Union of India - Subsection

Section 7(7) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2014

(7)In case of the new projects, the generating company or the transmission licensee, as the case may be, may be allowed tariff by the Commission based on the projected capital expenditure from the anticipated COD in accordance with Regulation 6 of these regulations:Provided that :
(i)the Commission may grant tariff upto 90% of the annual fixed charges claimed in respect of the transmission system or element thereof based on the management certificate regarding the capital cost for the purpose of inclusion in the POC charges in accordance with the CERC (Sharing of Inter State Transmission charges and losses), Regulation, 2010 as amended from time to time:
(ii)if the date of commercial operation is delayed beyond 180 days from the date of issue of tariff order in terms of clause (6) of this regulation, the tariff granted shall be deemed to have been withdrawn and the generating company or the transmission licensee shall be required to file a fresh application for determination of tariff after the date of commercial operation of the project:
(iii)where the capital cost considered in tariff by the Commission on the basis of projected capital cost as on COD or the projected additional capital expenditure exceeds the actual capital cost incurred on year to year basis by more than 5%, the generating company or the transmission licensee shall refund to the beneficiaries or the long term transmission customers /DICs as the case may be, the excess tariff recovered corresponding to excess capital cost, as approved by the Commission alongwith interest at 1.20 times of the bank rate as prevalent on 1st April of respective year:
(iv)where the capital cost considered in tariff by the Commission on the basis of projected capital cost as on COD or the projected additional capital expenditure falls short of the actual capital cost incurred on year to year basis by more than 5%, the generating company or the transmission licensee shall be entitled to recover from the beneficiaries or the long term transmission customers /DICs as the case may be, the shortfall in tariff corresponding to reduction in capital cost, as approved by the Commission alongwith interest at 0.80 times of bank rate as prevalent on 1st April of respective year.