Union of India - Act
Joint Electricity Regulatory Commission for the State of Goa and Union Territories (Generation, Transmission and Distribution Multi Year Tariff) Regulations, 2018
UNION OF INDIA
India
India
Joint Electricity Regulatory Commission for the State of Goa and Union Territories (Generation, Transmission and Distribution Multi Year Tariff) Regulations, 2018
Rule JOINT-ELECTRICITY-REGULATORY-COMMISSION-FOR-THE-STATE-OF-GOA-AND-UNION-TERRITORIES-GENERATION-TRANSMISSION-AND-DISTRIBUTION-MULTI-YEAR-TARIFF-REGULATIONS-2018 of 2018
- Published on 10 August 2018
- Commenced on 10 August 2018
- [This is the version of this document from 10 August 2018.]
- [Note: The original publication document is not available and this content could not be verified.]
Chapter 1
Preliminary
1. Short Title, Commencement and Extent.
- 1.1. These Regulations shall be called the Joint Electricity Regulatory Commission for the State of Goa and Union Territories (Generation, Transmission and Distribution Multi Year Tariff) Regulations, 2018.2. Definitions.
- 2.1 In these Regulations, unless the context otherwise requires:1. "Accounting Statements" shall mean for each Financial Year, the balance sheet, the profit and loss statement, the cash flow statement and the report of the statutory auditors together with notes thereto:
Provided that in case of any local authority engaged in the business of distribution of electricity, the Accounting Statement shall mean the items, as mentioned above, prepared and maintained in accordance with the relevant Acts or Statutes as applicable to such local authority;2. "Act" shall mean the Electricity Act, 2003 (36 of 2003), as amended from time to time;
3. "Aggregate Revenue Requirement" or "ARR"shall mean the annual revenue requirement comprising of allowable expenses and return on capital pertaining to the Generating Company, Transmission Licensee or Distribution Licensee, for recovery through tariff, in accordance with these Regulations;
4. "Allocation Statement" shall mean for each Financial Year, a statement showing the amounts of any revenue, cost, asset, liability, reserve or provision etc. determined by apportionment or allocation between Distribution Wires Business and Retail Supply Business of a Distribution Licensee;
5. "Allotted Transmission Capacity" shall mean the power transfer in MW between the specified point(s) of injection and point(s) of drawal allowed to a Long-term Consumer or a Medium-term Consumer on the intra- State transmission system under the normal circumstances and the expression "allotment of transmission capacity" shall be construed accordingly;
6. "Auxiliary Energy Consumption" or "AUX" in relation to a period in case of a Generating Station means the quantum of energy consumed by auxiliary equipment of the Generating Station, such as the equipment being used for the purpose of operating plant and machinery including switch yard of the Generating Station and the transformer losses within the Generating Station, expressed as a percentage of the sum of gross energy generated at the generator terminals of all the units of the Generating Station:
Provided that Auxiliary Energy Consumption shall not include energy consumed for supply of power to housing colony and other facilities at the Generating Station and the power consumed for construction works at the Generating Station;7. "Applicant" shall mean a Generating Company, Transmission Licensee or Distribution Licensee who has made an application for determination of Aggregate Revenue Requirement and tariff in accordance with the Act and these Regulations and shall include a Generating Company, Transmission Licensee or Distribution Licensee whose tariff is being determined by the Commission on suo-motu basis;
8. "Area of Supply" shall mean the area within which a Distribution Licensee is authorised by its license to supply electricity;
9. "Authority" shall mean the Central Electricity Authority referred to in Section 70 of the Act;
10. "Availability" in relation to a transmission system for a given period shall mean the time in hours during the period the transmission system is capable of transmitting electricity at its rated voltage expressed in percentage of total hours in the given period;
11. "Bank Rate" shall mean the Bank Rate declared by the Reserve Bank of India from time to time;
12. "Base Year" shall mean the Year immediately preceding the first Year of the Control Period;
13. "Bulk Power Transmission Agreement" shall mean an executed Agreement that contains the terms and conditions under which a Transmission System User is entitled to access the intra-State transmission system of a Transmission Licensee;
14. "Change in Law" shall mean the occurrence of any of the following events:
15. "Central Commission" or "CERC" shall mean the Central Electricity Regulatory Commission referred to in sub-section (1) of Section 76 of the Act;
16. "Commission" shall mean the Joint Electricity Regulatory Commission for the State of Goa and Union Territories (except Delhi) referred to in Section 83 of the Act;
17. "Control Period" shall mean the period of three (3) Years from April 1, 2019 to March 31, 2022;
18. "Central Transmission Utility" or "CTU" shall mean any Government company which the Central Government may notify under sub-section (1) of Section 38 of the Act;
19. "Cut-off Date" shall mean 31stMarch of the Year closing after two (2)Years from the Year of commercial operation of the project, and in case the project is declared under commercial operation in the last quarter of a Year, the Cut-off Date shall be 31stMarch of the Year closing after three (3) Years from the Year of commercial operation:
Provided that the Cut-off Date may be extended by the Commission if it is proved on the basis of documentary evidence that the capitalisation could not be made within the Cut-off Date for reasons beyond the control of the project developer;20. "Consumer" shall any person who is supplied with electricity for his own use by a Licensee or the Government or by any other person engaged in the business of supplying electricity to the public under this Act or any other law for the time being in force and includes any person whose premises are for the time being connected for the purpose of receiving electricity with the works of a Licensee, the Government or such other person, as the case may be, but shall be restricted to such Consumers within the State;
21. "Contracted Capacity" shall mean the capacity in MW contracted by a Transmission System User;
22. "Day" shall mean a day starting at 00.00 hours and ending at 24.00 hours;
23. "Date of Commercial Operation" or "COD" in case of a transmission system shall mean the date declared by the Transmission Licensee from 00.00 hours,for which an element of the transmission system is in regular service after successful trial operation for transmitting electricity, and communication signal from sending end to receiving end:
