Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 21, Cited by 0]

Andhra Pradesh High Court - Amravati

Sarada Metals And Alloys Ltd vs A.P. Electricity Regulatory ... on 22 April, 2026

 APHC010465652024                                                           Bench
                         IN THE HIGH COURT OF ANDHRA PRADESH
                                                                            [3483]
                                      AT AMARAVATI

                             WRIT PETITION NO: 24693 of 2024

Sarada Metals and Alloys Ltd.                                         ...Petitioner

     Vs.

A.P. Electricity Regulatory Commission                              ...Respondent

                                      **********

Advocate for Petitioner:                   Mr. P. Chidambaram, learned Senior
                                           Counsel appearing vice Mr. Sai Sanjay
                                           Suraneni

Advocate for Respondent:                   Mr. V. R. N. Prashanth

         CORAM : THE CHIEF JUSTICE DHIRAJ SINGH THAKUR
                 SRI JUSTICE RAVI CHEEMALAPATI

         DATE       : 22nd April, 2026.


Per DHIRAJ SINGH THAKUR, CJ:


       The petitioner in the present Writ Petition challenges inter alia the

validity and vires of Regulation 3.3 of the Andhra Pradesh Electricity

Regulatory Commission Renewable Power Purchase Obligation (Compliance

by   purchase       of    Renewable   Energy/Renewable     Energy    Certificates)

Regulations, 2017 and 2022, issued by the Andhra Pradesh Electricity

Regulatory Commission (for short, "the APERC").


2.     With a view to understand in the correct perspective the background in

which the present controversy arises, it is necessary to give in brief the

material facts:
                                          2
                                                                           HCJ & RCJ
                                                                       WP_24693_2024


      The petitioner is engaged in the business of manufacturing and export

of manganese - based Ferro Alloys which is a primary element of steel

making. For this the petitioner claims to operate the Ferro Alloys Plant at

Vizianagaram in Andhra Pradesh. The petitioner also claims to operate an 80

MW Captive Power Plant within the premises of the Ferro Alloy Plant. The

petitioner further claims that it synchronized its Captive Power Plant on

03.02.2013 and therefore, fell within the ambit of Ministry of Power‟s directive

dated 01.10.2019, reference whereto shall be made in the later paragraphs.


3.    At this stage, it is also deemed apt to refer to the statutory provisions

which are relevant for the decision in the instant case.


      The Electricity Act, 2003 (for short, "the Act of 2003") was enacted with

a view to consolidate the laws relating to generation, transmission,

distribution, trading and use of electricity and also for taking measures

conducive to the development of the electricity industry, rationalisation of

electricity tariff and for constitution of Central Electricity Authority, Regulatory

Commissions and establishment of Appellate Tribunal and matters connected

therewith.


4.    Before the promulgation of the Act of 2003, the electricity supply in India

was governed by three enactments namely the Indian Electricity Act, 1910,

the Electricity (Supply) Act, 1948 and the Electricity Regulatory Commissions

Act, 1998.
                                         3
                                                                         HCJ & RCJ
                                                                     WP_24693_2024


5.    While the Indian Electricity Act, 1910 created the basic framework for

electricity supply in India, the Electricity (Supply) Act, 1948 envisaged the

creation of State Electricity Boards, on whom a duty was enjoined to arrange

the supply of electricity. However, the performance of SEBs is said to have

deteriorated on account of various factors and in that backdrop with a view to

encourage private sector participation in generation, transmission and

distribution and with the objective of distancing the regulatory responsibilities

from the Government to the Regulatory Commissions and with a view to

harmonise and rationalise the provisions of the Indian Electricity Act, 1910, the

Electricity (Supply) Act, 1948 and the Electricity Regulatory Commissions Act,

1998, there was a need felt for self-contained comprehensive legislation which

finally assumed the shape of the Electricity Act, 2003.


6.    At this stage, it would be apt to refer to some of the provisions of the Act

of 2003:


      While Section 2 of the Act pertains to definitions, Section 3 envisages

that the Central Government shall from time to time prepare "the National

Electricity Policy and Tariff Policy" in consultation with State Governments and

the authority for development of the power systems.


7.    Sub-section (2) of Section 3 envisages that the Central Government

shall publish the National Electricity Policy and Tariff Policy from time to time

and further, Section 3(3) of the Act confers the Central Government with the
                                          4
                                                                        HCJ & RCJ
                                                                    WP_24693_2024


power to review and revise the National Electricity Policy and the Tariff Policy,

in consultation with the State Governments and the Authority.


