CHARGE
4. The charge against the accused Ram Prakash under Section
11 of Prevention of Corruption Act, 1988 and against accused M/s Megha
Engineering ... after the accused had handed over the
charge.
Ld. Counsel for accused M/s Megha Engineering &
Infrastructure Ltd. did not examine the witness despite
Airport Authority Of India vs M/S Lok Shail Enterprises on 17 October, 2023
IN
Supreme Court in case title
'Ssangyong Engineering and Construction Ltd Vs. N.H.A.I,
(2019) 15 SCC 131' held that the amended ... excepted matters' is only
those decisions of Engineer In charge which are taken in writing
by invoking any of the enumerated clause under Clause
that till the time he was associated with the
present project Engineering-in-Charge of the defendant, not issued any letter
under clause ... other contract made by the contractor with the
Engineering in Charge or the NBCC.
It is an agreed term of the contract that
PROSECUTION EVIDENCE
4. To connect the arraigned accused persons with the offences
charged, the prosecution in total has examined twelve witnesses viz
Sh. Keshav Chandra ... Delhi as PW9, Sh. Tilak Raj Magon, Director M/s Ambica
Engineering Pvt. Ltd. as PW10, Sh. Radhey Shyam,
Superintendent Engineer, Delhi
Additional Commissioner Order);
Kumar (Engineering) in MCD and was
in-charge of Engineering and
Sanitation Department and
Shahdara South and North
Zone. He accorded sanction
accused M/s. Reliance Engineering Works, for
construction of storage tanks.
12. It is further stated in the charge sheet that the balance amount ... even as per the charge
sheet, the said order was placed on M/s. Swastika Engineering.
25. The Ld. Defence counsel has also argued that
Loha Mandi,
Naraina,Delhi28. During investigation the said firm Ramesh
Engineering Works was found to be a fictitious and nonexisting firm ... issued by R
C Luthra as prop of Ramesh Engineering works.
CHARGE
26 Copies required U/S 207 Cr P C supplied to accused.
After
year.
5. As per the chargesheet, the budgetary quotation
obtained from M/s. Bhartiya Vehicles & Engineering Co.
Ltd. was not put up before ... filed the Chargesheet Ex. PW13/B
before the Court. At the time of filing of the Charge
sheet, accused persons namely
Haryana) .....Complainant
Versus
1. A. K. Jhamb
The then Director Engineering & CMD (Addl. Charge)
National Projects Construction Corporation Ltd.
(A Govt. of Indian Enterprises ... vacancy.
5. Shri A.K. Jhamb has taken over charge of the post of
Director (Engg.) NPEC in Schedule 'C' scale