extension of mining leases.
9. Since the Petitioner Company has been granted the
mining lease for non-captive purposes, hence, Section 8A(6)
is attracted ... view such
leaseholders who had moved applications for renewal of
captive/non-captive mines would be entitled to continue
process of mining and
winning of coal was started. The mining operations commenced on
02.11.2005 and coal dispatch from the Panchwara Coal Mine
started ... also mentioned that the Panchwara Central Coal
Block is a captive coal mine of the Punjab State Electricity Board
and therefore, royalty cannot be determined
extension of mining leases.
9. Since the Petitioner Company has been granted the
mining lease for non-captive purposes, hence, Section 8A(6)
is attracted ... view such
leaseholders who had moved applications for renewal of
captive/non-captive mines would be entitled to continue
Ispat
Bhawan, Lodi Road, New Delhi and one of its captive mines at
Bhawnathpur under the Raw Material Division P.O. & P.S.
Bhawnathpur ... Jharkhand (through Secretary of Mines Government
of Jharkhand)
2. The Assistant Mining Officer, Garhwa.
3. The Dy. Director-Mines Cum Certificate Officer, Palamau Division
Ispat
Bhawan, Lodi Road, New Delhi and one of its captive mines at
Bhawnathpur under the Raw Material Division P.O. & P.S.
Bhawnathpur ... Jharkhand (through Secretary of Mines Government
of Jharkhand)
2. The Assistant Mining Officer, Garhwa.
3. The Dy. Director-Mines Cum Certificate Officer, Palamau Division
supply of washer grade coking coal to power houses other than captive
ones, as pointed out in your letter, falls within the jurisdiction ... Government of India
on 16.10.1971 under which except the captive mines of TISCO and
IISCO, the management of all coking coal mines had been taken
Central Government
has nationalized all the coking coal mines in the country other
than the captive ... mines by enacting Coking Coal Mines
(Nationalization) Act, 1972 . On enacting the same, Central
Government nationalized other non-coking coal mines besides
the captive mines
Raiyati Land
admeasuring 1257.19 acres comprised in the Mining Lease
for the Kathautia Coal Mine is also yet to be handed over to
the Petitioner ... CMDPA, including the right to produce coal from
the Kathuatia Coal Mine for captive use in the specified
power plants as well as the obligation
Raiyati Land
admeasuring 1257.19 acres comprised in the Mining Lease
for the Kathautia Coal Mine is also yet to be handed over to
the Petitioner ... CMDPA, including the right to produce coal from
the Kathuatia Coal Mine for captive use in the specified
power plants as well as the obligation
Raiyati Land
admeasuring 1257.19 acres comprised in the Mining Lease
for the Kathautia Coal Mine is also yet to be handed over to
the Petitioner ... CMDPA, including the right to produce coal from
the Kathuatia Coal Mine for captive use in the specified
power plants as well as the obligation