8.    Section 3(4) envisages preparation of National Electricity Plan in

accordance with the National Electricity Policy and is required to be notified

once in five years.


9.    Section 9 of the Act deals with captive generation and envisages that a

person may construct, maintain and operate a captive generating plant and

dedicated transmission lines with a right inter alia to an open access for

purposes of carrying electricity from its captive generation plant to the

destination of its use which further is made subject to availability of adequate

transmission facility.


10.   Section 61 falling in Part VII of the Act deals with Tariff Regulations and

envisages that the Appropriate Commission shall subject to the provisions of

the Act, specify the terms and conditions for determination of tariff. It further

envisages that the determination of tariff shall inter alia be guided by the

National Electricity Policy and Tariff Policy.


11.   According to Section 2(4), Appropriate Commission means the Central

Regulatory Commission referred to in sub-section (1) of Section 76 or the

State Regulatory Commission referred to in Section 82 or the Joint

Commission referred to in Section 83, as the case may be.
                                            5
                                                                                HCJ & RCJ
                                                                            WP_24693_2024


12.   Section 82 envisages constitution of Electricity Regulatory Commission

which would be prefixed by the name of the respective States. The State

Governments were enjoined to constitute the State Electricity Regulatory

Commissions within six months from the appointed date, by notification.

However, as per the proviso to Section 82, the State Electricity Regulatory

Commission established by the State Governments under Section 17 of the

Electricity Regulatory Commissions Act, 1988, and functioning immediately

before the appointed date, would continue to be the State Commission for

purposes of the Act of 2003.


13.   The State Electricity Regulatory Commissions would be deemed to be a

body corporate having perpetual succession and common seal.


14.   Section 86 of the Act of 2003 envisages the functions to be discharged

by the State Electricity Regulatory Commissions inter alia to determine the

tariff for generation, supply, transmission and wheeling of electricity, within the

State, facilitate intra-State transmission and wheeling of electricity, issue

licences to persons seeking to act as transmission licensees, distribution

licensees and electricity traders. Reference to Section 86(1)(e) is necessary,

which reads as under:

             "86. (1)(e) promote cogeneration and generation of
             electricity from renewable sources of energy by providing
             suitable measures for connectivity with the grid and sale of
             electricity to any person, and also specify, for purchase of
             electricity from such sources, a percentage of the total
             consumption of electricity in the area of a distribution
             licensee;"
                                            6
                                                                                HCJ & RCJ
                                                                            WP_24693_2024


15.   Section 86(4) is also important and envisages as under:

            (4) In discharge of its functions, the State Commission shall
            be guided by the National Electricity Policy, National
            Electricity Plan and tariff policy published under section 3.



16.   Section 181 of the Act of 2003 further envisages the framing of

regulations by the State Commission.


17.   The Central Government on 06.01.2006 notified the Tariff Policy which

was   further   amended      on     31.03.2008,     20.01.2011       and    08.07.2011.

Subsequently, the Ministry of Power notified its revised Tariff Policy vide

notification dated 28.01.2016, in accordance with the powers vested in it

under Section 3 of the Electricity Act, 2003.


18.   According to Clause 2.2 of the Tariff Policy the Central Electricity

Regulatory Commission and State Electricity Regulatory Commissions were

enjoined to be guided by the Tariff Policy in discharging their functions

including framing of regulations.


19.   Clause 4 of the Tariff Policy clearly envisaged inter alia that the

objective of the policy was to promote generation of electricity from renewable

sources.


20.   Clause 6.4 further envisaged as under:

            "6.4 Renewable sources of energy generation including Co-
            generation from renewable energy sources:

            (1) Pursuant to provisions of section 86(1)(e) of the Act, the
            Appropriate Commission shall fix a minimum percentage of the
            total consumption of electricity in the area of a distribution
                                                  7
                                                                                      HCJ & RCJ
                                                                                  WP_24693_2024

                 licensee for purchase of energy from renewable energy
                 sources, taking into account availability of such resources and
                 its impact on retail tariffs. Cost of purchase of renewable energy
                 shall be taken into account while determining tariff by SERCs.
                 Long term growth trajectory of Renewable Purchase
                 Obligations (RPOs) will be prescribed by the Ministry of
                 Power in consultation with MNRE."