Provided that where the transmission line or substation is dedicated for evacuation of power from a particular Generating Station, the Generating Company and Transmission Licensee shall endeavour to commission the Generating Station and the transmission system simultaneously as far as practicable and shall ensure the same through appropriate Implementation Agreement:Provided also that in case a transmission system or an element thereof is prevented from regular service for reasons not attributable to the Transmission Licensee or its supplier or its contractors but is on account of the delay in commissioning of the concerned Generating Station or in commissioning of the upstream or downstream transmission system, the Transmission Licensee shall approach the Commission through an appropriate application for approval of the Date of Commercial Operation of such transmission system or an element thereof:Provided further that the Date of Commercial Operation for a Generating Station shall be as defined in the prevalent CERC Tariff Regulations;24. "De-capitalisation" shall mean reduction in Gross Fixed Assets of the project corresponding to the removal of assets as approved by the Commission;
25. "Distribution Business" shall mean the business of operating and maintaining a distribution system for supplying electricity in the Area of Supply of the Distribution Licensee;
26. "Distribution Licensee" shall mean a Licensee authorised to operate and maintain a distribution system for supplying electricity to the Consumers in its Area of Supply;
27. "Distribution Wires Business" shall mean the business of operating and maintaining a distribution system for wheeling of electricity in the Area of Supply of the Distribution Licensee;
28. "Expected Revenue from Tariff and Charges" shall mean the revenue estimated to accrue to the Generating Company, Transmission Licensee or Distribution Licensee from the regulated business at the prevailing tariff;
29. "Electricity Supply Code" shall mean the Electricity Supply Code specified under Section 50 of the Act;
30. "Existing Project" shall mean a project declared under commercial operation prior to April 1, 2019;
31. "Force Majeure Event" shall mean, with respect to any party, any event or circumstance or combination of events or circumstances including those stated below, which is not within the reasonable control of, and is not due to an act of omission or commission of that party and which, by the exercise of reasonable care and diligence, could not have been avoided, and without limiting the generality of the foregoing, would include the following events:
32. "Generation Company" shall mean any company or body corporate or association or body of individuals, whether incorporated or not, or artificial juridical person, which owns or operates or maintains a Generating Station and for the purpose of these Regulations, shall exclude a company generating electricity from renewable sources;
33. "Generating Station" shall mean any station for generating electricity, including any building and plant with step-up transformer, switchgear, switch yard, cables or other appurtenant equipment, if any, used for that purpose and the site thereof; a site intended to be used for a Generating Station, and any building used for housing the operating staff of a Generating Station, and where electricity is generated by water-power, includes penstocks, head and tail works, main and regulating reservoirs, dams and other hydraulic works, but does not in any case include any sub-station and for the purpose of these Regulations shall exclude stations generating electricity from renewable sources;
34. "Grid" shall mean the high voltage backbone system of inter-connected transmission lines, sub-stations and generating plants;
35. "Gross Station Heat Rate" or "GHR" means the heat energy input in kCal required to generate one kWh of electrical energy at generator terminals of a thermal Generating Station;
36. "Integrated Utility" means the Department of Power in the State of Goa and the Union Territories of Andaman and Nicobar Islands, Chandigarh, Daman and Diu, Lakshadweep and Puducherry, in its present form or the successor entities performing more than one of the functions of generation, transmission and distribution after restructuring thereof;
37. "Licensed Business" shall mean as defined in Regulation 2 of Joint Electricity Regulatory Commission for Goa & Union Territories (Treatment of Other Business of Transmission Licensees and Distribution Licensees) Regulations, 2009 as amended from time to time;
38. "Licensee" shall mean a person who has been granted license under Section 14 of the Act and for the purpose of these Regulations shall also include an Integrated Utility;
39. "MCLR" shall mean One Year Marginal Cost of Funds based Lending Rate;
40. "Mid-term Review" shall mean a review to be undertaken in accordance with the Regulation 5.2 (b);
41. "Month" shall mean a calendar month as per the Gregorian calendar;
42. "New Project" shall mean a project declared under commercial operation on or after April 1, 2019;
43. "Non-Tariff Income" shall mean income relating to the Licensed Business other than from tariff, excluding any income from Other Business and, in case of the Retail Supply Business of a Distribution Licensee, excluding income from wheeling and receipts on account of Cross-Subsidy Surcharge and Additional Surcharge on charges of wheeling;
44. "Operation and Maintenance expenses" or "O&M expenses" in relation to a Generating Company, Transmission Licensee or Distribution Licensee shall mean the expenditure incurred on operation and maintenance of the system by the Generating Company, Transmission Licensee or Distribution Licensee, and includes the expenditure on manpower, repairs, spares, consumables, insurance and overheads etc.;
45. "Original Project Cost" means the capital expenditure incurred by the Generating Company or the Transmission Licensee or the Distribution Licensee, as the case may be, within the original scope of the project up to the Cut-off Date as admitted by the Commission;
46. "Other Business" shall mean as defined in Regulation 2(i)(f) of Joint Electricity Regulatory Commission for Goa & Union Territories (Treatment of Other Business of Transmission Licensees and Distribution Licensees) Regulations, 2009, as amended from time to time;
47. "Prudence Check" shall mean scrutiny of the reasonableness of expenditure incurred or proposed to be incurred, financing plan, use of efficient technology, cost and time over-run and such other factors as may be considered appropriate by the Commission for determination of tariff;
48. "Rated Voltage" shall mean the manufacturer's design voltage at which the transmission system is designed to operate or such lower voltage at which the line is charged, for the time being, in consultation with Transmission System Users;
49. "Retail Supply Business" shall mean the business of sale of electricity by a Distribution Licensee to its Consumers in accordance with the terms of its license;
50. "State" shall mean the State of Goa, and includes the Union Territories, except Delhi;
51. "State Grid Code" shall mean the State Grid Code specified by the Commission under Clause (h) of subsection (1) of Section 86 of the Act;
52. "State Load Despatch Centre" or "SLDC" shall mean the centre established under sub-section (1) of Section 31 of the Act;
53. "Transmission Licensee" shall mean a Licensee authorised to establish or operate transmission lines;
54. "Transmission System User" shall mean the Distribution Licensee or Open Access User, as the case maybe, who uses the intra-State transmission network for the purpose of transmission of electricity;
55. "Useful life" in relation to a unit of a transmission system and distribution system from the Date of Commercial Operation shall be as defined in Appendix I to these Regulations;
56. "Working Day" shall mean a Day on which banks are open for business;
57. "Year" or "Financial Year" shall mean a Financial Year (FY), beginning from 1st April of calendar Year and ending on 31st March of the next calendar Year.
