39. Operation and maintenance expenses.
| Sr. No. | Category of Project | Annual O&M expenses Rupees in Lac per MW |
| (i) | Above 100 kW to 2 MW capacity | 33 |
| (ii) | Above 2 MW to 5 MW capacity | 29 |
| (iii) | Above 5 MW to 25 MW capacity | 24 |