 21.       Pursuant to the notification of the Tariff Policy by way of publication in

 Gazette on 28.01.2016, the Government of India, Ministry of Power issued

 guidelines for long term growth trajectory of Renewable Purchase Obligations

 (RPOs) dated 22.07.2016. The following was notified as the growth trajectory

 for non-solar as well as solar, uniformly for all States and Union Territories for

 three years from 2016-17 to 2018 to 2019:


Long term trajectory        2016-17                  2017-18                 2018-19
Non-solar                   8.75%                    9.50%                   10.25%
Solar                       2.75%                    4.75%                   6.75%
       Total                11.50%                   14.25%                  17.00%


 22.       The obligation to purchase renewable energy was cast on obligated

 entities excluding consumption met from hydro sources of power which was to

 be calculated on total consumption of electricity by a particular obligated

 entity.


 23.       An obligated entity as per the APERC RPO Regulations, 2012, means

 an entity obligated to purchase renewable power under clause (3) of

 Regulations.


 24.       The Government of India, Ministry of Power, subsequently, by virtue of

 the notification dated 14.06.2018, issued the long term growth trajectory of
                                             8
                                                                                HCJ & RCJ
                                                                            WP_24693_2024


 Renewable Purchase Obligations for Solar and Non-solar, uniformly for all the

 States and Union Territories for three years, i.e., 2019-20 to 2021-22 as

 under:


Long term trajectory   2019-20                  2020-21                2021-22
Non-solar              10.25%                   10.25%                 10.50%
Solar                  7.25%                    8.75%                  10.50%
       Total           17.50%                   19.00%                 21.00%


 25.   At this point, it is relevant to refer to the Clarification, dated 01.02.2019,

 issued by the Government of India, Ministry of Power, clarifying that the long

 term growth trajectory of Renewable Purchase Obligation of Solar and Non-

 solar for the period 2016-19 and 2019-22 as prescribed in the Ministry‟s

 notification, dated 22.07.2016, at the request of various stakeholders, had

 been examined in consultation with Ministry of New and Renewable Energy

 and it was therefore clarified that RPO of the Captive Power Plant may be

 pegged at the RPO level applicable in the year in which the Captive Power

 Plant was commissioned. For facility of reference, the clarification is

 reproduced hereunder:

             "I am directed to refer to the Ministry of Power's Order of even
             number dated 22ndJuly, 2016 and 14thJune, 2018 regarding long
             term growth trajectory of Renewable Purchase Obligation
             (RPO) for Solar and Non-solar for the period 2016-19 and 2019-
             22 respectively.

             2. The request of various stakeholders regarding capping of
             RPO for Captive Power Plants (CPP) has been examined in
             consultation with Ministry of New and Renewable Energy and it
             is clarified that RPO of the CPP may be pegged at the RPO
             level applicable in the year in which the CPP was
             commissioned. As and when the company adds to the capacity
             of the CPP it will have to provide for additional RPO as
             obligated in the year in which new capacity is commissioned.
                                            9
                                                                               HCJ & RCJ
                                                                           WP_24693_2024

            There should not be an increase in RPO of CPP without any
            additional fossil fuel capacity being added.

            3. This issues with the approval of Hon'ble MoS(I/C) for Power
            and NRE."


26.   Subsequently, another clarification, dated 01.10.2019, was issued by

the Ministry of Power, which reads as under:

            "I am directed to refer to the Ministry of Power's Order of even
            number dated 22nd July, 2016 and 14th June, 2018 regarding
            long term growth trajectory of Renewable Purchase Obligation
            (RPO) for Solar and Non-solar for the period 2016-19 and 2019-
            22 respectively.

            2       A clarification was issued by Ministry of Power, vide
            letter dated 1 February, 2019 regarding capping of RPO for
            Captive Power Plants (CPP) (copy enclosed).

            3       Based on the concern raised by various stakeholders
            and after due consultation with MNRE, GEA and CERC it is
            further clarified that

            i)      For CPPs commissioned before 1.04.2016, RPO should
            be at the level as mandated by the appropriate Commission for
            the year 2015-16. For CPPs commissioned from 1.04.2016
            onwards, the RPO level as mandated by the appropriate
            Commission or Ministry of Power, whichever is higher, for the
            year of commissioning of the CPP shall be applicable.

            ii)     In case of any augmentation in the capacity, the RPO
            for augmented capacity shall be the RPO applicable for the year
            in which the CPP has been augmented.

            iii)    In case, for meeting the RPO obligation, CPP has
            surplus power than its consumption requirement, such a CPP
            may sell its surplus power to the DISCOMS under the prevailing
            arrangements or in the power exchange.
                                          10
                                                                             HCJ & RCJ
                                                                         WP_24693_2024

            This issues with the approval of Hon'ble MoS(I/C) for Power
            and NRE."