3. Scope of Regulation and extent of application.
- 3.1 The Commission shall determine tariff within the Multi Year Tariff framework, for all matters for which the Commission has jurisdiction under the Act, including in the following cases:(a)Supply of electricity by a Generating Company to a Distribution Licensee:Provided that where a shortage of supply of electricity exists, it may fix the minimum and maximum ceiling of tariff for sale or purchase of electricity in pursuance of an agreement, entered into between a Generating Company and a Distribution Licensee or between Distribution Licensees, for a period not exceeding one year to ensure reasonable prices of electricity;(b)Intra-State transmission of electricity;(c)Intra-State wheeling of electricity;(d)Retail supply of electricity:Provided that in case of distribution of electricity in the same area by two or more Distribution Licensees, the Commission may, for promoting competition among Distribution Licensees, fix only the maximum ceiling of tariff for retail sale of electricity:Provided further that where the Commission has allowed Open Access to certain Consumers under subsection4. Norms of operation to be ceiling norms.
- 4.1 For removal of doubts, it is clarified that the norms of operation specified under these Regulations are the ceiling norms and this shall not preclude the Transmission Licensee or the Distribution Licensee, as the case may be, and the beneficiaries from accepting improved norms of operation as determined by the Commission and such improved norms shall be applicable for determination of tariff.Chapter 2
General Principles
5. Guiding Principles for MYT Framework.
- 5.1 The Commission shall determine the tariff for matters covered under clauses (a), (b),(c) and (d) of Regulation 3.1, under a Multi Year Tariff framework with effect from April 1, 2019.6. Values for Base Year.
- 6.1 The values for the Base Year of the Control Period shall be determined on the basis of the audited accounts or provisional accounts of last three (3) Years, and other factors considered relevant by the Commission:Provided that, in absence of availability of audited accounts or provisional accounts of last three (3) Years, the Commission may benchmark the parameters with other similar utilities to establish the values for Base Year:Provided further that the Commission may change the values for Base Year and consequently the trajectory of parameters for Control Period, considering the actual figures from audited accounts.7. Segregation of Retail Supply and Distribution Wires Business.
- 1.1 The Distribution Licensee shall segregate the accounts of the Licensed Business into Distribution Wires Business and Retail Supply Business. The ARR for Distribution Wires Business shall be used to determine wheeling charges.The ARR for Retail Supply Business, which shall include the ARR for Distribution Wires Business, in accordance with Regulation 57, shall be used to determine retail supply tariff.8. Business Plan.
- 8.1 The Transmission Licensee and Distribution Licensee shall file for the Commission's approval a Business Plan for the entire Control Period, duly approved by the competent authority by August 31, 2018:Provided that the Generation Company shall not be required to file a Business Plan for the Control Period.9. Multi Year Tariff Application.
- 9.1 The Applicant shall submit the forecast of Aggregate Revenue Requirement for each year of the Control Period and tariff proposal for the first Year of the Control Period, in amanner as provided in these Regulations and in formats specified by the Commission from time to time. The application shall be accompanied by such fee payable, as may be specified by the Commission in the Joint Electricity Regulatory Commission (Conduct of Business) Regulations, 2009, as amended from time to time, by November 30, 2018:Provided that the application shall also be accompanied by the true-up Petition based on the latest available audited accounts and the annual performance review for the current Year based on the actual performance during the first six Months of the Year and estimates for the subsequent six Months.10. Trajectory for Specific Variables.
- 10.1 The Commission, while approving the Business Plan and/or Multi Year Tariff Petition, may stipulate a trajectory for certain variables, including but not limited to Auxiliary consumption, Station Heat Rate, O&M expenses etc.:Provided that the utilities shall adhere to the norms as specified in the Order on Multi Year tariff petition:Provided further that the Generating Company or Transmission Licensee or Distribution Licensee, as the case may be, may seek a review at the time of Mid-term Review of Aggregate Revenue Requirement for the balance Control Period.11. Annual Performance Review, Truing-up and tariff determination during the Control Period.
- 11.1 The Generating Company, Transmission Licensee and Distribution Licensee shall be subject to annual performance review and truing up of expenses and revenue during the Control Period in accordance with these Regulations.12. Uncontrollable and Controllable factors.
- 12.1 For the purpose of these Regulations, the term "uncontrollable factors" for a Transmission or Distribution Licensee shall comprise of the following factors, which were beyond the control of the Licensee, and could not be mitigated by the Licensee:(a)Force Majeure events;(b)Change in Law, judicial pronouncements and Orders of the Central Government, State Government or Commission;(c)Variation in the number or mix of Consumers or quantities of electricity supplied to Consumers;(d)Transmission loss;(e)Variation in the cost of power purchase due to variation in the rate of power purchase from approved sources, subject to clauses in the power purchase agreement or arrangement approved by the Commission;(f)Variation in fuel cost;(g)Change in power purchase mix;(h)Inflation;(i)Transmission Charges for a Distribution Licensee;(j)Variation in market interest rates for long-term loans;(k)Employee expenses limited to one time payment owing requirements of a pay commission and terminal liability of employees;(l)Taxes and Statutory levies;(m)Taxes on income;(n)Income from the realisation of bad debts written off:Provided that where the Applicant believes, for any variable not specified above, that there is a material variation or expected variation in performance for any Financial Year on account of uncontrollable factors, such Applicant may apply to the Commission for inclusion of such variable at the Commission's discretion, under this Regulation for such Financial Year:Provided further that the uncontrollable factors for a Generating Company shall be as specified in the prevalent CERC Tariff Regulations.13. Mechanism for pass through of gains or losses on account of uncontrollable factors.
