EPC
contractor & its sub-contractors and not on account of
any reasons which were beyond the control of the
petitioner and the EPC contractor ... petitioner and the EPC
contractor/sub-contractors. In our view there has been
failure on the part of the EPC contractor to mobilize
resources
EPC Contractor shall be final,binding and
conclusive evidence in respect of the amounts payable by the
Construction Contractor to the EPC Contractor ... EPC
Contractor may have in relation to the Construction
Contractor's liability."
10] The bank hereby waives the necessity for the EPC
Contractor
amounting to INR 1,026.08 million being the claim received from
EPC Contractor for additional expenditure incurred in respect of laying of
Sudan pipeline ... India
Limited, where the Company's share being 90%. The EPC contractor executing the
project on behalf of the consortium claimed additional costs aggregating
EPC) Contract method. As per this method, any bidder who
won two or more bid packages became eligible to act as a `Single EPC
Contractor ... appoint
one single EPC contractor and all other winner
bidders shall work as sub-contractor to the
proposed single EPC contractor."
"Contract agreement
with Oil India Limited, Company's
share being 90%. The EPC contractor executing the project on
behalf of the consortium has claimed additional costs ... also considered the various decisions cited before us. We find
the EPC Contractor executing the project on behalf of the
consortium claimed additional costs aggregating
quash the decision
selecting the respondent No. 3 as EPC contractor, but later when it came to
light that resolutions were already passed ... generation of power
respectively. For the purpose of selection of EPC contractor for 160 MW Natural
Fired Combined Cycle Power Plant, Request for Qualification
that the EPC has
incurred any loss and has been indemnified by MAPEX to that
extent.
(c) Even no agreement entitling EPC Contractor to claim ... show whether under the terms of the sub-contract/EPC contract, the EPC
Contractor was entitled to raise a claim of prolongation cost
Project Site from EPC Contractor to Construction
Contractor. In case of failure of such notice being
given to the Construction Contractor, Notice to
proceed shall ... Concessionaires/EPC Contractors Representative,
(which consent shall not be unreasonably withheld).
The construction Contractor shall furnish to the
Concessionaire/EPC Contractor particulars of the
subcontractors
appoint one
single EPC contractor and all other winner bidders
shall work as sub contractor to the proposed single
EPC contractor.
Contract agreement between EPC ... appoint one
single EPC contractor and all other winner bidders
shall work as sub contractor to the proposed single
EPC contractor.
Contract agreement between EPC
executing the scope related to an EPC Contract : (ix) In case Applicant proposes to employ some : EPC contractor or other contractor(s) then Name