27.   On a reading of the above two clarifications, it becomes clear that while

the clarification, dated 01.02.2019, pegged the RPO of a Captive Power Plant

at the RPO level applicable in the year in which the Captive Power Plant was

commissioned, as per the subsequent clarification, dated 01.10.2019, all

Captive Power Plants commissioned before 01.04.2016, RPO was required to

be at the level mandated by the Appropriate Commission for the year 2015-16

and for all Captive Power Plants commissioned from 01.04.2016 onwards, the

RPO level as mandated by the Appropriate Commission or Ministry of Power,

whichever was higher, for the year of commissioning would be applicable.


28.   In exercise of powers conferred in Sections 61, 66, 86(1) (e) and 181 of

the Electricity Act, 2003, the Andhra Pradesh Electricity Regulatory

Commission framed the regulations called the Renewable Power Purchase

Obligation (Compliance by Purchase of Renewable Energy/Renewable

Energy Certificates) Regulations, 2012 (for short, "APERC RPO Regulations,

2012,").


29.   Regulation 3.3 of the aforementioned regulations provided as under:

            "3.3 Every consumer owning a captive generating plant of
            installed capacity of One (1) MW shall purchase Renewable
            Energy Certificates issued under the Central Electricity
            Regulatory Commission (Terms and Conditions for
            recognition and issue of Renewable Energy Certificate for
            Renewable Energy Generation) Regulations, 2010 as
            amended from time to time, corresponding to a quantum of
            not less than 5% of its consumption of energy, during each
            of the years from 2012-13 to 2016-17 (each year
            commencing from 1stApril of the Calendar Year and ending
                                              11
                                                                                   HCJ & RCJ
                                                                               WP_24693_2024

                on 31stMarch of the subsequent Calendar Year) provided
                that the purchase of energy from renewable energy sources
                shall also be treated as fulfillment of the Renewable Power
                Purchase Obligation (RPPO) prescribed herein;"


30.   Subsequently, the APERC notified Regulation No.1 of 2017 (APERC

RPO Regulations, 2017). According to Clause 3.3 whereof, every consumer

owning a captive generating plant of installed capacity at 1 MW and above

and connected to the grid was required to purchase Renewable Energy

Certificates issued under the Central Electricity Regulatory Commission

(Terms and Conditions for recognition and issue of Renewable Energy

Certificate for Renewable Energy Generation) Regulations, 2010, as amended

from time to time corresponding to a minimum quantity of electricity expressed

as a percentage of its consumption of energy, during FY2017-18 to FY 2021-

22 as specified in TABLE-I under clause 3.1 of this Regulation, which

envisaged as under:


                                          TABLE-I


        Year             2017-18      2018-19     2019-20      2020-21          2021-22
  Non-solar             6%           7%           8%          9%              10%
  Solar                 3%           4%           5%          6%              7%
        Total           9%           11%          13%         15%             17%


      Proviso to Regulation 3.3 further provided that, the purchase of energy

from renewable energy sources would also be treated as fulfillment of

Renewable Power Purchase Obligation.


31.   Subsequently, the APERC framed Regulation No.5 of 2022 (APERC

RPO Regulations, 2022) and notified the same on 29.09.2022, which enjoined
                                        12
                                                                        HCJ & RCJ
                                                                    WP_24693_2024


a consumer owning a captive generating plant to purchase renewable energy

as per the specifications below:


                         From the date
                         of publication
                            of these
                         Regulations in       FY        FY          FY         FY
        Period
                           the official     2023-24   2024-25     2025-26    2026-27
                         gazette to the
                           end of FY
                            2022-23
RPPO, i.e. the                18%            19%        20%         22%        24%
minimum quantity of
renewable electricity
to be purchased as a
percentage of total
consumption



32.   As per Clause 7.1 of the 2017 Regulations, framed by the APERC, if an

obligated entity does not fulfill the Renewable Power Purchase Obligation as

provided in Clause 3 thereof, during any year, the Commission was given the

power to direct the obligated entity to deposit such amount as the Commission

may determine on the basis of the shortfall in units of the Renewable Power

Purchase Obligation.


33.   Not only this, in terms of Clause 7.2 of the Regulation, in addition to the

compliance of the directions under clause (7.1), a penalty can as well be

imposed by the Commission to an extent to be decided by the Commission

under Section 142 of the Electricity Act, 2003.