- 13.1 Approved aggregate gain or loss to the Transmission Licensee or Distribution Licensee on account of uncontrollable factors shall be pass-through as an adjustment in the tariff of the Transmission Licensee or Distribution Licensee over such period as may be specified in the Order of the Commission passed under these Regulations:Provided that the mechanism for pass through of gains or losses on account of uncontrollable factors for a Generating Company shall be as specified in the prevalent CERC Tariff Regulations.14. Mechanism for sharing of gains or losses on account of controllable factors.
- 14.1 Approved aggregate gain to the Transmission Licensee or Distribution Licensee on account of controllable factors shall be shared equally between Licensee and Consumers:Provided that the mechanism for sharing of gains or losses on account of controllable factors for a Generating Company shall be as specified in the prevalent CERC Tariff Regulations.15. Determination of Tariff.
- 15.1 The proceedings to be held by the Commission for determination of tariff shall be in accordance with the Joint Electricity Regulatory Commission (Conduct of Business) Regulations, 2009, as amended from time to time.16. Filing Procedure.
- 16.1 The Applicant shall provide, as part of its Petition to the Commission, in such formats as specified by the Commission from time to time, full details of its calculation of the Aggregate Revenue Requirement and Expected Revenue from Tariff and Charges, and thereafter, shall furnish such further information or particulars or documents as the Commission may reasonably require to assess such calculation:Provided that the Petition shall be accompanied by, where relevant, tariff and charges revision proposal showing category-wise tariff for recovery of Aggregate Revenue Requirement for the respective Year of the Control Period:Provided further that the Commission may specify additional/alternative formats for details to be submitted by the Applicant, from time to time, as it may reasonably require for assessing the Aggregate Revenue Requirement and for determining the tariff.17. Tariff Order.
- 17.1 The Commission shall, within one hundred and twenty (120) Days from the date of acceptance of the complete Petition, subject to petitioner providing information subsequently sought by the Commission in a timely manner and after considering all suggestions and objections received from the various stakeholders:(a)issue a Tariff Order; or(b)reject the application for reasons to be recorded in writing if such application is not in accordance with the provisions of the Act and Regulations made thereunder or the provisions of any other law for the time being in force:Provided that an Applicant shall be given a reasonable opportunity of being heard before rejecting its application.18. Adherence to Tariff Order.
- 18.1 No tariff or part of any tariff may ordinarily be amended more frequently than once in a Year, except in respect of any changes expressly permitted under the terms of any fuel surcharge formula as may be specified.19. Annual determination of tariff.
- 19.1 The Commission shall determine the tariff of a Generating Company, Transmission Licensee and Distribution Licensee covered under a Multi Year Tariff framework for each Year during the Control Period, in accordance with timelines specified in Regulation 17, having regard to the following:20. Subsidy Mechanism.
- 20.1 If the Government requires to grant any subsidy to any Consumer or class of Consumers in the tariff determined by the Commission, the Government shall, notwithstanding any direction which may be given under Section 108 of the Act, pay in advance the amount to compensate the Distribution Licensee/person affected by the grant of subsidy, as a condition for the Licensee or any other person concerned to implement the subsidy provided for by the Government, in the manner specified in these Regulations:Provided that no such direction of the Government shall be operative if the payment is not made in accordance with the provisions contained in these Regulations, and the tariff fixed by the Commission shall be applicable from the date of issue of orders by the Commission in this regard.Chapter 3
Financial Principles
21. Financial Principles for a Generating Company.
- 21.1 The Capital Cost for a Generating Company shall be determined by the Commission, guided by the relevant provisions of the prevalent CERC Tariff Regulations governing generation of electricity, subject to prudence check. The Capital Cost so determined shall form the basis of determination of tariff for Existing Projects and New Projects.22. Financial Principles for Transmission and Distribution Business.
- 22.1 The financial principles specified in the subsequent sections of this Chapter of these Regulations shall be applicable to the Transmission and Distribution Licensee.23. Capital Cost.
- 23.1 Capital cost for a capital investment Project shall include:(a)the expenditure incurred or projected to be incurred, including interest during construction and financing charges, as admitted by the Commission after prudence check;(b)capitalised initial spares subject to the ceiling rates specified in this Regulation;(c)the expenses incurred by the Licensee on obtaining right of way, as admitted by the Commission after prudence check;(d)additional capitalisation determined in accordance with Regulation 24;(e)any gain or loss on account of foreign exchange rate variation pertaining to the loan amount availed up to the Date of Commercial Operation, as admitted by the Commission after prudence check:Provided that any gain or loss on account of foreign exchange rate variation pertaining to the loan amount availed up to the Date of Commercial Operation shall be adjusted only against the debt component of the capital cost:Provided further that the capital cost of the assets forming part of the Project but not put to use or not in use, shall be excluded from the capital cost:Provided also that the Licensee shall submit documentary evidence in support of its claim of assets being put to use.| (a) | Transmission Line & Distribution Line | 1.0% |
| (b) | Transmission Sub-station & DistributionSub-station (Green Field) | 4.0% |
