dealing with (NH-19-4L Chhapra - Hajipur
Section on BOT (Annuity).
Chhapra Hajipur Expressways Limited Madhucon
House, Plot No.1129/A Road ... BOT (Annuity), length of which is 66.74 K.M.
and date of Award was 27.01.2011 and scheduled
date of completion of project was 24.7.2013, which
Jurisdiction Case No.8375 of 2021
======================================================
NH-30-Patna Bakhtiyarpur section on BOT (Toll)
... ... Petitioner/s
Versus
The State of Bihar
... ... Respondent/s
======================================================
Appearance ... 8375 of 2021
titled as NH-30- Patna Bakhtiyarpur Section on BOT (Toll)
Vs. the State of Bihar & Ors. was initiated on the basis
dealing with (NH-19-4L Chhapra - Hajipur
Section on BOT (Annuity).
Chhapra Hajipur Expressways Limited Madhucon
House, Plot No.1129/A Road ... BOT (Annuity), length of which is 66.74 K.M.
and date of Award was 27.01.2011 and scheduled
date of completion of project was 24.7.2013, which
dealing with (NH-19-4L Chhapra - Hajipur
Section on BOT (Annuity).
Chhapra Hajipur Expressways Limited Madhucon
House, Plot No.1129/A Road ... BOT (Annuity), length of which is 66.74 K.M.
and date of Award was 27.01.2011 and scheduled
date of completion of project was 24.7.2013, which
8352 of 2021
======================================================
NH-19-4L Chhapra - Hajipur Section on BOT (Annuity)
... ... Petitioner/s
Versus
The State of Bihar
... ... Respondent/s
======================================================
Appearance ... titled as NH-19-4L Chhapra - Hajipur Section on BOT
(Annuity) Vs. the State of Bihar & Ors , was initiated on the
basis
Vishal Tripathi, stands
constituted by N.H.A.I. for monitoring 40 projects in relation to
which construction is being carried out within the State ... work plan and work program of the
projects.
ii. Works Progress- Target/Achievement
iii. Bottlenecks impending the project and possible
resolution identifying the key stakeholder
Vishal Tripathi, stands
constituted by N.H.A.I. for monitoring 40 projects in relation to
which construction is being carried out within the State ... work plan and work program of the
projects.
ii. Works Progress- Target/Achievement
iii. Bottlenecks impending the project and possible
resolution identifying the key stakeholder
Jurisdiction Case No.8375 of 2021
======================================================
NH-30-Patna Bakhtiyarpur section on BOT (Toll)
... ... Petitioner/s
Versus
The State of Bihar
... ... Respondent/s
======================================================
Appearance ... Section on BOT (Toll).
The correctness of the affidavit dated 04.02.2022,
filed by Shri Prabhanshu Shekhar, Deputy General Manager
(Tech) cum Project Director in National
Vishal Tripathi, stands
constituted by N.H.A.I. for monitoring 40 projects in relation to
which construction is being carried out within the State ... work plan and work program of the
projects.
ii. Works Progress- Target/Achievement
iii. Bottlenecks impending the project and possible
resolution identifying the key stakeholder
8352 of 2021
======================================================
NH-19-4L Chhapra - Hajipur Section on BOT (Annuity)
... ... Petitioner/s
Versus
The State of Bihar & Ors.
... ... Respondent/s
======================================================
Appearance ... BOT (Annuity), length of which is
66.74 K.M. and date of Award was 27.01.2011 and scheduled
date of completion of project was 24.7.2013, which