34.   In the backdrop of the aforementioned legal provisions, a notice dated

27.12.2021, came to be served upon the petitioner intimating the petitioner
                                         13
                                                                          HCJ & RCJ
                                                                      WP_24693_2024


regarding non-compliance of Clause 3.2/3.3 of the RPPO in its capacity as an

obligated entity for the period 2012-13 to 2018-19, it was therefore required to

show-cause as to why it not be directed to deposit an amount of

Rs.16,46,90,400/-.


35.   An appropriate response, dated 07.04.2022, according to the petitioner,

was submitted to the show-cause notice, which was considered by the

APERC but the same came to be rejected on 30.05.2023 and an amount of

Rs.16,24,90,400/- was determined as payable by the petitioner on account of

its failure to meet the RPPO for the energy consumed.


36.   An Original Petition bearing No.82 of 2023 came to be filed before the

APERC in which the petitioner inter alia sought a declaration that the

petitioner‟s RPPO liability be capped as per the Ministry of Power‟s

clarification, dated 01.10.2019, for Captive Power Plants.


37.   By virtue of the order dated 03.09.2024, the APERC dismissed the

Original Petition by holding that it was vested with exclusive powers of

regulating tariffs and all other aspects related thereto, and further that the

National Electricity Policy, National Electricity Plan and the Tariff Policy

published under Section 3 of the Act would only be a guiding factor.


38.   It rejected the contention of the counsel for the petitioner that the

clarificatory orders passed by the Ministry of Power were in any way binding

on the Commission and that if at all it had only a guiding force. It held:
                                             14
                                                                                 HCJ & RCJ
                                                                             WP_24693_2024

             ".... No doubt, the clarificatory orders of the MoP sought to limit
             the CPPs' liability for RPPO; the same would certainly be a
             material consideration for this Commission while making its
             Regulations for the future. However, as the obligation is for the
             past periods, which is already governed by Regulations issued
             by this Commission, in due exercise of the statutory powers, in
             the opinion of this Commission, such Clarificatory Orders,
             despite having statutory flavor, cannot displace the Regulations
             already in force. In other words, to act on a Clarificatory Order
             of the MoP would be to negate the Regulations framed and
             notified by this Commission. Such a course is not desirable so
             long as the Regulations continue to be enforced for the
             Obligated Entities concerned."



39.   While placing reliance on Tata Power Company Limited (supra), it

was held that the Tariff Policy was not per se binding on the Commission but

would be one of the material considerations only.


40.   Although the Electricity Act did provide for an appeal under Section 111

before the Appellate Tribunal for Electricity (APTEL), yet since the petitioner

challenges the vires of the Regulations of 2017 & 2022, the present petition

has been filed challenging the 3.3 RPPO Regulations of 2017 and 2022 as

ultra vires to the Electricity Act, 2003. Apart from this, a direction is sought to

APERC to amend Regulation 3.3 of the 2017 and 2022 Regulations to give

effect to the Ministry of Power‟s directive, dated 01.10.2019, regarding long

term growth trajectory of RPO Captive Power Plants, which envisaged a cap

on RPO of Captive Power Plant commissioned before 01.04.2016 at the RPO

prescribed by the APERC for F.Y. 2015-16, which was at 5% of the power

consumed.


41.   Mr. P. Chidambaram, learned Senior Counsel, would submit that the

impugned regulations and, in particular, Regulation 3.3 of APERC RPPO
                                          15
                                                                           HCJ & RCJ
                                                                       WP_24693_2024


Regulations of 2017 and 2022, are ultra vires the Electricity Act, 2003

inasmuch as the regulations failed to give effect to the Ministry of Powers

Directive, dated 01.10.2019, which mandates capping the RPO for Captive

Power Plants commissioned before 01.04.2016 at 5%, which was applicable

in the case of the petitioner herein. It was urged that the directive issued by

the Ministry of Power was rooted in Clause 6.4.1 of the Tariff Policy, 2016,

was therefore statutory in nature, and possessed the force of law and APERC

being a delegate under the Electricity Act was statutorily bound to be guided

by the Tariff Policy and the directives issued thereunder.


42.   It was stated that Section 86(4) of the Electricity Act mandated that

APERC shall be guided by the National Electricity Policy and the Tariff Policy

and by disregarding the Ministry of Powers Directive, APERC had acted in

contravention of these statutory provisions which rendered the impugned

regulations ultra vires.


43.   Reliance was finally placed upon the judgment of the Apex Court

rendered in Reliance Infrastructure Ltd. v. State of Maharashtra and Tata

Power Company Limited v. MERC &Ors.


