Section 5A in Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009

5A. [ Processing of Application. [Added by Notification No. L-1/(3)/2009-CERC, dated 9.1.2019 (w.e.f. 7.7.2009).]

(a)All Applications shall be made online in accordance with detailed Procedure.
(b)The applications complete in all respects, received online shall have a time and date stamp. Further, such applications received by 24:00 hrs. of the last day of the month shall be deemed to have been received during the month and shall be processed after the end of the month.
(c)Upon submission of the online application, auto-generated acknowledgement for receipt of application shall be issued by the nodal agency.
(d)After scrutiny, nodal agency shall intimate the deficiencies in the application, if any, to the applicant within one week of receipt of application. The applicant shall rectify the deficiency within one week thereafter, failing which the application shall be closed and 20% of the application fees shall be forfeited and balance shall be refunded and the Bank Guarantee, if any, shall be returned within 15 days of closure of the application. If the rectified application is received from the applicant after 24:00 hrs of the last day of the month in which application is made, application shall be deemed to have been made in subsequent month and shall be processed accordingly.]