appears that on 1.12.2004, AAN had applied for
electric connection. The GEB / DGVCL did not grant the
reconnection mainly on the ground that there ... filed SCA No.21824 of
2006 against the GEB / DGVCL for suitable direction about
power connection. It was filed on 11.10.2006. The said writ
petition
carving out the SEZ area
from the existing distribution licensee area of DGVCL and by delimiting its
existing area of Supply?" This ... Appellant herein. 1st Respondent
Dakshin Gujarat Viz Company Limited (DGVCL) is the distribution licensee
in terms of Section 14 of the Electricity Act 2003 having
Jitendrabhai Babubhai Patel vs The Dakshin Gujarat Vij Co. Ltd. (Dgvcl) on 27 June, 2022
Author: A. S. Supehia
Bench: A.S. Supehia ... made thereunder ?
==========================================================
JITENDRABHAI BABUBHAI PATEL
Versus
THE DAKSHIN GUJARAT VIJ CO. LTD. (DGVCL)
==========================================================
Appearance:
MR KIRTIDEV R DAVE(3267) for the Petitioner
former petition is the Dakshin
Gujarat Vij Company Limited ("DGVCL", for short). The
petition has been preferred under Articles ... Crores for
168.62 Million Units (MU) electricity issued by DGVCL
upon respondent No.1Essar Steel India Limited
(hereinafter referred to as "ESIL
Merely because the name on
the electricity bill is not changed, the DGVCL cannot merge
the Bill, though the consumers are different with different
premises ... arrangement have been made by the licensee for
supply of electricity. The DGVCL has failed to appreciate
that the part or combination of part
denial. It is
undisputed that the petitioner is a registered contractor with
DGVCL, having been awarded the contract for electrification
work in the villages ... that a sum of ₹40,00,000/- is due
and receivable from DGVCL for the work completed to date. It
appears that the stock
Dakshin Gujarat Vij Company Limited -
original petitioner (hereinafter referred to "the DGVCL" for
short), by confirming the order passed by the appellate
authority ... dated 1/11/2013 by which the learned appellate
authority directed the DGVCL to refund the excess amount
paid by Essar Steel India Limited - respondent
petitioner has further stated that
on 23.10.2017 the respondent No.1 DGVCL
addressed a letter to the petitioner
requesting them to complete the work
awarded ... remain present for personal hearing on
1.3.2018 at the corporate office of DGVCL,
Surat at 11 hours for execution of work of
supply and installation
petitioner has further stated that
on 23.10.2017 the respondent No.1 DGVCL
addressed a letter to the petitioner
requesting them to complete the work
awarded ... remain present for personal hearing on
1.3.2018 at the corporate office of DGVCL,
Surat at 11 hours for execution of work of
supply and installation
Dakshin Gujarat Vij Co Ltd - Dgvcl & 2 vs Bayer Vapi Private Limited (Bvpl) & 2 on 3 July, 2015
Author: N.V.Anjaria
Bench ... SPECIAL CIVIL APPLICATION NO. 7117 of 2014
==========================================================
DAKSHIN GUJARAT VIJ CO LTD - DGVCL & 2....Applicant(s)
Versus
BAYER VAPI PRIVATE LIMITED (BVPL