from pole to pole. An order of the Consumer
Grievance Redressal Forum (CGRF) in his favour could
not dispel the darkness at his home ... referred to as
'the Electricity Act ' for short) before the CGRF
constituted under the Kerala State Electricity Regulatory
Commission (Consumer Grievance Redressal Forum
aggrieved consumer can redress grievance by
approaching the Consumer Grievance Redressal Forum (CGRF)
constituted under the Kerala State Electricity Regulatory Commission
(Consumer Grievance Redressal Forum ... Electricity Board. The appellant instead filed a complaint before
the CGRF and filed a Writ Petition in this Court for a mandamus to
the CGRF
taken to the concerned Consumer Grievances Redressal Forum,
hereinafter, the "CGRF", constituted under Section 42 (5) of the
Electricity Act, 2003, which obliges ... parties, it is abundantly appropriate that the matter gains
attention of the CGRF since technical personnel are involved in
that Commission, as is apparent from
Consumer Grievance Redressal Forum (hereinafter referred to as the
'CGRF'). CGRF is established by the licensee themselves as
mandated under the Electricity ... related to maintainability. The learned Single Judge was of the view
that CGRF is an institutional grievance redressal forum maintained
by the licensee
Consumer Grievance Redressal Forum (hereinafter referred to as the
'CGRF'). CGRF is established by the licensee themselves as
mandated under the Electricity ... related to maintainability. The learned Single Judge was of the view
that CGRF is an institutional grievance redressal forum maintained
by the licensee
directing
the respondent to approach the Consumer Grievance Redressal
Forum (CGRF). Respondent was directed to pay a sum of
Rs.2,00,000/- and impugned ... bill was directed to be kept in
abeyance till the CGRF took a decision. Respondent complied
with the direction to pay the amount. CGRF
Cheppad, challenges the orders of the Consumer
Grievance Redressal Forum (hereinafter 'CGRF') dated 03.03.2022 and the
State Electricity Ombudsman dated ... Code (hereinafter 'the Supply Code').
3. The petitioner approached the CGRF challenging the said
demand, and the Forum ordered that the short assessment
short `Regulations 2005') before the Consumers'
Grievance Redressal Forum (CGRF). It was filed with prayers to quash
Ext.P5 mahazar and also ... sought to be amended as per Ext.P9. On
26.11.2009 the CGRF passed Ext.P10 interim order directing that the
supply
2009 ISSUED BY THE
RESPONDENT TO THE DEPUTY CHIEFENGINEER, CGRF,
KOTTARAKKARA.
EXT P2- REPLYDTD.21/1/2010 FILED BY THE PETITIONER BEFORE THE
CONSUMER GRIEVANCE ... REDRESSAL FORUM,KOTTARAKKARA.
EXT P3- ORDER NO.CGRF/KTR/OP NO.453/2009/72 DTD.27/2/2010
ISSUED BY THE DEPUTY CHIEF ENGINEER, CHAIRPERSON
27574/2024 has been filed to implement order No.CGRF-CR/OP
No.120/2023-24 of the Consumer Grievances Redressal Forum,
Central Region (hereinafter ... referred to as the CGRF), WP(C)
No.28394/2024 has been filed by the Kerala State Electricity Board
(hereinafter referred to as the KSEB