Terms and Conditions of Intra-State Open Access) Regulations, 2010
23. Cross subsidy surcharge.
(1) If open access facility is availed of by a subsidising ... consumer, in addition to transmission and/or wheeling charges, shall pay cross subsidy surcharge determined by the Commission. Cross subsidy surcharge determined on Per Unit
Terms and Conditions of Intra-State Open Access) Regulations, 2015
23. Cross subsidy surcharge.
(1) If open access facility is availed of by a subsidising ... customer, in addition to transmission and/or wheeling charges, shall pay cross subsidy surcharge determined by the Commission. Cross subsidy surcharge determined on per unit
access in such phases and subject to such conditions (including the cross-subsidies, and other operational constraints) as may be specified within one year ... shall have due regard to all relevant factors including such cross subsidies, and other operational constraints : Provided that such open access shall be allowed
section (2) of section 33; (j) reduction of surcharge and cross subsidies under second proviso to sub-clause (ii) of clause (d) of sub-section ... tariff under section 55; (za) the period within which the cross subsidies shall be reduced under clause (g) of section 55; (zb) details
progressively, reflects the cost of supply of electricity and also reduces cross subsidies within the period to be specified by the Commission; (h) the promotion
utilized for the purpose of meeting the requirement of current level cross-subsidy : Provided further that such surcharges and cross-subsidies shall be progressively reduced
charge shall be zero. (3) Embedded open access consumers shall pay cross subsidy surcharge and additional surcharge as determined by the Commission in accordance with
utilized for the purpose of meeting the requirement of current level cross-subsidy : Provided further that such surcharge and cross-subsidies shall be progressively reduced
consumers shall be exempted from payment of transmission charges, wheeling charges, cross subsidy surcharge and additional surcharge. However, they shall continue to pay other charges
charges of wheeling, in addition to wheeling charges and cross subsidy surcharge, to meet out the fixed cost of such distribution licensee arising