44.   The stand of the official respondent was that APERC was an

autonomous body and further that under Section 86(1)(e) of the Act of 2003,

APERC was empowered to specify Renewable Power Purchase Obligations

for obligated entities within the State. It is also stated that it was an exercise of

the powers so vested in the Commission that the regulations came to be
                                         16
                                                                          HCJ & RCJ
                                                                      WP_24693_2024


framed earlier in the year 2012, subsequently in 2017, and thereafter in the

year 2022. It was also held that while Section 86(4) of the Electricity Act

mandated the APERC to be "guided" by the National Electricity Policy and the

Tariff Policy, it did not imply that every such directive issued by the Ministry of

Power was automatically binding on the APERC. The term "guided", it was

urged, suggested an advisory role rather than a mandatory obligation to follow

each such directive.


45.   Apart from this, Mr. V. R. N. Prashanth, learned Counsel appearing for

APERC, would submit that the clarification, dated 01.02.2019, and the

clarification, dated 01.10.2019, cannot be considered to be a part of the

National Tariff Policy, inasmuch as while the National Tariff Policy authorizes

the Ministry of Power to provide the long term growth trajectory, it did not

empower the Ministry of Power to cap the Renewal Power Purchase

Obligations and further that the Electricity Regulatory Commissions have been

given unbridled powers to fix the percentage of Renewal Power Purchase

Obligations by taking into consideration various factors including the

availability of renewable power sources with a view to strike harmonious

balance, which safeguarded the interest of the end consumer also.


46.   We are not convinced with the argument of learned counsel for the

respondent that the Ministry of Power had no authority to cap the Renewable

Power Purchase Obligation at all and that it could have only provide for a long

term growth trajectory as in terms of National Tariff Policy and, in particular, in
                                                 17
                                                                                         HCJ & RCJ
                                                                                     WP_24693_2024


terms of clause 6.4 of the said Tariff policy. It goes without saying that if the

Ministry of Power could prescribe a long term growth trajectory of Renewable

Power Purchase Obligations, it would also carry with it the power to regulate

the said growth trajectory or even cap it at a particular level and for a specific

period and in the case of specific group of Captive Power Plants.


47.     At this stage, it may be apt to refer to some of the judgments, which

have a direct bearing on the issues that arise in the present petition. In

Reliance Infrastructure Ltd. v. State of Maharashtra1, the Apex Court was

examining the validity of the tariff regulation, framed by the Maharashtra ERC,

which was challenged as being opposed to the National Tariff Policy. In that

context, the Apex Court, while examining the purport with the interpretation in

the case of Reliance Infrastructure Ltd. of the phrase „shall be guided‟ as

contained in Section 61 of the 2003 Act, held:


                   "29. Section 181 empowers the State Commissions to make
                   regulations consistent with the Act and the Rules to carry out
                   the provisions of the Act. Among the matters for which the
                   regulations may provide are "the terms and conditions for the
                   determination of tariff under Section 61". In specifying the
                   terms and conditions for the determination of tariff, the
                   appropriate Commission (as Section 61 provides) "shall be
                   guided" by the factors which are set out in clauses (a) to (i).
                   The expression "shall be guided" comprises of two
                   elements: the "shall" and, the "guidance". Clauses (a) to
                   (i) provide guidance to the Commission in specifying the
                   terms and conditions for the determination of tariff. The
                   expression "shall" indicates that the factors which are
                   specified in clauses (a) to (i) have to be borne in mind by the
                   appropriate Commission. As guiding factors, they provide
                   considerations which are material to the determination of
                   tariffs by the appropriate Commission.




1
(2019) 3 SCC 352
                                                 18
                                                                                         HCJ & RCJ
                                                                                     WP_24693_2024

                  30. The National Tariff Policy has multi-faceted objectives.
                  Significant among them is the need to ensure to consumers
                  the availability of electricity at reasonable and competitive
                  rates. The policy also seeks to ensure the financial
                  viability of the sector and underlines the need to attract
                  investments. A financially sustainable electricity sector is an
                  important facet of the overall regulatory framework. The
                  objectives of the policy emphasise the need to promote
                  transparency,       consistency      and   predictability    in
                  regulatory approaches across jurisdictions. The policy
                  emphasises the need to minimise perceptions of regulatory
                  risk. Finally, the policy recognises the need to promote
                  competition, efficiency in operations and improvements in the
                  quality of supply. In designing and formulating the
                  regulatory framework for tariffs, the delegate of the
                  legislature has to bring about a balance between the
                  competing goals which the Tariff Policy incorporates.

