speak rescinding of contract,
but it speaks of the breach of the contract or when the
contract is broken. Evidently, the contract was broken ... right to terminate the contract is on account of the contract
terms being broken by a party to the contract. In the case
on hand
progress of the work, or after the completion or abandonment of the contract by the Contractor, shall also be final, conclusive and binding ... progress of the work, or after the completion thereof or abandonment of the contract by the Contractor shall be final and conclusive and binding
plaintiff and the plaintiff by his conduct accepted or abandoned the contract and has come out with the suit only after knowing that the price ... delay coupled with other circumstances indicates that the plaintiff has abandoned the contract then no question of discretion arises. This proposition is correct. The learned
deductible expenditure since the
contract has been abandoned. Although the assessee has
abandoned the contract, the fact remains that they have
made a claim ... contract has been abandoned, the entire expenditure is a
8
deductible expenditure. Although the assessee has
abandoned the contract, the fact remains that they have
contract to be enforceable in law.
(ii) The plaintiffs themselves abandoned the alleged
contract during the pendency of RFA No.374/1989, the
compromise ... concluded
contract. Secondly, that assuming it is a concluded contract,
it has been abandoned by the plaintiffs, these pleas are
mutually destructive. Either a contract
Kare Electronics And Developments Pvt ... vs M/S Panyam Cements & Mineral Industries ... on 20
Clause (2) of the conditions of contract, which provided for rescinding the contract in case of abandonment of work, the appellant-firm was called upon ... whether the action of the Board in terminating the contract on the ground of abandonment of work can be said to be fair, non-arbitrary
Upon such default the
contractor can stop the work and may abandon the
contract and seek compensation on the basis of fair and
reasonable value ... Upon such default the
contractor can stop the work and may abandon the
contract and seek compensation on the basis of fair and
reasonable value
Upon such default the
contractor can stop the work and may abandon the
contract and seek compensation on the basis of fair and
reasonable value ... Upon such default the
contractor can stop the work and may abandon the
contract and seek compensation on the basis of fair and
reasonable value
entitled to annual increments at the rate of Rs. 10. The contract also provides that in the event of Muthuswamy deciding to start ... that it is Muthuswamy that has committed the breach of the contract and abandoned the service voluntarily and therefore, he is not entitled (liable