State of Madhya Pradesh - Section

Section 11 in Madhya Pradesh Electricity Regulatory Commission (Terms and Conditions for Tariff determination of energy from Renewable Energy Sources) Regulations, 2017

11. Capital Cost.

- The norms for the Capital cost as specified in the subsequent technology specific chapters shall be inclusive of all capital work including plant and machinery, civil work, erection and commissioning, financing and interest during construction, and evacuation infrastructure up to inter-connection point;Provided that for project specific tariff determination, the generating company shall submit the break-up of capital cost items along with its petition in the manner specified under Regulation 8.