                  31. As part of the process, the delegate has to bear in mind
                  the interests of diverse stakeholders including consumers and
                  producers. ...The operating norms must be designed to
                  promote efficiency and to ensure that the gains which accrue
                  on account of efficient operations are shared with the
                  consumers of electricity. The operating norms will, therefore,
                  have due regard to the performance in the past as well as
                  capacities for future achievement. These must be
                  dovetailed with all relevant considerations, bearing on
                  the requirements of the policy.

                  32. The Tariff Policy provides guidance to the appropriate
                  Commission when it frames regulations. The power to
                  frame regulations is legislative in nature. It is conferred upon
                  the appropriate Commission. The Commission weighs
                  numerous factors. Its discretion in carrying out a complex
                  exercise cannot be constrained. The delegate of the
                  legislature is therefore under a mandate to bring about a fair
                  and equitable balance between competing considerations.
                  Standing at the forefront of those considerations is above all
                  the need to ensure efficiency and to protect the interests of
                  consumers. ..."




48.     In Tata Power Co. Ltd. Transmission v. MERC & Ors.2, the Apex

Court was considering, inter alia, the issue as to whether the National Tariff

Policy(NTP) framed under Section 3 of the Act is binding on the State

Regulatory Commissions. In that context, the Apex Court held that the

2
(2023) 11 SCC 1
                                             19
                                                                                      HCJ & RCJ
                                                                                  WP_24693_2024


interpretation in the case of Reliance Infrastructure Ltd. of the phrase „shall

be guided‟ as contained in Section 61 would be equally applicable to the said

phrase as contained in Section 86(4) of the Act of 2003. It was held:


            "98. Section 181 of the Act stipulates that the State
            Commission(s) may by notification, make regulations
            consistent with the Act and the rules framed by the State
            Government under Section 180 of the Act to carry out the
            provisions of the Act. ...

            99. At this juncture, it is necessary to refer to Section 86 of the
            Act. Section 86 lists the functions of the State Commission.
            Section 86(a) states that the State Commission shall discharge
            the function of determining the tariff for transmission. Section
            86(c) stipulates that the State Commissions shall facilitate
            intra-State transmission of electricity. Section 86(4) provides
            that in the discharge of its functions, which includes the
            determination of tariff for the transmission of electricity under
            clause (a), the State Commission shall be guided by the NEP,
            National Electricity Plan and NTP notified under Section 3 of
            the Act.

            114. This      Court      in Reliance    Infrastructure [Reliance
            Infrastructure Ltd. v. State of Maharashtra, (2019) 3 SCC 352]
            held that the principles prescribed in Section 61 are all material
            considerations that must guide the appropriate Commission
            while it prescribes the terms and conditions for determining the
            tariff. It was held that it was the responsibility of the
            Commission to ensure a delicate balance of the principles
            prescribed under Section 61. Thus, while NTP which is
            prescribed as one of the principles under Section 61 shall
            be a material consideration, it cannot be interpreted to
            mean that it is the "only" material consideration. This
            interpretation of "shall be guided" is equally applicable to
            the use of the phrase in Section 86(3).

            121. While the determination and regulation of tariff falls within
            the exclusive domain of the Regulatory Commission, it is
            crucial to note that Sections 61 and 86 stipulate that the
            Commission shall be guided by NTP while specifying terms
            and conditions for determining tariff. The State Commission
            while exercising its power to make regulations under Section
            181(2)(zd) on the terms and conditions for determination of
            tariff under Section 61 must conform to the provisions of the
            Act. Thus, while framing regulations under Section
                                            20
                                                                                    HCJ & RCJ
                                                                                WP_24693_2024

            181(2)(zd), the Commission must be guided by the
            principles mentioned in Section 61, which includes the
            NEP and NTP.

            122. This Court in Reliance Infrastructure Ltd. v. State of
            Maharashtra, (2019) 3 SCC 352 has already held that NTP is
            one of the material considerations. NTP is one of the many
            guidelines that the Commission must necessarily consider
            while regulating tariff. The State and the Central Government
            only have an advisory role in the regulation of tariff. The
            Electricity Regulatory Commissions Act, 1998, which was
            consolidated with other statutes on electricity while enacting
            the Electricity Act, 2003, was enacted to distance the
            governments from the determination of tariffs. Further, the Act
            does not seek to centralise the power to regulate tariff with the
            Centre. One of the objectives of the Act was to provide the
            "States enough flexibility to develop their power sector in
            the manner they consider appropriate". Thus, since the
            appropriate Commissions possess full autonomy in the
            determination and regulation of tariff, and the States have
            been provided flexibility to develop their power systems
            for intra-State transmission of electricity, the NTP 2016
            shall be oneof the material considerations...."



