)/2009-CERC, dated 9.1.2019 (w.e.f. 7.7.2009).]Provided, however, that an inter-State transmission licensee other than Central Transmission Utility, nevertheless, shall sign a connection agreement with the Central Transmission Utility, as provided for in Clause (5) of regulation 8 of these Regulations.