Schedule to the
EIA Notification, 2006. The entry 8(a) of the Schedule of EIA
Notification 2006 as follows:
Building and Construction projects greater than ... Environmental Clearance from
Central Government.
Thereafter vide Gazette Notification No. S.O. 3252 (E) dated
22.12.2014, the Ministry of Environment, Forest and Climate
Change
Schedule to the EIA Notification, 2006. The entry
8(a) of the Schedule of EIA Notification 2006 as follows:
Building and Construction projects greater than ... Environmental Clearance from Central
Government.
Thereafter vide Gazette Notification No. S.O. 3252 (E) dated
22.12.2014, the Ministry of Environment, Forest and Climate
Change
2015, dated
03.04.2017 and applied to State Level Environment Impact Assessment
Authority(SEIAA)- Tamil Nadu for Environmental Clearance(EC) as
per EIA Notification ... 6227/2017, dated 21.07.2017 had stated that "as per MoEF
Notification No.S.O.3252 (E) dated 22.12.2014, the construction of
industrial shed, school
Animal Husbandry, Dairying and Fisheries (FS-1) Department dated
22.12.2014 to carry out the techno-economic feasibility studies of the
project. Accordingly, required surveys ... ecologically and environmentally sensitive as per CRZ
Notification, 2011 and Environmental Impact Assessment Notification,
2006. The necessary District Level Coastal Regulation Zone (CRZ)
clearances were
issued amendment to the EIA Notification vide
S.0.3252 (E) dt. 22.12.2014 exempting Industrial Shed, School, Colleges,
Hostel for educational Institution mentioned under ... Notification,
2006 & its subsequent amendments, the activities listed in the Schedule of
the EIA Notification require prior Environmental Clearance. As per EIA
Notification