delay events in the Rejoinder, delay in
OMP (COMM) 10/2018 Page 4
FRL revisions, delay in issuance of drawings, delay in land
Acquisition, delay ... service road due to delay in
land, utility shifting, decisions, issue of drawings etc., Claimant's
delay analysis in Rejoinder and the Strip Charts
permitted IRCON to deduct liquidated
damages and thereafter carry out the delay analysis and grant extension of
time.
36. The relevant observations of the Arbitral ... Contract, liquidated damages are levied for
delays attributable to the Contractor. Therefore, unless a delay analysis is
done and it is found the delay
states that the work execution was delayed and as such SAIL got a delay analysis done by one
M/s Dastur & Co. A perusal ... Construction Ltd. as a
consequence to the aforesaid delay analysis report. Thus, the aforesaid delay analysis report is a
document created at the expense
Backwash Sump was not made available to respondent as per
Delay Analysis Sheet. Letters dated 14.05.2014, 17.07.2014 and 24.07.2014 are not denied
by the petitioner ... fabrication yard was delayed by petitioner.
Petitioner repeatedly requested to expedite civil progress and handover Civil Fronts. Delay
analysis sheet enclosed with letter dated
M/S S.K.B.Builders India Limited vs Indianoil Corporartion Limited on 2 August
consortium, after recording the reservations of SMS to the delay
analysis prepared by ONGC. The caveat further stated that SMS was
reiterating the contents ... ONGC, its reply to the delay analysis statement
prepared by ONGC, along with its own delay analysis statement dated
18th July, 2018, in which ONGC
issues
raised by you shall be dealt during the detailed delay analysis
as per provisions of contract at a later date. However,
considering the continuity ... management accords
extension of time up to 31.12.2017 with RRLD, without delay
analysis at this stage."
9. Relying on the above letter
nature of work during the said period included
Project Coordination, Marketing, Delay Analysis, Auditing and Training and
Development. From 28.10.2014 to 28.12.2016, he was posted ... primary feature of his
work during the relevant period was Delay Analysis, Preparation for Contract
Closure, Marketing, Resolution of long pending issues, labour unrest, audit
sample. No reason has been stated by the Food Analyst
for delayed analysis of the food. It is not known whether the sample was
kept ... reason that there was delay. There is no
prejudice caused to the petitioners due to the delayed analysis of the food
sample. As said earlier
extension was granted during the execution of contract, pending detailed
delay analysis, payment against Running Account Bills should be released
to the contractor without deducting ... work by the given date.
3.1. The petitioner addressed a detailed delay analysis with letter
dated 19.11.2020 explaining various grounds of delay attributable