Section 39 in Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2017

39. Operation and maintenance expenses.

(1)Normative annual O&M expenses for the control period shall be as follows:-
Sr. No. Category of Project Annual O&M expenses Rupees in Lac per MW
(i) Above 100 kW to 2 MW capacity 33
(ii) Above 2 MW to 5 MW capacity 29
(iii) Above 5 MW to 25 MW capacity 24
Chapter-VI Other Parameters