Section 7(7)(i) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014
(i)the Commission may grant tariff upto 90% of the annual fixed charges claimed in respect of the transmission system or element thereof based on the management certificate regarding the capital cost for the purpose of inclusion in the POC charges in accordance with the CERC (Sharing of Inter State Transmission charges and losses), Regulation, 2010 as amended from time to time: