Showing contexts for: theme engineering in (Exemption) M/S Msv International Inc vs National Highways Authority Of India on 17 June, 2021Matching Fragments
9. Finally, it was submitted that the prayers in the main petition and this application were identical and therefore, grant of interim order directing the removal of the petitioner from black-listing would tantamount to grant of the final relief. Reliance has been placed by learned Senior Counsel on Patel Engg. Ltd. v. Union of India (2012) 11 SCC 257, NCC-BGR Consortium and Another v. NTPC Limited and Another 2020 SCC OnLine Del 68, National Highways Authority of India & Ors v. Neeraj Upadhyay Order dated 21st February, 2014 in Civil Appeal No. 2732/2014 and National Highways Authority of India v. Theme Engineering Services Private Ltd. & Others 2021 SCC OnLine Del 1357, in support of his submissions.