State of Rajasthan - Section

Section 44 in Rajasthan Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) Regulations, 2009

44. Petition for determination of generation tariff (thermal).

(1)A generating company may file petition for determination of tariff for supply of electricity to distribution licensees complying with the provisions of Part II of these Regulations.
(2)Tariff in respect of a generating station under these Regulations may be determined stage-wise, Unit-wise or for the whole generating station. The terms and conditions for determination of tariff for generating stations specified in this Part shall apply in like manner to stages or Units, as the case may be, as to generating stations.
(3)Where the tariff is being determined for stage or Unit of a generating station, the Generating Company shall adopt a reasonable basis for allocation of capital cost relating to common facilities and allocation of joint and common costs across all stages or Units, as the case may be:Provided that the Generating Company shall maintain an Allocation Statement providing the basis for allocation of such costs, and submit such statement to the Commission along with the application for determination of tariff.
(4)A generating company may make petition for determination of provisional tariff in advance of the anticipated date of commissioning of Unit or Stage or Generating Station as a whole, as the case may be, based on the capital expenditure actually incurred up to the date of making the petition or a date prior to making of the petition, duly audited and certified by the statutory auditors and the provisional tariff shall be charged from the date of commercial operation of such Unit or Stage or Generating Station, as the case may be.
(5)A generating company shall make a fresh petition as per these Regulations, for determination of final tariff based on actual capital expenditure incurred up to the date of commercial operation of the generating station duly certified by the statutory auditors based on annual audited accounts.
(6)Any difference in provisional tariff and the final tariff determined by the Commission and not attributable to the generating company may be adjusted in the tariff for the following year as directed by the Commission.