State of Tamilnadu - Subsection

Section 5(13) in The Tamil Nadu Electricity Supply Code, 2004

(13)[ Excess demand charge and excess energy charge during Restriction and Control of supply:
(i)The maximum demand charges for HT supply shall be based on the actual recorded demand at the point of supply or at 90% of the demand quota as fixed from time to time through restriction and control measures whichever is higher. In case the maximum recorded demand is in excess of the quota fixed, the demand in excess of the quota fixed shall be charged at rates specified by the Commission from time to time.
(ii)The energy consumption over and above the energy quota fixed shall be charged at the rates specified by the Commission from time to time in respect of such class of consumers upon whom the restriction and control measures apply.
(iii)The services which draw electricity from TNEB Grid for using welding sets during the restricted hours shall be charged at the rates specified by the Commission from time to time.]