| (c) | Transmission Sub-station (Brown Field) | 6.0% |
| (d) | Series Compensation devices and HVDC Station | 4.0% |
| (e) | Gas Insulated Sub-station (GIS) | 5.0% |
| (f) | Communication System | 3.5% |
24. Additional Capitalisation.
- 24.1 The capital expenditure, actually incurred or projected to be incurred, in respect of New Project or an ExistingProject, on the following counts within the original scope of work, after the Date of Commercial Operation and up to the Cut-off Date may be admitted by the Commission, subject to prudence check:(i)Undischarged liabilities recognized to be payable at a future date;(ii)Works deferred for execution;(iii)Procurement of initial capital spares within the original scope of work, in accordance with the provisions of Regulation 23.6;(iv)Liabilities to meet award of arbitration or for compliance of the order or decree of a court of law; and(v)Change in law or compliance with any existing law:Provided that the details of works asset wise/work wise included in the original scope of work along with estimates of expenditure, liabilities recognized to be payable at a future date and the works deferred for execution shall be submitted along with the application for determination of tariff.25. Consumer Contribution, Deposit Work, Grant and Capital Subsidy.
- 25.1 The works carried out by the Transmission Licensee and Distribution Licensee after obtaining a part or all of the funds from the users shall be classified as Deposit Works;26. Debt to Equity Ratio.
- 26.1 In case of Existing Projects, debt to equity ratio allowed by the Commission for determination of tariff for the period ending March 31, 2018 shall be considered:Provided that in case of retirement or replacement or De-capitalisation of the assets, the equity capital approved as mentioned above, shall be reduced to the extent of 30% (or actual equity component based on documentary evidence, if it is lower than 30%) of the original cost of such assets:Provided further that in case of retirement or replacement or De-capitalisation of the assets, the debt capital approved as mentioned above, shall be reduced to the extent of outstanding debt component based on documentary evidence, or the normative loan component, as the case may be, of the original cost of such assets.27. Return on Equity.
- 27.1 Return on equity shall be computed on the paid up equity capital determined in accordance with Regulation 26 for the assets put to use for the Transmission Licensee and shall be allowed in accordance with the prevalent CERC Tariff Regulations for transmission system.28. Interest on Loan.
- 28.1 The loans arrived at in the manner indicated in Regulation 26 on the assets put to use, shall be considered as gross normative loan for calculation of interest on the loan:Provided that interest and finance charges on capital works in progress shall be excluded:Provided further that in case of De-capitalisation or retirement or replacement of assets, the loan capital shall be reduced to the extent of outstanding loan component of the original cost of the de-capitalised or retired or replaced assets, based on documentary evidence.29. Foreign Exchange Rate Variation.
- 29.1 The Licensee may hedge foreign exchange exposure in respect of the interest on foreign currency loan and repayment of foreign loan acquired for the transmission system or distribution system, in part or in full at its discretion.30. Depreciation.
- 30.1 The value base for the purpose of depreciation shall be the capital cost of the asset admitted by the Commission:Provided that the depreciation shall be allowed after reducing the approved original cost of the retired or replaced or decapitalized assets:Provided also that the no depreciation shall be allowed on the assets financed through consumer contribution, deposit work, capital subsidy or grant.31. Interest on Working Capital.
- 31.1 The norms for working capital for Transmission Licensee shall be as specified in Chapter 5 of these Regulations.32. Tax on Income.
- 32.1 The treatment of tax on income for a Transmission Licensee shall be in accordance with the prevalent CERC Tariff Regulations.33. Rebate.
- 33.1 The rebate to be provided by a Generating Company or Transmission Licensee to a Distribution Licensee for early payment of bills shall be in accordance with the prevalent CERC Tariff Regulations.34. Late Payment Surcharge.
- 34.1 In case the payment of bills of transmission charges by a beneficiary is delayed beyond a period as specified in the prevalent CERC Tariff Regulations, a late payment surcharge shall be levied on the billed amount in accordance with the prevalent CERC Tariff Regulations.35. Income from Other Business.
- 35.1 Where the Transmission Licensee or Distribution Licensee is engaged in any Other Business, the income from such business shall be calculated in accordance with the Joint Electricity Regulatory Commission for Goa & Union Territories (Treatment of Other Business of Transmission Licensees and Distribution Licensees) Regulations, 2009, as amended from time to time and shall be deducted from the Aggregate Revenue Requirement of the Licensee:Provided that the Licensee shall follow a reasonable basis for allocation of all joint and common costs between the transmission or distribution business and the Other Business and prepare Accounting Statements in accordance with Joint Electricity Regulatory Commission for Goa & Union Territories (Treatment of Other Business of Transmission Licensees and Distribution Licensees) Regulations, 2009, as amended from time to time and submit to the Commission along with its application for determination of tariff:Provided further that where the sum total of the direct and indirect costs of such Other Business exceeds the revenues from such Other Business, no amount shall be allowed to be added to the Aggregate Revenue Requirement of the Licensee on account of such Other Business.Chapter 4
Generation
36. Applicability.
- 36.1 The Regulations contained in this Chapter shall apply for determination of tariff for supply of electricity to Distribution Licensee from a Generating Station located in the State.37. Components of Tariff.
- 37.1 The Aggregate Revenue Requirement for a Generation Company shall comprise of the following components:(a)Return on Equity;(b)Interest and finance charges on Loan;(c)Depreciation;(d)Interest on Working Capital;(e)Operation and maintenance expenses;(f)Income tax.38. Norms of Operation.
- 38.1 The norms of operation for a Generating Station including Normative annual plant availability factor (NAPAF), Normative Annual Plant Load Factor (NAPLF), Gross Station heat Rate, Auxiliary Consumption etc. shall be in accordance with the prevalent CERC Tariff Regulations governing generation of electricity.Chapter 5
Intra-State Transmission
39. Applicability.
- 39.1 The Regulations contained in this Chapter shall apply for determination of tariff for access and use of the intra- State transmission system in the States.40. Components of Tariff.
