Secretary to Government,
Government of Tamil Nadu,
Electricity Board Department,
Secretariat Building, Chepuak, Chennai.
2. The Chairman,
Tamilnadu Electricity Board,
Anna Salai, Chennai ... Respondents
Prayer ... Secretary to Government, Government of Tamil Nadu, Electricity Board Department, Secretariat Building, Chepuak, Chennai and the Chairman, Tamilnadu Electricity Board, Anna Salai, Chennai, respondents
PHOTOGRAPHS SHOWING THE 11 KV ELECTRIC LINE DRAWN
ADJACENT TO THE SHOOL BUILDING THAT TOO OVER THE SSHOOL
PALY GROUND
EXT.P2. TRUE COPY ... lapse
attributable to the respondent Board. It is stated that the
building was constructed by the 7th respondent school
hardly one year back
Petitioner
Vs.
1.The Chairman,
Tamil Nadu Electricity Board,
K.R.R. Building, 800 Anna Salai, Chennai.
2.The Executive Engineer,
Tamil Nadu Electricity Board ... Petitioner
Vs.
1.The Chairman,
Tamil Nadu Electricity Board,
K.R.R. Building, 800 Anna Salai, Chennai.
2.The Executive Engineer,
Tamil Nadu Electricity Board
were installed by the OP just inside the main entrance of the building.
The cover of the high voltage line / wire proceeding towards the said ... wire
proceeding towards the meter boxes installed at the entrance of the building
was under the control of the Kolkata Municipal Corporation who have
life and personal safety of others from the
fall of the roof/building and negligent in not providing safety protection measures and
instruments ... Sunil Kumar and Harish due to
electrocution and fall of roof/building, thereby committed an offence
reaching the age of 21 years act as a financial
security and building block for the future. The amount will be deposited
in a fixed ... that live electric
wires should not fall on the roof of the building by strictly following the
Rules to protect the lives of the public
A.Pavadai vs The Revenue Divisional Officer on 6 February, 2014
Author: S.Manikumar
Bench
caution in regard to the
maintenance of live wire above the building and that the
deceased Hanumanthappa, came in contact with the live wire ... though the defendants 1 and 2 were
8
unaware of the building put up by the third defendant.
Necessary steps should have been taken
held that be it natural calamity or act of God,
construction of building was not in accordance with the sanctioned
5
plan-proper building materials
Dalip Kumar Jha vs State Of Punjab Etc on 1 December, 2014
Author: M.M