State of Madhya Pradesh - Act
Madhya Pradesh Electricity Regulatory Commission (Terms and Conditions for Tariff determination of energy from Renewable Energy Sources) Regulations, 2017
MADHYA PRADESH
India
India
Madhya Pradesh Electricity Regulatory Commission (Terms and Conditions for Tariff determination of energy from Renewable Energy Sources) Regulations, 2017
Act 43 of 2017
- Published on 6 July 2016
- Commenced on 6 July 2016
- [This is the version of this document from 6 July 2016.]
- [Note: The original publication document is not available and this content could not be verified.]
1. Short Title and Commencement.
2. Definitions.
| (a) Wind energy power project | 25 years |
| (b) Biomass power project with Rankine cycle technology | 20 years |
| (c) Bagasse based cogeneration project | 20 years |
| (d) Small Hydro Power Plant | 35 years |
| (e) Solar PV/Solar thermal power project | 25 years |
| (f) Biogas based power project | 20 years |
| (g) Municipal Solid Waste Power Project | 20 years |
3. Scope and extent of application.
- These Regulations shall apply in all cases where tariff, for a generating station or a unit thereof based on renewable sources of energy, is to be determined by the Commission under Section 62 read with Section 86 of the Act.Provided that these Regulations shall apply subject to the fulfillment of eligibility criteria specified in Regulation 4 of these Regulations.4. Eligibility Criteria.
Chapter 1
General Principles
5. Control Period or Review Period.
- The Control Period or Review Period under these Regulations shall be of five years w.e.f. 01.04.2017 or from the date of order, whichever is later.Provided that the benchmark capital cost for Solar PV and Solar thermal projects may be reviewed from time to time as the Commission deems it necessary;Provided also that the tariff determined as per these Regulations for the RE projects commissioned during the Control Period, shall continue to be applicable for the entire duration of the 'useful life' as specified in these Regulations;Provided also that in case Regulations for the next Control Period are not notified until commencement of next Control Period, the tariff norms as per these Regulations shall continue to remain applicable until notification of the revised Regulations.6. Project Specific tariff.
7. Petition and proceedings for determination of Tariff.
8. Tariff Structure.
9. Tariff Design.
10. Despatch principles for electricity generated from Renewable Energy Sources.
Chapter 2
Financial Principles
11. Capital Cost.
- The norms for the Capital cost as specified in the subsequent technology specific chapters shall be inclusive of all capital work including plant and machinery, civil work, erection and commissioning, financing and interest during construction, and evacuation infrastructure up to inter-connection point;Provided that for project specific tariff determination, the generating company shall submit the break-up of capital cost items along with its petition in the manner specified under Regulation 8.12. Debt Equity Ratio.
13. Loan and Finance Charges.
14. Depreciation.
15. Return on Equity.
16. Interest on Working Capital.
17. Operation and Maintenance Expenses.
18. Sharing of CDM Benefits.
19. Subsidy or incentive by the Central / State Government.
- The Commission shall indicate in the tariff order whether any incentive or subsidy offered by the Central or State Government is taken into consideration or not. However, the accelerated depreciation benefit if availed by the generating company, for the renewable energy power plants shall be taken into consideration while determining the tariff under these Regulations.20. Discounting Factor.
- The Commission shall indicate the discounting factor in the tariff order for the purpose of working out the Levelized tariff for the useful life of the project.21. Taxes and Duties.
- Tariff determined under these Regulations shall be exclusive of taxes and duties as may be levied by the appropriate Government:Provided that the taxes and duties levied by the appropriate Government shall be allowed as pass through on actual incurred basis.Chapter 3
Technology specific parameters for Wind Energy
22. Capital Cost.
23. Capacity Utilisation Factor (CUF).
24. Operation and Maintenance (O & M) Expenses.
Chapter 4
Technology specific parameters for Small Hydro Project
25. Capital Cost.
| Project Size | Capital Cost ( Rs. in Lakh/ MW) |
| Below 5 MW | 650 |
| 5 MW to 25 | MW |
26. Capacity Utilisation Factor.
- Capacity utilisation factor for the small hydro projects shall be 30%.27. Auxiliary Consumption.
- Normative Auxiliary Consumption for the small hydro projects shall be 1.0%.28. Operation and Maintenance Expenses.
- Normative Operation and Maintenance (O&M) expenses during the Control period shall be at 3% of the capital cost in first year of the project with an escalation at the rate of 5.72% per annum for the balance useful life of the project for the purpose of determination of tariff.Chapter 5
Technology specific parameters for Biomass Power Projects based on Rankine Cycle Technology
29. Capital Cost.
- The normative capital cost for the biomass power projects based on Rankine cycle shall be Rs. 475 Lakh/MW during the Control Period.30. Plant Load Factor.
- The Plant Load Factor for the purpose of determination of Tariff shall be:| (a) During thefirst year of operation: | 65% |
| (b) From 2nd Year onwards | 80% |