State of Rajasthan - Subsection

Section 26(5) in Rajasthan Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulations, 2016

(5)The long term/ medium term open access customer shall provide the injection schedule at the generator end and drawal schedule at the supply end to SLDC, RDPPC, supplier end Distribution Licensee and to the consumer end Distribution Licensee before 10.00 AM of the day preceding the day of scheduling. The Injection schedule shall have the open access consumer and supplier identification. Where open access is provided to more than one open access consumer, supplier shall provide a break up of injection schedule as applicable to each open access consumer considering that the adjustment of energy in such case shall be as per Regulation 25.