- 40.1 The annual transmission charges for each Financial Year of the Control Period shall provide for the recovery of the Aggregate Revenue Requirement of the Transmission Licensee for the respective Financial Year of the Control Period, as reduced by the amount of Non-Tariff Income, income from Other Business and short-term transmission charges of the previous Year in accordance with Joint Electricity Regulatory Commission for the State of Goa and Union Territories (Connectivity and Open Access in Intra-State Transmission and Distribution) Regulations, 2017, as amended from time to time:Provided that in case of competitively awarded transmission system projects in pursuance of Section 63 of the Act and in accordance with guidelines for competitive bidding for transmission, the annual transmission charges shall be as per the annual Transmission Service Charges (TSC) quoted by such competitively awarded transmission projects.41. Operation and Maintenance (O&M) expenses for Transmission Licensees.
- 41.1 Operation and Maintenance (O&M) expenses shall comprise of the following:(a)Employee expenses - salaries, wages, pension contribution and other employee costs;(b)Administrative and General expenses including insurance charges if any; and(c)Repairs and Maintenance expenses.42. Norms of Working Capital for Transmission Licensee.
- 42.1 The Transmission Licensee shall be allowed interest on the estimated level of working capital for the Financial Year computed in accordance with prevalent CERC Tariff Regulations.43. Non-Tariff Income.
- 43.1 The amount of Non-Tariff Income relating to the transmission business as approved by the Commission shall be deducted from the Aggregate Revenue Requirement in determining annual transmission charges of the Transmission Licensee:Provided that the Transmission Licensee shall submit full details of its forecast of Non-Tariff Income to the Commission along with its application for determination of Aggregate Revenue Requirement.44. Norms of Operations for Transmission Licensee.
- 44.1 The norms of operations for a Transmission Licensee shall be applicable as specified in the prevalent CERC Tariff Regulations.Provided that sharing of incentive, if any with the beneficiaries for exceeding the norms of operations shall be in accordance with provisions of prevalent CERC Tariff Regulations.45. Transmission Loss.
- 45.1 The energy losses in the transmission system of the Transmission Licensee, as determined by the State Load Despatch Centre, shall be borne by the Transmission System Users in proportion to their usage of the intra- State transmission system.46. Sharing of charges for Intra-State Transmission Network.
- 46.1 The Aggregate Revenue Requirement of the Transmission Licensee, as approved by the Commission, shall be shared by all long-term users and medium-term users of the transmission system on a monthly basis in the ratio of their respective Allotted Transmission Capacity to the total Allotted Transmission Capacity, in accordance with the following formula:ATCn = (Transmission ARR / 12) x (CCn/ SCC)Where,ATCn = annual transmission charges payable by the nth long-term user or medium-term user of the transmission system;Transmission ARR = Aggregate Revenue Requirement of the Transmission Licensee, determined in accordance with these Regulations;CCn = Allotted Transmission Capacity by the nth long-term user or medium-term user of the transmission system;SCC = sum of Allotted Transmission Capacity by all long-term users and medium-term users of the transmission system:Provided that the ATCn shall be payable on a monthly basis by each long-term user or medium-term user of the transmission system and shall be collected by the State Transmission Utility (STU).47. Consequential Impact of any Government of India Scheme.
- 47.1 The consequential impact of any Government of India scheme for waiver/reduction of transmission charges, incentives, and losses for any entity/ies, on the transmission charges payable by the other entities, shall be addressed through separate Orders to be issued by the Commission from time to time.Chapter 6
Distribution Wires Business
48. Separation of Accounts of Distribution Licensee.
- 48.1 Every Distribution Licensee shall segregate accounts for Distribution Wires Business and Retail Supply Business and shall prepare an Allocation Statement. The wheeling charges pertaining to Distribution Wires Business of the Distribution Licensee shall be determined by the Commission on the basis of these segregated accounts:Provided that in case complete accounting segregation has not been done, the following Allocation Statement shall be applicable:Table 1: Allocation Statement for segregation of Distribution Wires Business and Retail Supply Business| Particulars | Wires Business (%) | Retail Supply Business (%) |
| Power Purchase Expenses | 0% | 100% |
| Inter-State Transmission Charges | 0% | 100% |
| Intra-State Transmission Charges | 0% | 100% |
| Employee Expenses | 40% | 60% |
| Administration & General Expenses | 50% | 50% |
| Repair & Maintenance Expenses | 90% | 10% |
| Capital Cost | 90% | 10% |
| Depreciation | 90% | 10% |
| Interest on Long-term Loan Capital | 90% | 10% |
| Interest on working capital and on consumersecurity deposits | 10% | 90% |
| Bad Debts Written off | 0% | 100% |
| Income Tax | 90% | 10% |
| Non-Tariff Income | 10% | 90% |
| Income from Other Business | 50% | 50% |
49. Applicability.
- 49.1 The Regulations contained in this Chapter shall apply to the determination of wheeling charges for usage of distribution wires of a Distribution Licensee by a distribution system user, other than retail supply Consumers.50. Aggregate Revenue Requirement for Distribution Wires Business.
- 50.1 The wheeling charges for Distribution Wires Business of the Distribution Licensee shall provide for the recovery of the Aggregate Revenue Requirement, which shall comprise of the following:51. Operation and Maintenance (O&M) expenses for Distribution Wires Business.
- 51.1 The Operation and Maintenance expenses for the Distribution Wires Business shall be computed in accordance with this Regulation.52. Norms of Working Capital for Distribution Wires Business.
- 52.1 The Distribution Licensee shall be allowed interest on the estimated level of working capital for the Distribution Wires Business for the Financial Year, computed as follows:53. Non-Tariff Income.
