extent of open access in successive phases and in determining the charges for wheeling, it shall have due regard to all relevant factors including such ... allowed on payment of a surcharge in addition to the charges for wheeling as may be determined by the State Commission: Provided further that such
from other business to be utilised for reducing the transmission and wheeling charges under proviso to section 41; (p) reduction *** of surcharge and cross-subsidies ... section (2) of section 42; (q) payment of additional charges on charges of wheeling under sub-section (4) of section 42; (r) guidelines under
following functions, namely:– (a) determine the tariff for generation, supply, transmission and wheeling of electricity, wholesale, bulk or retail, as the case may be, within ... consumers under section 42, the State Commission shall determine only the wheeling charges and surcharge thereon, if any, for the said category of consumers
rates, charges and terms and conditions in respect of intervening transmission facilities under proviso to section 36; (j) payment of the transmission charges ... from other business to be utilised for reducing the transmission and wheeling charges under proviso to section 41; (o) duties of electricity trader under
extent of open access in successive phases and in determining the charges for wheeling, it shall have due regard to all relevant factors including such ... eliminated on payment of a surcharge in addition to the charges for wheeling as may be determined by the State Commission; And whereas the second
Ladakh (Green Energy Open Access), Regulations, 2024
17. Wheeling Charges
specified by the concerned State Commission, be utilised for reducing its charges for wheeling: Provided further that the distribution licensee shall maintain separate accounts
neighbouring country(ies) subject to payment of the applicable charges for transmission or wheeling of electricity through the Indian grid. Provided that in case ... discovered through competitive bidding, subject to payment of the applicable charges for transmission or wheeling of electricity through the Indian grid. (3) Where the tariff
receipts on account of Cross-Subsidy Surcharge and Additional Surcharge on charges of wheeling
Rules, 2005
6. The surcharge under section 38
.-The surcharge on transmission charges under section 38, the manner of progressive reduction of such surcharge ... section 38 shall be in accordance with surcharge on the charges for wheeling, the manner of progressive reduction of such surcharge and the manner