information on its website. (v) The floor price of transmission and wheeling charges determined on the basis of relevant order of the Commission shall ... favour of whom the capacities have been allocated, shall pay transmission charges, wheeling charges, as the case may be, determined by bidding under
system shall pay the wheeling or Dedicated Distribution facility charge, as the case may be, as under: (a) Wheeling charges payable to the Distribution Licensee ... charges payable by a user of the Distribution System User under this Regulations may comprise of any combination of fixed/demand charges, and variable charges
supply and shall separately and clearly indicate the following: (i) Wheeling charges, recovered or recoverable from consumers in accordance with Regulation 16.1 below; (ii) Cross ... wheeling of electricity shall be raised on the Generator or the Licensee and shall separately and clearly indicate the following: (i) Wheeling charges, recovered
Conditions of Tariff) Regulations, 2005
57. Components of tariff.
- 57.1 The wheeling charges of the Distribution Licensee shall provide for the recovery of the aggregate ... consumers and Distribution System Users; and (g) Contribution to contingency reserves. Wheeling charges = Aggregate revenue requirement, as above, minus: (h) Non-tariff income
year; plus (c) Two months equivalent of the expected revenue from wheeling charges at the prevailing tariffs; minus (d) Amount, if any, held as security ... assets shall be allowed towards such appropriation in the calculation of wheeling charges: Provided that where the amount of such Contingencies Reserves exceeds five
term Open Access shall be granted and an estimate of the wheeling charges. (j) The applicant shall sign the Connection and Use of Distribution System
specified in the MERC (Transmission Open Access) Regulations, 2014. Provided that Wheeling charges would not be applicable in case of all such Open Access consumers ... been accessed under the Transmission Open Access Regulation. Provided further that wheeling charges would not be applicable in case of all Generating stations which have
Generating station shall pay the wheeling charge to the Distribution Licensee as determined by the Commission. Provided that wheeling charges would not be applicable
entitled to levy a penalty equal to the two times wheeling charges for the financial year or part thereof for which he had failed
shall pay to the Distribution Licensee an additional surcharge on the charges of wheeling and cross-subsidy surcharge, to meet the fixed cost of such ... same assets or facilities, or from other Consumers, either through wheeling charges, standby charges or such other charges as may be approved by the Commission