- 53.1 The amount of Non-Tariff Income relating to the Distribution Wires Business as approved by the Commission shall be deducted from the Aggregate Revenue Requirement in determining the wheeling charges of Distribution Wires Business of the Distribution Licensee:Provided that the Distribution Licensee shall submit full details of its forecast of Non-Tariff Income to the Commission along with its application for determination of wheeling charges.54. Determination of Wheeling Charges.
- 54.1 The Commission shall specify the Wheeling Charge of Distribution Wires Business of the Distribution Licensee in its Order passed under sub-section (3) of Section 64 of the Act:Provided that the revenue from wheeling charges paid by the distribution system users other than the retail Consumers under the above proviso shall be used to reduce the Aggregate Revenue Requirement of the Distribution Wires Business to be recovered from the retail Consumers of the concerned Distribution Licensee, in accordance with Joint Electricity Regulatory Commission for the State of Goa and Union Territories (Connectivity and Open Access in Intra-State Transmission and Distribution) Regulations, 2017, as amended from time to time.55. Wheeling Losses.
- 55.1 The Distribution Licensee shall be allowed to recover, in kind, the approved level of wheeling losses arising from the operation of the distribution system, as stipulated in the respective Tariff Order.Chapter 7
Retail Supply of Electricity
56. Applicability.
- 56.1 These Regulations shall apply to determination of tariff for retail supply of electricity by a Distribution Licensee to its Consumers.57. Aggregate Revenue Requirement for Retail Supply Business.
- 57.1 The tariff for retail supply of the Distribution Licensee shall provide for the recovery of the Aggregate Revenue Requirement of the Retail Supply Business for the respective Years of the Control Period, as approved by the Commission and comprising the following components:(a)Cost of own power generation and power purchase expenses from other sources;(b)Inter-State transmission charges;(c)Intra-State transmission charges;(d)SLDC fees and charges;(e)Balance Aggregate Revenue Requirement for Distribution Wires Business, as determined under Chapter 6 of these Regulations, after deducting income from wheeling charges payable by distribution system users other than the retail Consumers getting electricity supply from the same Distribution Licensee in accordance with Joint Electricity Regulatory Commission for the State of Goa and Union Territories (Connectivity and Open Access in Intra-State Transmission and Distribution) Regulations, 2017, as amended from time to time;(f)Provision for bad and doubtful debts;(g)Return on Equity capital;(h)Operation and Maintenance Expenses;(i)Depreciation;(j)Interest and finance charges on Loan Capital;(k)Interest on Working Capital;(l)Interest on consumer security deposits;(m)Income Tax;Less(n)Non-Tariff income;(o)Income from Other Business, to the extent specified in these Regulations;(p)Receipts on account of Cross-Subsidy Surcharge;(q)Receipts on account of Additional Surcharge:Provided that Depreciation, Interest on Loan Capital, Interest on Working Capital, Interest on consumer security deposits, Contribution to Contingency Reserves, Return on Equity, and Income Tax for Retail Supply Business shall be allowed in accordance with the provisions specified in Chapter 3 of these Regulations:Provided further that prior period income/expenses shall be allowed by the Commission at the time of truing up based on audited accounts, on a case-to-case basis, subject to prudence check:Provided also that all penalties and compensation payable by the Licensee to any party for failure to meet any Standards of Performance or for damages, as a consequence of the orders of the Commission, Courts, Consumer Grievance Redressal Forum, and Ombudsman, etc. or penalty imposed by Commission on Licensee for non-compliance with Renewable Purchase Obligations in accordance with Joint Electricity Regulatory Commission for state of Goa & Union Territories (Procurement of Renewable energy) Regulations, 2010, as amended from time to time shall not be allowed to be recovered through the Aggregate Revenue Requirement:Provided also that the Distribution Licensee shall maintain separate details of such penalties and compensation paid or payable by the Licensee, if any, and shall submit them to the Commission along with its Petition.58. Cost of Power Purchase.
- 58.1 The Distribution Licensee shall be allowed to recover the cost of power generated by the Generating Stations owned by it or purchased from approved sources for supply to Consumers based on the power procurement plan of the Distribution Licensee, approved by the Commission.59. Transmission Charges.
- 59.1 The Distribution Licensee shall be allowed to recover transmission charges payable for access to and use of the inter-state and intra-State transmission system in accordance with the tariff approved by the Commission under Chapter 5of these Regulations.60. Operation and Maintenance (O&M) expenses for Retail Supply Business.
- 60.1 The Operation and Maintenance Expenses for the Retail Supply Business shall be computed in accordance with this Regulation.61. SLDC Fees & Charges.
- 61.1 The Distribution Licensee shall be allowed to recover SLDC fees and charges payable to SLDC in accordance with the tariff approved by the Commission.62. Provision for bad and doubtful debts.
- 62.1 The Commission may allow bad debts written off as a pass through in the Aggregate Revenue Requirement, based on the trend of write off of bad debts in the previous years, subject to prudence check:Provided that the Commission shall true up the bad debts written off in the Aggregate Revenue Requirement, based on the actual write off of bad debts excluding delayed payment charges waived off, if any, during the year, subject to prudence check:Provided also that the provision for bad and doubtful debts shall be limited to 1% of the annual Revenue Requirement of the Distribution Licensee:Provided further that if subsequent to the write off of a particular bad debt, revenue is realised from such bad debt, the same shall be included as an uncontrollable item under the Non-Tariff Income of the year in which such revenue is realised.63. Norms of Working Capital for Retail Supply Business.
- 63.1 The Distribution Licensee shall be allowed interest on the estimated level of working capital for the Retail Supply Business for the Financial Year, computed as follows:64. Non-Tariff Income.
- 64.1 The amount of Non-Tariff Income relating to the retail supply of electricity as approved by the Commission shall be deducted from the Aggregate Revenue Requirement in calculating the tariff for retail supply of electricity by the Distribution Licensee:Provided that the Distribution Licensee shall submit full details of its forecast of Non-Tariff Income to the Commission along with its application for determination of tariff.65. Receipts on account of Cross-Subsidy Surcharge and Additional Surcharge.
