State of Rajasthan - Subsection

Section 44(4) in Rajasthan Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) Regulations, 2009

(4)A generating company may make petition for determination of provisional tariff in advance of the anticipated date of commissioning of Unit or Stage or Generating Station as a whole, as the case may be, based on the capital expenditure actually incurred up to the date of making the petition or a date prior to making of the petition, duly audited and certified by the statutory auditors and the provisional tariff shall be charged from the date of commercial operation of such Unit or Stage or Generating Station, as the case may be.