[Cites 0, Cited by 0]
[Entire Act]
NCT Delhi - Section
Section 63 in The Delhi Electricity Supply Code And Performance Standards Regulations, 2007
63. Procedure for lodging complaint:.
- (i) Complaint can be lodged over the telephone to the Centralised Complaint Receiving Centre of the Licensee, giving the details of name, address, telephone no., if available and brief nature of the complaint.| Nature of cause of power supply failure | Maximum Time Limit for restoration. |
| Fuse blown out or MCB tripped | Within three hours for Urban areasWithin eight hours forRural areas |
| Service line broken | Within six hours for Urban areas |
| Service line snapped from the pole | Within twelve hours for Rural areas |
| Fault in distribution mains | Temporary Supply to be restored within four hours fromalternate source, wherever feasible.Rectification of faultand thereafter Restoration of normal power supply within twelvehours |
| Distribution transformer failed/burnt | Temporary Restoration of supply through mobile transformer oranother backup source within eight hours, whereverfeasibleReplacement of failed transformer within forty-eighthours |
| HT mains failed | Temporary restoration of power supply within four hours,wherever feasible.Rectification of fault within twelve hours |
| Problem in grid (33 kV or 66 kV) substation | Restoration of supply from alternate source, wherever feasiblewithin six hoursRoster load shedding may be carried out toavoid overloading of alternate source.Repair and restorationof supply within forty-eight hours |
| Failure of Power Transformer | Restoration of supply from alternate source, wherever feasiblewithin six hoursRoster load shedding may be carried out toavoid overloading of alternate source.Replacement action tobe intimated to the Commission within seventy-two hours andreplacement of power transformer within 20 days |
| Burnt meter | Restoration of supply by bypassing the burnt meter within sixhoursReplacement of burnt meter within three days |
| Street light complaint | Restoration within seventy-two hours |
| No. | Cause of problem related to voltage variation | Time limit for the rendering service | Authorised Person | Next higher level for complaint |
| 1. | Local problem | Within 4 hours | Assistant Manager | District Manager |
| 2. | Tap of transformer | Within 3 days | Assistant Manager | District Manager |
| 3. | Repair of distribution line / transformer / capacitor | Within 30 days | Assistant Manager | District Manager |
| 4. | Installation and Up-gradation of HT / LT System | Within 90 days | Assistant Manager | District Manager |