49.   While the issue in Tata Power Co. Ltd. Transmission (supra) was not

centered around the Renewable Power Purchase Obligations, yet the Apex

Court did examine the phrase „shall be guided‟ as existing in Section 86(4) of

the Act of 2003. The legal position which thus stands crystallized by the

Hon‟ble Supreme Court leaves this Court in no doubt that framing of

regulations with regard to the Power Purchase Obligations falls exclusively

within the domain of the Commission, which however must consider the

guidance as provided by the National Tariff Policy in terms of Section 86(4) of

the Act.
                                       21
                                                                      HCJ & RCJ
                                                                  WP_24693_2024


50.    It can also be seen that the guidance which is provided by the Central

Government envisaged under Section 86(4) is a material consideration but not

the only material consideration as was held in Tata Power Co. Ltd.

Transmission (supra) and further that the role of the State and the Central

Government was only advisory in nature and that the Electricity Regulatory

Commissions had full autonomy and power in framing regulations which

included the Regulations prescribing Renewable Power Purchase Obligations.


51.    Mr. P. Chidambaram, learned Senior Counsel would, however, urge

that while the clarifications dated 01.02.2019 and 01.10.2019 may not have

any binding force, yet the Commission ought to have considered the same as

to whether the regulations of RPPO of 2017 or for that matter, regulations of

RPPO of 2022 required an amendment.


52.    It was also urged that according to the stand taken by the APERC, it

was nowhere reflected that the clarifications dated 01.02.2019 and

01.10.2019, were at all considered for purposes of deciding whether an

appropriate amendment to the Regulations of 2017 or 2022 were warranted or

not.


53.    At the very outset, we can see that the Regulations impugned of 2017

were framed in the year 2017 when the clarification dated 01.02.2019 and the

subsequent clarification dated 01.10.2019, were not in existence. The

petitioner also did not challenge the said regulations on the grounds which are

now sought to be urged before us and the petition came to be filed as late as
                                        22
                                                                        HCJ & RCJ
                                                                    WP_24693_2024


in October, 2024. By that time, even when the petitioner could have

approached this Court for purposes of seeking appropriate relief from this

Court in regard to the Regulations of 2017, yet it chose to remain silent.

54.   We are of the opinion that as far as the challenge to the Regulations of

2017 is concerned, the same is belated. The regulations of 2017 are no longer

in force and have worked itself out and, therefore, challenge to the same

cannot be permitted at this stage. However, insofar as the Regulations of

2022 are concerned, APERC was in fact obliged to at least consider the

clarification, dated 01.02.2019 as also the clarification, dated 01.10.2019,

before framing the 2022 Regulations. We are quite in agreement with the

argument of Mr. P. Chidambaram, learned Senior Counsel that even when the

notification dated 01.02.2019, and the subsequent clarifications had no

binding effect on the APERC, yet it could be considered to be a material

factor, which ought to have been considered, among others, before framing

the Regulations of 2022.

55.   Be that as it may, we direct the State Electricity Regulatory Commission

to consider the clarification dated 01.10.2019, and to decide whether any

amendment was necessary in the light of the said clarification. If the guidance

given by the aforementioned clarification is accepted, the necessary

amendment would be incorporated by the Commission in the Regulations of

2022 and appropriate relief extended to the petitioner. Till such time as the

matter is considered by the APERC in regard to the Regulations of 2022, no

coercive action be taken for recovery of any amount, which would be beyond
                                         23
                                                                       HCJ & RCJ
                                                                   WP_24693_2024


the obligation of the petitioner as was fixed by clarification dated 01.10.2019,

for the period the said clarification remained in force.

56.   However, it is made clear that in the event the APERC decides not to

amend the regulations for any good reason, the petitioner would be under an

obligation to show strict compliance to Regulations of 2022. We further hold

that the petitioner would be under an obligation to satisfy the demand raised

by the Commission in regard to the period covered under the 2017

Regulations.


57.   This Writ Petition is disposed of accordingly. No costs.


      Consequently, connected miscellaneous applications, if any, shall stand

closed.




                                                  DHIRAJ SINGH THAKUR, CJ.



                                                      RAVI CHEEMALAPATI, J.

SSN/AKN/KBS 97 24 HCJ & RCJ WP_24693_2024 HON'BLE MR.JUSTICE DHIRAJ SINGH THAKUR, CHIEF JUSTICE & HON'BLE MR. JUSTICERAVI CHEEMALAPATI Writ Petition No: 24693 of 2024 DATE : 22.04.2026 SSN/AKN/KBS