- 65.1 The Cross-Subsidy Surcharge received by the Distribution Licensee in accordance with the Joint Electricity Regulatory Commission for the State of Goa and Union Territories (Connectivity and Open Access in Intra- State Transmission and Distribution) Regulations, 2017, as amended from time to time, at the rate approved by the Commission shall be deducted from the Aggregate Revenue Requirement, at the time of truing up.66. Distribution Losses.
- 66.1 The Distribution Licensee shall recover the approved level of distribution losses arising from the Retail Supply of electricity.67. Determination of Tariff.
- 67.1 The Commission may categorize Consumers on the basis of their load factor, power factor, voltage, total consumption of electricity during any specified period or the time at which the supply is required or the geographical position of any area, the nature of supply and the purpose for which the supply is required and any other factor as considered appropriate by the Commission.Chapter 8
Miscellaneous
68. Saving of Inherent Power of the Commission.
- 68.1 Nothing in these Regulations shall be deemed to limit or otherwise affect the inherent power of the Commission to make such orders as may be necessary for ends of justice or to prevent the abuse of the process of the Commission.69. Issue of Orders and Practice Directions.
- 69.1 Subject to the provision of the Act and these Regulations, the Commission may, from time to time, issue Orders and Practice directions with regard to the implementation of these Regulations and procedure to be followed on various matters.70. Power to amend.
- 70.1 The Commission may, at any time, vary, alter, modify or amend any provisions of these Regulations following the due process of law.71. Power to remove difficulties.
- 71.1 If any difficulty arises in giving effect to the provisions of these Regulations, the Commission may, by general or specific order, make such provisions not inconsistent with the provisions of the Act, as may appear to be necessary for removing the difficulty.72. Power of Relaxation.
- 72.1 The Commission, for reasons to be recorded in writing, may relax any of the provisions of these Regulations on its own motion or on an application made before it by an interested person.73. Interpretation.
- 73.1 If a question arises relating to the interpretation of any provision of these Regulations, the decision of the Commission shall be final.74. Repeal.
- 74.1 The Joint Electricity Regulatory Commission for the State of Goa and Union Territories (Multi Year Distribution Tariff) Regulations, 2014 and JERC (Terms and Conditions for Determination of Tariff) Regulations, 2009shall stand repealed from the date of coming into force of these Regulations and any reference to these Regulations in any of the Regulations, standards, codes or procedures of the Joint Electricity Regulatory Commission shall be deemed to be replaced by the Joint Electricity Regulatory Commission for the State of Goa and Union Territories (Generation, Transmission and Distribution Multi Year Tariff) Regulations, 2018.| S. No | Asset Class | Useful Life (Years) | Rate (%) |
| 1 | Land owned under full title | Infinity | 0 |
| 2 | Land held under lease | ||
| (A) | For investment in land | Period of lease or the period remainingunexpired on the assignment of the lease | 0 |
| (B) | For cost of clearing site | Period of lease remaining unexpired at the dateof clearing the site | 0 |
| 3 | Assets purchased new | ||
| (A) | Buildings and civil engineering works of apermanent character, not mentioned above: | ||
| (i) | Offices and showrooms | 50 | 1.80 |
| (ii) | Temporary erection such as wooden structures | 5 | 18.00 |
| (iii) | Roads other than kutcha roads | 50 | 1.80 |
| (iv) | Others | 50 | 1.80 |
| (B) | Transformers, transformer (kiosk) substationequipment & other fixed apparatus (including plantfoundations) | ||
| (i) | Transformers (including foundations) having arating of 100 kilo volt amperes (kVA) and over | 25 | 3.60 |
| (ii) | Others | 25 | 3.60 |
| (C) | Switchgear, including cable connections | 25 | 3.60 |
| (D) | Lightning arrestors: | ||
| (i) | Station type | 25 | 3.60 |
| (ii) | Pole type | 15 | 6.00 |
| (iii) | Synchronous condenser | 35 | 2.57 |
| (E) | Batteries | 5 | 18.00 |
| (F) | Underground cable including joint boxes anddisconnected boxes | 35 | 2.57 |
| (G) | Cable duct system | 50 | 1.80 |
| (H) | Overhead lines including supports: | ||
| (i) | Lines on fabricated steel operating at nominalvoltages higher than 66 kV | 35 | 2.57 |
| (ii) | Lines on steel supports operating at nominalvoltages higher than 11 kV but not exceeding 66 kV | 25 | 3.60 |
| (iii) | Lines on steel or reinforced concrete supports | 25 | 3.60 |
| (iv) | Lines on treated wood supports | 25 | 3.60 |
| (I) | Meters | ||
| Electro Mechanical | 15 | 6.00 | |
| Electronic/Smart Meters | 10 | 9.00 | |
| (J) | Self propelled vehicles | 5 | 18.00 |
| (K) | Air conditioning plants: | ||
| (i) | Static | 15 | 6.00 |
| (ii) | Portable | 5 | 18.00 |
| (L) | Others | ||
| (i) | Office furniture and fittings | 15 | 6.00 |
| (ii) | Office equipment | 15 | 6.00 |
| (iii) | Internal wirings including fittings andapparatus | 15 | 6.00 |
| (iv) | Street Light fittings | 15 | 6.00 |
| (M) | Apparatus let on hire: | ||
| (i) | Other than motors | 5 | 18.00 |
| (ii) | Motors | 15 | 6.00 |
| (N) | Communication equipment | ||
| (i) | Radio and higher frequency carrier systems | 15 | 6.00 |
| (ii) | Telephone lines and telephones | 15 | 6.00 |
| (O) | Assets purchased in second hand and assets nototherwise provided for in the schedule | such reasonable period as the Commissiondetermines in each case having regard to the nature, age andconditions of assets at the time of its acquisition by thecurrent owner |